Explosive ordnance surveying for marshalling and stabling yards

For facility designers, operators and site management, railway yards, switches, operational areas, cable routes and deep foundations are divided by actual ground disturbance and construction stage. FONTANA-EOD reviews ordnance evidence and survey conditions for the proposed work. Submit the facility drawing, list of ground disturbances and demolition sequence so that investigations and records can be coordinated for each working volume.

Divide the site into subareas

Distinguish tracks, switches and operational zones.

Record sources of interference

Identify installations, utilities and track superstructure.

Coordinate the demolition sequence

Coordinate demolition and follow-up investigation.

Other railway and route projects

Before redevelopment and extension of the facility

Clarify investigation requirements for track and operational areas

In marshalling and stabling yards, explosive ordnance investigation is related to the specific track, installation or structural section. Depth of ground disturbance, existing investigations and interference from rails, cables, earthing systems or foundations determine the suitable approach. Unresolved areas and results are documented so that they remain assigned to individual construction stages and possessions.

Project references

Selected project examples

Typical working volumes

Which subareas need their own explosive ordnance investigation

Marshalling and stabling yards are divided by technical interference, access, construction stage and depth of ground disturbance. Each project area has its own technical task rather than being covered by a general conclusion for the whole site.

Person with a tablet beside an open cable duct along a railway.

Track and switch areas

Switches, rails, fastenings, cables and earthing systems create dense technical interference. Track-superstructure works, formation improvement and drainage may also disturb depths not previously assessed.

Investigation is divided by track, switch area, construction stage, working width and depth. Zones where data cannot be interpreted receive a separate follow-up measure.

The service specification records survey feasibility, the planned demolition sequence and the technical assessment needed before the next operating state.

Assess the track and switch area
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Stabling and preparation tracks

Long groups of tracks are often redeveloped, extended or provided with new drainage section by section. Access and operating conditions may differ considerably between construction stages.

Survey areas, excavation areas and deep points are linked to the respective track group and construction stage so that handovers between sections remain clear.

For long track groups, handover points and adjoining zones not investigated are marked so that later construction stages can clearly take over the documented section.

Define the technical subdivisions of stabling tracks
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Workshop, washing and service areas

Workshop access routes, washing and cleaning installations, utility connections, pits and technical foundations create additional construction and utility structures. Earlier alterations may further change ground conditions.

As-built drawings and current construction geometry are related to one another. Open areas, excavations and individual foundations have separate investigation tasks.

For contaminated materials or materials subject to waste legislation, explosive ordnance investigation, contaminated-land assessment and soil management remain technically separate tasks coordinated in time.

Investigate the operational area and excavations
Person with a tablet beside an open cable duct along a railway.

Cables, drainage and chambers

Cable troughs, utility trenches, drainage, chambers and crossings often run alongside tracks or cross several operational zones. Existing and new installations must remain spatially distinguishable.

Alignment, width, depth, chambers and crossing points define the investigation geometry. Dense technical interference is documented as a methodological constraint.

Crossings and chambers receive their own identifiers so that survey data, excavation sections and later changes to utility routes can be updated consistently.

Investigate cable and drainage routes
Person with a tablet beside an open cable duct along a railway.

Masts, signals and technical foundations

Overhead line, lighting and signal masts, together with equipment foundations, create numerous deep point ground disturbances. Their position may change during construction design.

Point lists include coordinates, foundation geometry, design depth and installation method. Relocated or additional points are checked against the existing investigation volume.

An area survey can be used only within its demonstrated range. If it does not cover the proposed foundation volume, the scope and geometry of additional investigations are specified before procurement.

Investigate mast and foundation positions
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Demolition and progressive access

Existing tracks, ballast bodies, structures and technical installations may restrict preliminary investigation. Demolition opens up new areas and depths that were previously inaccessible.

