Two people discussing plans at a table beside a vehicle on a construction site.

ordnance clearance plan

A clearance plan connects planned ground interventions with a reasoned approach to ordnance clearance. Existing findings, investigation needs and construction phases form a traceable plan. Send FONTANA-EOD the current design and available ordnance documents. Describe the planning question you want to resolve so we can agree which questions the clearance plan should answer.

Initial information

Separate established details from assumptions.

Decision

Justify the intended procedure.

Coordination

Coordinate construction and records.

Read the overview

Briefly explained

What is a clearance plan and what is it for?

A clearance plan is the professional planning basis for an ordnance clearance operation. It describes the task, assesses available information, assigns clearance needs spatially and justifies the intended procedure. It also includes construction sequence, protective requirements, quality controls, documentation and traceable consideration of effort. The plan describes the planned service; it is not yet an execution record or ordnance clearance confirmation.

Project references

Selected project examples

Prepare decisions

When is clearance planning needed?

Planning needs follow from knowledge, intervention and applicable requirements. A property name or total area alone does not describe the task.

Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

New construction, extension or changed use

Where suspected ordnance and planned ground disturbance coincide, the necessary procedure requires professional clarification. For new construction, excavations, foundations, utility connections and temporary working areas should be considered separately. For an extension, also assess which existing records actually cover the new intervention.

Assess construction and interventions
Two people discussing plans at a table beside a vehicle on a construction site.

Incomplete or contradictory information

An older report, new design and authority statement may concern different areas or work statuses. The plan must resolve these differences or identify them as unresolved conditions. It must not conceal missing findings through an apparently unambiguous method decision.

Bring existing knowledge together
Two people discussing plans at a table beside a vehicle on a construction site.

Several trades and construction phases

For construction in sections, planners and site management need a traceable sequence. Which investigation must be available before which intervention? Where does further work depend on demolition, access or specialist feedback? The clearance concept provides the technical basis for this; the overall construction sequence must still be coordinated with the specific dates.

Coordinate construction phases and records
Clearance plan content

What the clearance plan describes

Initial information, intended interventions, method selection and required records must be consistent. The BFR KMR 6.2 describe planning content; Appendix A-9.4.9 organises the explanatory report's content. Scope, level of detail and required appendices are specifically determined for each commission.

Purpose, commission and planning objective

Identify the construction project, client, planning area and specific purpose. Which decision should the plan support and which services are commissioned? Record the underlying design and other specialist planning to include. A clear task description prevents participants expecting different services from the same document.

Sources, investigations and unresolved initial information

Compile relevant documents with dates and versions: authority information, historical investigations, technical investigations, earlier clearance and existing results reports. Assess their usability for the present task. The report must distinguish known facts, professional interpretations and provisional assumptions; information gaps are expressly included.

Location, existing conditions and third-party requirements

Ground structure, groundwater, surfaces, buildings, utilities, interference and accessibility influence planning. Rights of use, neighbours, nature conservation, water law and other requirements may also matter. Describe only conditions evidenced for the specific project and clarify those still needing assessment. Not every factor is equally important at every location.

Construction project and spatial clearance requirements

Show ordnance-relevant interventions with plan references, such as excavations, foundation elements, retaining structures, shafts or utility trenches. Assign the professional conclusion needed to each area. Property boundary, later structure and actual working space are not automatically identical. Exclusions and unresolved subareas must remain recognisable.

Method comparison and preferred solution

The plan explains which methods are possible, their prerequisites and limits. Selection is justified from actual conditions. The preferred solution includes spatial and temporal sequence, necessary preliminary services, technical infrastructure and coordination with other trades; merely listing equipment is insufficient.

Checks, documents and effort

Define the quality controls, responsibilities and results documents needed, including acceptance and handling of deviations. Construction duration and economic considerations must relate traceably to the planned solution. Maps, drawings, schedules and source appendices must reflect the same status as the explanatory report.

Planning decisions

Align planning decisions with available data

The next decision depends on existing knowledge and the conditions the measure must satisfy. Document review, technical assessment and planning updates each provide a specific result for further work.

Before method selection: the basis remains insufficient

Historical documents, current intervention plans or earlier investigation reports concern different parts of the project. The client and specialist planners assign findings to actual construction areas and depths. Suspicion and unresolved questions determine the further contribution needed. The decision may first require additional information or technical investigations. Their results provide the traceable basis for later method selection; historical suspicion alone does not describe a completed investigation.

Clarify initial information and suspicion

Before execution: site conditions limit the solution

Utilities, metal installations, ground structure or lack of access can affect planned surveying. Specialist planning assesses which conclusions are possible and the conditions a suitable alternative needs. For work in sections, preliminary services and handover points are coordinated with construction. The planning status identifies the selected solution and remaining limits. Unresolved areas remain visible even when other parts can progress.

Determine technical investigation needs

Before procurement: the design has changed

A deeper excavation, relocated route or additional shaft may require other investigation areas and services. The developer, planners and specialist company compare the new design with earlier information. Affected clearance objectives, quantities, method assumptions and records are reassessed. The plan and appendices are updated to the same status. Procurement therefore reflects the actual construction task; adopting an earlier specification unchanged would not adequately account for changed planning.

Connect planning and records
Area and depth

The clearance objective must match the actual intervention

An understandable clearance objective describes the professional conclusion needed for a given area. It must not arise solely from a desired equipment name or an existing blanket clearance wording.

Define working areas unambiguously

Link each relevant intervention to a unique identifier and readable plan. Retaining works, working space and an additional shaft within an excavation may form different assessment areas. A shared project name does not replace assignment. The spatial definition is professionally coordinated with construction planning. Individual foundations are assigned with planned geometry; utilities with route and sections. A measurement grid or borehole arrangement is justified from the task and site conditions rather than adopted from another project.

Describe depths with their reference

Depths are comparable only with an unambiguous reference, such as specified ground level or an elevation. If terrain or planning changes, the values must be related to each other. Intervention depth, professionally substantiated suspected volume and demonstrable investigation scope are assessed together; a general standard depth does not suit every project. Record the terrain status underlying a section and intended filling or excavation. Later lowered ground can change the distance to the depth range previously considered. Planning must describe the relevant geometry with the same traceable reference.

Identify limits and unresolved areas

The concept should show what the intended measure is to achieve and which prerequisites are still missing. Excluded, inaccessible or insufficiently assessable areas must not enter an overall conclusion unnoticed. How a later ordnance clearance confirmation is read depends on its documented scope. Also identify which preliminary construction work will make an excluded zone accessible and which professional step follows. This dependency matters for construction: an organisationally completed planning phase does not mean all later working areas have already been investigated or cleared.

A justified selection

Which clearance method suits the project?

The preferred solution must be technically suitable, feasible under the site conditions and understandable to the client. The BFR also provide for consideration of construction times and economic efficiency.

Two people with a tablet beside a marked construction area; plans lie in the foreground.

Compare suitability and limits

What conclusions can each method support under the existing ground, built-environment and interference conditions? Which areas remain unresolved? What preliminary work is needed? Also explain why an otherwise established method is unsuitable for a particular sub-area. Manufacturer data or previous use on other sites does not replace this assessment.

Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Plan preliminary work and the sequence

If an area is initially inaccessible or cannot be investigated sufficiently, the next steps must be planned by specialists. Measures alongside construction are not a universal shortcut. In particular, under DGUV guidance, merely watching excavated material is not equivalent to a technical ordnance survey alongside construction. Methods, protection requirements and handover points belong together. The DGUV questions on explosive ordnance clearance explain this distinction. Planning specifies the technical approach required and the conditions for the next work step.

Update the planning

Address missing documents and design changes

A concept depends on the information on which it is based. If that information changes or remains insufficient for a decision, subsequent work must remain traceable.

Resolve specific gaps in knowledge

Link each relevant gap to the decision it affects. For example, if an earlier report covers only the existing hall, it cannot yet support conclusions for a new extension area. Planning must establish what additional information is needed. Preliminary work is determined as required, rather than prescribing the same investigation programme as a precaution in every case.