Necessary investigations and protective measures are specified before ground disturbance during demolition. Areas accessible afterwards receive the additional investigation required for the further work planned there. The suitability of explosive ordnance surveying during construction is assessed for the respective excavation. Each stage receives its own investigation records.

For each area newly accessible after demolition, the need for a repeat area survey, point investigation or layer-by-layer monitoring is determined.

Coordinate demolition and excavation
Design and construction progress

Which technical assessment suits each project stage

The appropriate next step depends on the design stage, access, ground-disturbance geometry and records required.

Early site and redevelopment planning

For options, site development or fundamental reorganisation, the first step is to review the historical indications, earlier documents and as-built information available for the planned construction sections.

The result provides a spatial basis for estimating costs, programme planning and later technical investigations.

Early area boundaries can be updated later but must be checked against the approved construction and track drawing before construction.

Clarify historical suspicion indicators

Construction stages during ongoing operations

Where track groups are closed and reopened section by section, investigation volumes, handovers and unresolved zones must be updated clearly.

Operational work authorisation and explosive ordnance investigation status are documented separately.

Subarea handover states the investigation status, remaining limitations and conditions of use by the subsequent trade.

Structure construction stages and records

Area investigation in an interference environment

Open adjoining areas may have different survey conditions from switch areas, workshop zones or areas with dense infrastructure. Methods are not specified as a blanket solution for the whole installation.

The survey objective, target object, ground conditions, track superstructure and sources of technical interference determine the appropriate combination of methods.

Where surfaces and installation conditions vary, trial surveys or separate subarea concepts may be needed before quantities and dates are agreed as binding.

Select area-survey methods

Deep point and linear ground disturbance

Masts, piles, sheet piles, signals, lighting, shafts and deep ground investigations require investigation of the future working volume.

Coordinates, design depth, diameter and construction method are clearly specified before commissioning.

Replacement or alternative points are accepted only if they still provide technically sufficient coverage of the proposed foundation or working volume.

Prepare deep interventions

Areas that cannot be surveyed within an excavation

Rails, foundations, utilities or lack of access may limit preliminary investigation. These zones are identified spatially and are not assessed as being without anomalies.

The technical suitability of explosive ordnance surveying during construction for the planned excavation is assessed. If specified, excavation layers, stop points and responsibilities are defined in advance.

Before work begins, site management receives a clear procedure for deviations, additional excavation depths and areas revealed only during demolition.

Plan excavation monitoring

An anomaly or an actual find

A survey anomaly, an object causing technical interference and a suspicious object found must be distinguished technically.

Measurement anomalies are interpreted by specialists and may lead to additional investigation or controlled exposure. If a suspicious object is found, work stops, the immediate area is evacuated and the police are notified immediately.

The status of a suspected point remains traceable through surveying, exposure, assessment and handover under the same position identifier.

Clarify the findings and recovery process
Project situation, investigation and evidence

How the subarea and ground disturbance determine the next step

Initial conditions are related to the planned working volume. Each stage produces spatially limited records and identifies the measure required before the next construction or operating state.

Evidence of ordnance still incomplete

Historical indications, previous uses, indications of bombing or official statements are only partly available.

The historical assessment relates sources and areas with suspected ordnance to track groups, operational areas and proposed ground disturbance.

Further design can identify the subareas assessed reliably and locations where data or technical investigations are still missing.

Review sources and site information

Accessible open subarea

Adjoining areas, construction corridors or cleared zones can be investigated with a suitable surface method.

Survey data recorded with geographic coordinates, interference zones and technical limits form the basis for the next decision.

The subsequent assessment remains limited to the area actually covered and depth supported by the data; adjoining track or operational zones are not automatically assessed with it.

Plan the surface investigation

Point list for masts and foundations

The construction design includes coordinates and depths for numerous individual ground disturbances.

Depth investigation is related to the actual point and depth volume; later design relocations are checked again.

If a point moves, the new depth volume is checked for coverage within the existing investigation geometry or a need for additional investigation.

Have the point list technically reviewed

Area accessible only after demolition

Existing track superstructure, tracks or installations prevent adequate preliminary investigation.

After demolition, survey feasibility and investigation requirements are reassessed. Explosive ordnance surveying during construction is considered only where technically suitable for further excavation.

Before the next ground disturbance, the investigations and protective measures needed for the newly accessible working volume are technically clarified. Necessary technical investigations are carried out before the affected ground disturbance; planning a later follow-up measure alone does not demonstrate that a volume of ground has been investigated.

Plan the demolition sequence and follow-up investigation

Survey area with severe limitations

Technical interference or lack of access limits data quality.

Zones where data cannot be interpreted are mapped and remain visible in the project file as unresolved areas. Suitable additional investigations or changes to the construction sequence are specified for them.

A limited survey result is not treated as a finding without anomalies but as a documented reason for a different investigation or construction-sequence solution.

Coordinate limitations and further investigations

Confirmed point with suspected ordnance

An anomalous area is investigated further or exposed under controlled conditions.

Position, investigation, findings, handover and unresolved adjoining areas are documented in traceable records.

For each outstanding point, the measures list specifies the action, responsibility and date when the decision is needed.

Assess the suspected point and clearance objective
Project file and site management

Which documents site management needs for the investigated area

In large track and operational installations, documentation must remain clear across several construction stages, work packages and contractors. Drawings, survey data and reports therefore use the same identifiers for tracks, subareas and points. Investigation conditions and outstanding tasks are recorded for each area.

Installation and area references

The track group, switch, chainage, construction section, workshop zone, cable route, mast position or borehole position provides the spatial reference.

Drawing revisions and changes in construction stage are updated in traceable records.

Positional references are chosen so that external designers or later contractors can clearly locate the investigated area without local knowledge.

Basis for suspicion and assessment

Historical assessments, official information, known finds, earlier reports and project requirements are documented with their sources and scope.

Contradictions and missing appendices remain identifiable as unresolved points.

Sources are not merely collected but assessed for currency, spatial references and usability for the current construction stage.

Methods and working conditions

The survey principle, grid, line layout, investigation depth, borehole geometry, surface, ground conditions and sources of technical interference are described by section.

Later project participants can then also assess the technical scope of the conclusions.

Changes in parameters or equipment configuration between subareas are identified because they may affect comparability of results.

Measurements and findings

Raw data, interpreted data, anomaly lists, site drawings, field logs and exposure findings must use the same positional references and identifiers.

Automatic display does not replace specialist plausibility checks.

Anomaly and findings identifiers remain unchanged from the first interpretation to the final decision.

Areas that cannot be investigated

Track superstructure, utilities, structures, operations, lack of access or major sources of interference may limit investigations.

These areas are identified spatially and assigned a specific follow-up measure.

Each limitation is documented with the proposed response: later access, another method or adaptation of the construction sequence.

Section report and handover

The report describes investigation status, assessment limits, outstanding points and the next technical step for the respective subarea.

Partial handovers are later brought together into a consistent overall file.

The handover status also includes a list of outstanding measures and drawing revisions to which the assessment does not yet extend.

Verifiable project file

Which data belong together across construction stages and installation areas

Records are structured so that subareas, deep points, survey limits and later design changes can be clearly traced. Each file has project, section and investigation references. The project file also identifies the drawing revision assigned to an investigation, its assessment and the respective handover. A later construction section can then build on the documented status without adopting unchecked assumptions.

Drawing and revision register

Lists the site, track, cable, structural and point drawings used, with dates and revision status.

The report can therefore be traced back to the actual drawing revision.

Subarea and status drawing

Identifies investigated zones, those assessed with limitations, unresolved zones and areas not yet accessible.

Site management and operators can identify the status of each track or operational area.

Survey and borehole point register

Links survey lines, borehole positions, investigation depths, deviations and results through clear identifiers.

Relocated or additional points are updated separately.

Interference-zone and limitation drawing

Shows rails, utilities, foundations, installations and areas with insufficient survey feasibility.

Each limitation receives a technically suitable follow-up measure.

Anomaly and findings list

Brings together anomalies, further investigation, exposure, findings and final status.

Survey observations and actual finds remain clearly distinct.

Report and handover register

Assigns section reports, drawings, data versions, handovers and outstanding measures to the respective construction stage.

The project file remains usable through work-package and personnel changes.

From drawing revision to a section decision

How explosive ordnance investigation is incorporated into construction stages and operational windows

Before the next construction section, completed investigations and outstanding tasks are reviewed. Short possessions require especially complete preparation but do not change technical requirements for surveying, assessment and documentation.

01

Define the project section and ground disturbance

The track group, switch area, operational area, cable route, structure, point list, working width and depth are taken from the current drawing revision.

02

Organise documents and ordnance evidence

Historical information, as-built drawings, earlier reports, known finds and operating requirements are checked for spatial consistency.

03

Divide subareas by survey feasibility

Open areas, zones affected by technical interference, deep volumes and areas accessible only after demolition are distinguished.

04

Specify methods and follow-up measures

Surface methods, depth investigation and explosive ordnance surveying during construction are assessed for suitability for each ground disturbance and planned accordingly.

05

Prepare mobilisation and operating windows

Access, railway safety arrangements, surveying, equipment movement, contacts and data handover are coordinated before mobilisation.

06

Carry out surveying and monitoring

Surveys, borehole investigations or construction-stage services are carried out by section and layer using the agreed methodology.

07

Assess data and findings

Survey readings, interference zones, exposure work and limitations are checked for plausibility against the evidence of ordnance and construction geometry.

08

Hand over and update the section

The report, drawings, point lists, outstanding measures and assessment limits are prepared for designers, operations and site management.

Working volumes and survey limitations

Investigate track areas, operational areas and foundations separately

Large railway yards appear continuous on the site drawing but technically comprise open adjoining areas, track areas affected by metal interference, linear utility alignments, individual foundations and demolition zones accessible only later.

Base investigation on the planned ground disturbance

A reliable brief describes not just the total area but the ground disturbance planned. Track redevelopment, cable trenches, drainage, mast foundations, workshop excavations and access routes need different area and depth references.

Within railway yards, rails, switches, cables, earthing systems, masts and technical installations can obscure survey data. These influences are recorded before method selection. A method is used only where it can answer the question about the target object or structure under actual conditions.

Deep points are described using coordinates, design depth, foundation geometry and installation method. The conclusions of a surface area survey must not automatically be extended to a deeper pile or borehole volume.

Demolition stages are treated as a separate project stage. Where removal of tracks, ballast or foundations makes new areas accessible, a new working volume arises and must be checked against the existing data.

The conclusion remains tied to the documented area. Any subsequent extension, deepening or relocation of the design is checked specifically against survey areas and investigation geometries.

Track and switch references

The track number, switch designation, chainage and construction section provide a clear spatial reference.

For procurement and construction, each item of information is identified as a design assumption, minimum requirement or binding acceptance basis.

Separate areas and depths

Near-surface zones, deep points, linear alignments and excavations are not combined into a single general conclusion.

Overlapping working volumes are not assessed twice but brought together through common geometry and clear responsibility.

Technical interference

Rails, utilities, foundations and installations are documented as sources of interference and existing conditions.

Known sources of interference are documented with their position and expected effect so that their influence is not confused with unidentified anomalies during interpretation.

Operational access

Possessions, electrical isolations, working routes and construction stages determine when investigation is technically possible.

Operational interruptions and subsequent electrical isolations are incorporated into updates as new survey or working conditions.

Drawing revisions

Revised track positions, point lists or depths are checked against the previous investigation scope before construction.

Drawing revisions are checked not only for coordinates but also for foundation dimensions, inclinations and subsequent installation direction.

Follow-up measures

Suitable further investigation is specified for areas that cannot be adequately surveyed or remain unresolved. Explosive ordnance surveying during construction requires technical suitability for the ground disturbance.

The selected follow-up measure has a clear trigger, spatial reference and intended decision date.

Select an investigation

Prepare investigation by installation zone

Two people with a tablet beside a marked construction area; plans lie in the foreground.

Determine ground disturbance and the decision needed

Explosive ordnance investigation becomes relevant where tracks, switches, workshop or service areas, drainage, cable routes, masts, signals or structures disturb a volume of ground not yet reliably assessed. The specific construction section, depth of ground disturbance, existing installations and decision needed before procurement or construction determine the approach.

Clarify investigation requirements for ground disturbance
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Consider differing survey conditions

Marshalling and stabling yards contain zones with very different survey conditions. Open adjoining areas, densely occupied track areas, workshops, fuelling and washing areas, and deep foundation points must not be combined in a single area assessment. Position, depth and suitable investigation methods are defined for each working volume.

Choose methods for different working volumes
Service stages

Which specialist service answers which project question within the installation

The services are not interchangeable. Historical assessment of suspected ordnance, area surveys, deep point investigation, excavation monitoring and clearance address different project questions and working volumes.

01

Historical aerial photograph analysis

Establishes areas with suspected ordnance and data gaps from historical sources.

It does not demonstrate the presence of objects actually in the ground today.

02

Surface survey

Detects measurable anomalies in suitable accessible areas.

Technical interference and depth supported by the data limit conclusions around tracks and installations.

03

Deep-ground and downhole surveys

Investigates defined point and depth volumes for masts, piles, excavation supports and boreholes.

It applies only to the defined geometry and does not replace assessment of the whole area.

04

Excavation supervision

In suitable excavation areas, each working layer is surveyed and assessed by a specialist. Controlled excavation in layers and an additional visual inspection follow. These steps are repeated to the agreed base of excavation; simply watching the excavator is insufficient.

Areas not monitored or modified later remain outside the assessment.

05

Area clearance

Systematically clears a defined volume of ground to the agreed clearance objective. The assessment remains limited to the area and depth actually treated and the task specified.

Areas and depths outside the clearance scope are not assessed with it.

06

Ordnance recovery

Recovers ordnance confirmed by specialists within the permitted scope of activities and responsibilities. Necessary exposure, securing and handover are coordinated for the specific finding.

It is not equivalent to preliminary detection or general clearance of the whole installation.

07

Magnetometry

Magnetometry records magnetic anomalies, particularly those caused by ferromagnetic objects. On suitable open adjoining and operational areas, it provides a position-referenced basis for anomaly assessment. Rails, switches, reinforcement, foundations and vehicles may strongly affect signals. Survey areas and interference zones are therefore documented separately.

08

TDEM

TDEM records time-dependent electromagnetic responses from conductive objects. It can provide additional investigation of selected areas or anomalies. Utilities, earthing systems, reinforcement and other technical installations affect interpretation. Target size, depth and survey geometry limit classification; the signal does not identify an object.

09

Ground-penetrating radar / GPR

GPR shows reflections at material and structural boundaries and can add information about layers, installations and changes in the ground. Moisture, soil conductivity and heterogeneous fill affect the depth supported by the data and interpretation. Radargrams and site drawings show structures and unresolved areas; a reflection does not identify ordnance.

Technical responsibility

Review investigations and records when construction changes

Before work begins, working areas, investigation methods and required records are specified. Across several construction stages, the documents must allow site management to identify which tracks, areas and depths have already been investigated.

Assign results to the tracks and areas investigated

FONTANA-EOD starts with the specific working volume and decision needed before the next construction or operating state. One general conclusion is not assigned to the entire installation.

Before mobilisation, ordnance evidence, surface, ground conditions, technical interference, depth of ground disturbance, access and operating windows are compared. This produces a structured approach for subareas and points.

During construction, deviations, areas not reached and design changes are recorded continuously. Decisions remain tied to the area actually investigated.

The project file distinguishes survey observations, technical assessment, actual findings and follow-up measures. This facilitates communication between designers, operations and site management.

A clear task

Area, track, depth, construction stage, target object and assessment required are specified before work begins.

Reasoned method selection

Methods are used according to their suitability for the specific working volume rather than equipment availability.

Execution by section

Survey areas, borehole positions and excavation areas remain assigned to the respective construction stage.

Transparent limitations

Interference zones, lack of access and areas where data cannot be interpreted are identified spatially.

Project file that can be updated

Drawing revisions, partial handovers and outstanding measures are updated consistently.

State the result and outstanding tasks

The report answers the project question and, where appropriate, identifies the next technical step.

Prepare the next construction section

Follow up unresolved track and installation areas

Record interference zones and later access

Rails, switches, cables, earthing systems, signals, masts, foundations and technical installations may limit geophysical methods. Where an adequate preliminary investigation is impossible, affected areas are shown on the drawing. Access timing and the method suitable for the planned ground disturbance are then assessed.

Bring section reports together across work packages and possessions

The records link the track or installation designation, subarea, construction stage, investigation depth, method, technical limits and follow-up decision. The assessment can then be reused in design, site management, procurement and later project stages. For large installations, the process for bringing together section reports, status drawings and outstanding measures across several work packages and possessions is also specified. This keeps it clear which area has already been investigated, which becomes accessible only after demolition and which design change triggers additional investigation.

Project organisation

Who designs, coordinates operations and carries out the work

Marshalling and stabling yards bring together operator requirements, construction responsibilities, private specialist services and public hazard response. Before work begins, responsibilities for reporting design changes, commissioning investigations and passing results to subsequent trades are specified.

Client

Infrastructure organisations and facility managers

Define project objectives, construction sections, the assessment needed and programme priorities. They provide existing information and commission specialist services.

Design

Railway, civil engineering and geotechnical design

Translate redevelopment and new construction into specific tracks, switches, excavations, routes, borehole positions and depths. They incorporate explosive ordnance investigation into design and the bill of quantities.

Operations

Operator and railway safety arrangements

Set requirements for access, possessions, electrical isolations and protective measures. Operational work authorisation and the specialist explosive ordnance assessment remain separate decisions.

Execution

Construction contractor and site management

Implement working areas, the demolition sequence, excavation layers and stop points. Changes in position, depth or construction method are communicated before construction.

Specialist contractor

FONTANA-EOD

Assesses documents and ordnance evidence, develops the commissioned approach, carries out specialist services and documents results and assessment limits.

Hazard response

KBD, KMBD, KRD and local authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and building control may be involved, depending on local procedures and the construction task. Contacts and requirements are assigned to the specific section and drawing revision. Technical investigation, operational work authorisation and official decisions about finds remain documented with their respective responsibilities.

Work outputs and supporting records

Which documents are used in practice within the project

Typical work outputs link the drawing revision, fieldwork and construction. They show not just survey readings but the spatial scope and next technical step. Design changes, new depths or construction stages requiring reassessment are also recorded.

Two people discussing plans at a table beside a vehicle on a construction site.

Subarea and construction-stage drawing

Organises track groups, operational areas, demolition stages and the timing of investigation.

The drawing provides the common spatial basis for designers, operations and the specialist contractor.

Site management and specialist designers can identify which area is available for the next work step.

Document subareas and construction stages
Illustration of a person beside a GPR instrument, with schematic waves in a ground section

Survey and interference-zone map

Links survey lines, technical interference, zones where data cannot be interpreted and the depth supported by the data.

Known installations and unresolved zones remain separately identifiable.

The map identifies technical influences that must be considered when interpreting survey data.

Assess survey methods and interference
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Mast and borehole point register

Records coordinates, foundation geometry, design depth, investigation depth and status.

Design changes can then be updated point by point.

The register supports clearance decisions for individual points without extending the assessment to the whole installation.

Investigate mast and borehole positions
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Excavation and demolition log

Documents excavation layers, demolition stages, stop points, observations and follow-up measures.

The assessment remains related to the area actually monitored.

The logs allow a traceable comparison between the planned excavation sequence and that actually carried out.

Provide specialist monitoring of excavation and demolition
Three people beside a fenced excavation containing an exposed elongated object.

Anomaly and findings drawing

Locates survey anomalies, further investigations, exposure work and actual findings.

Survey signals and actual finds are presented as technically separate categories.

Positional references are retained during subsequent exposure or clearance work.

Follow up anomalies and findings
Two people discussing plans at a table beside a vehicle on a construction site.

Section report and complete project file

Brings together initial conditions, methods, subareas, limitations and conclusions.

Several reports are combined to give a consistent investigation status for the whole installation.

An appendix list shows later designers and contractors which reports and drawing revisions belong to the documented investigation status.

Link section reports and the overall file
Side view of a yellow track maintenance machine above rails and concrete sleepers.
Yellow survey trolley on a track at night, with people in high-visibility clothing behind it.
Identify the project location

Identify track groups and operational areas

Illustrated map of Germany with location markers on a construction site.

Site plan and existing requirements

Mark tracks, switch areas, workshop and service areas and individual foundation positions on the site drawing. Add the respective construction stage and access available. On large installations, clear subarea identifiers prevent results from one work package being used as records for adjoining working areas.

Use results correctly

Assign results during ongoing facility redevelopment

Assess survey interference technically

A survey area whose data can be interpreted only with limitations initially describes a methodological limit. It establishes neither a confirmed ordnance find nor a sufficiently investigated area. The report must identify which conclusion is actually possible for the planned ground disturbance.

Assess survey findings technically

Incorporate design changes into section reports

For relocated cable routes, revised foundations or additional excavation support, check whether existing results cover the new working volumes. References to the work package, drawing revision and construction stage facilitate this comparison.

Check the project file after design changes

Technical information

Railways, roads and routes: brochure

The brochure shows how FONTANA-EOD combines historical investigation, specialist planning, surveying and construction supervision in infrastructure projects. It explains trackside constraints, method selection and limitations, and result documentation.

1 / 10
Railways, roads and routes: brochure — page 1

German · 10 pages

Questions from design and construction

Common questions about explosive ordnance surveying in marshalling and stabling yards

When should explosive ordnance surveying begin for marshalling or stabling yards?

Assessment should begin as soon as construction sections, planned ground disturbance and operating constraints are identifiable. For track redevelopment, switch renewal, workshop access, drainage, cable civil works, overhead line foundations or site development, historical ordnance evidence, current installations, depths of ground disturbance and accessible working volumes must be brought together before tendering and construction.

Why are marshalling and stabling yards particularly demanding for surveying?

Large railway yards contain rails, switches, fastenings, cables, earthing systems, signals, masts, drainage, foundations and often heterogeneous fill. These structures can strongly affect geophysical surveys. The site is therefore not assessed as a whole but divided into technically comparable subareas, deep point ground disturbances and zones accessible only after demolition.

Which methods can be considered in track and operational areas?

Selection follows the target object, surface, ground conditions, interference and depth. Historical assessment establishes the grounds for suspicion; GPR, magnetometry or TDEM can investigate suitable near-surface areas. The suitability of point-specific depth investigation is assessed for piles, masts, sheet piles and boreholes. For zones that cannot be adequately surveyed, access and supplementary methods are clarified. Where explosive ordnance surveying during construction is suitable, each layer is surveyed and assessed by a specialist. Controlled excavation in layers and an additional visual inspection follow; the steps are repeated to the agreed base of excavation. Merely watching the excavator work is insufficient.

How are switch areas, cable zones and drainage distinguished?

Each area receives a clear positional reference using the track, switch, chainage, construction section or coordinates. Cable and drainage routes are recorded with their width, depth, chambers and crossings; switch areas and track alignments are subdivided by construction stage and technical interference. This keeps it clear which assessment applies to which working volume.

What needs considering for short possessions and working windows?

Drawing revision, working area, surveying, equipment movement, railway safety arrangements, contacts and data handover must be coordinated before site work. A short working window must not lead to unclear survey lines or missing quality checks. Areas not reached or where data cannot be interpreted are recorded with precise positions and linked to later investigation or another measure.

Which documents are needed for an initial assessment?

Site and track drawings, switch and structure designations, construction sections, demolition stages, cable and utility drawings, drainage design, mast and borehole point lists, depths of ground disturbance, historical assessments, previous survey reports, existing reports of finds and operational and programme information are useful. Provisional documents can also be reviewed if their revision and unresolved assumptions are identified.

Official information and requirements are included with complete appendices, dates and spatial scope. In Germany, the relevant ordnance disposal service, local public order authority and, where applicable, building control are identified for the project location; operational work authorisations remain separate processes. Outside Germany, coordination is with the authorities responsible locally.

How are inaccessible areas beneath tracks or installations addressed?

These areas are not assessed as being without anomalies. The report identifies their position, depth and the cause of the limitation and assigns a suitable follow-up measure. Necessary investigations and protective measures are specified before ground disturbance during demolition. Depending on the ground disturbance and survey conditions, additional investigations on areas accessible later, point-specific depth investigation or technically suitable explosive ordnance surveying during construction may be appropriate.

If an unexpected suspicious object is found, stop work. Do not touch, move or uncover it further. Leave the immediate area and warn others without putting yourself at risk. In Germany, notify the police on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine what happens next; a project enquiry does not replace reporting the find.

What determines the effort, duration and cost of an ordnance assessment?

The determining factors are the size and number of subareas, existing tracks and installations, access, surface condition, methods required, number and depth of borehole or foundation positions, possessions, surveying, data quality, construction stages and documentation objectives. A reliable estimate therefore needs a structured list of working volumes and ground disturbances rather than an undifferentiated total area.

Prepare an enquiry

The documents we need for your installation

An initial enquiry does not need to contain a complete bill of quantities. It should identify subareas, construction sections, proposed ground disturbance and operational constraints.

Installation and location references

Track and switch drawings, operational areas, workshop and service zones, construction sections, chainage and current drawing revisions.

Across several work packages, identify which subareas are to be investigated first.

Ground disturbance and construction stages

Track removal, formation works, cable trenches, drainage, excavations, piles, masts, signals, foundations and maximum depths.

Possessions, demolition sequences and parallel trades affect the method.

Documents and evidence requirements

Historical assessments, official correspondence, as-built and utility drawings, previous survey reports, point lists and known findings.

State whether the result is needed for design, procurement, site management or project completion.

For initial technical assessment

For an initial assessment, a site drawing, the track or operational areas affected, a short description of ground disturbance, maximum depth, planned dates and available indications of ordnance are often sufficient.

FONTANA-EOD then identifies the documents still needed and the technically appropriate service stage. For large installations, work can be divided by priority, construction stage and subarea. Data formats, report recipients and handover dates are also agreed.

Spatial area

Track group, switch, operational area, cable alignment, structure and drawing revision.

Deep interventions

Mast, pile, excavation-support, shaft and borehole positions with design depth and construction method.

Operational organisation

Possession windows, access, electrical isolations, construction stages and contacts.

Documentation objective

Documents for design, procurement, site management, operator communication or the overall file.

GPR on a construction site
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.