Make assumptions and consequences explicit

If an important gap cannot initially be closed, the assumption used to continue planning and the consequences of a deviation must be clear. Identify which part of the decision depends on it and when the underlying information must be checked. A provisional planning position must not become an apparently established finding when passed on.

Assess changes from a technical perspective

A relocated route, deeper foundations or changed access may affect the existing solution. In that case, specifically review the clearance requirements, choice of method, protection requirements and documentation. Record the change together with the design revision, reasons and responsibilities. Superseded versions must remain identifiable so that subsequent execution uses the correct revision.

Fit clearance planning into the project sequence

The work moves from a clearly defined planning task to a reasoned solution. The preliminary work required depends on the information actually available and the decisions needed for the project.

01

Define the planning assignment

State the reason, area and decision required. Clarify the scope of specialist planning and its interfaces with other parties. A shared understanding of the task makes the concept easier to review later. Distinguish the entire property from the construction sections actually affected. An excavation, an access route and a future utility line may create different investigation and planning tasks. Also state whether the result is initially intended to support the choice between options, further specialist planning or preparation of procurement.

02

Bring the underlying information together

Compile existing information, historical findings and technical reports together with the current design. Identify the relevant design revisions. Keep important gaps visible rather than concealing them through an unstated assumption. For plans, also check coordinate and elevation references and the accompanying appendices. An earlier investigation mentioned in a report can only be used if its actual scope can be established. Record contradictions between the site plan, written conclusions and construction design with the area or depth affected.

03

Clarify the preliminary work needed

Specialist planning identifies which unresolved information prevents a further decision. Any necessary additions are directed at that question. A general investigation programme unrelated to the task does not adequately describe the planning needs. Missing ground investigation data, an untraceable investigation boundary and unclear metallic interference affect different decisions. Not every gap is therefore addressed through the same investigation. After a necessary addition, its results feed back into the planning; earlier assumptions are reviewed on that basis.

04

Compare solutions with clear reasons

Suitable methods are assessed against the actual conditions and the required clearance objective. Preliminary work, limits and effects on the construction sequence form part of the comparison. The preferred solution must be understandable to the client and those responsible for further planning. The comparison also considers equipment access, required working areas, necessary preliminary work and coordination with other trades. Along a route, open stretches and sections near utilities may require different solutions. A technically possible option is therefore also assessed for its feasibility under the specific site conditions.

05

Coordinate interfaces and the status of results

Bring construction phases, responsibilities, checks and the documents needed later together. Identify the subject of each outstanding coordination issue. The report and its appendices must describe the same traceable planning revision. For phased construction, agree what feedback is required before each subsequent ground intervention. Clearly delimit any unresolved sub-area on the plan. Specify which investigations must actually have been carried out, and which associated records must be available, before the next intervention.

06

Prepare further planning

The concept is provided for the next agreed planning steps. If the project changes, the decisions affected are reviewed. Subsequent execution and its documentation remain distinguishable from the preceding planning. Before handover, the relevant plans and assumptions are checked against the current design revision. Later detailed execution planning requires the preferred solution with its spatial and timing conditions. Site management and the procurement team receive the same revision so that the specification and planned execution remain aligned.

Keep the basis of a planning decision traceable

A later change is easier to assess if the basis of the original decision remains known. The planning file therefore links the documents used, technical assessment and relevant design revision.

Documents with their origin and revision status

For information taken from other sources, it should be clear who produced it and which area it concerns. Earlier findings retain their provenance even when incorporated into a new report. A shared project name does not automatically mean that all documents cover the same area or ground intervention. Record the author, document date, plan revision and associated appendices. Historical evidence of suspected ordnance, survey data and reports on completed clearance retain their different functions. A map compiled from several sources must show which conclusion was taken from which document and where a separate technical assessment begins.

Decisions and the conditions that determine them

The reasons for the preferred solution must show which prerequisites are essential to it. When something changes, this allows a targeted review of the decision affected. Not every new piece of information requires the same response; what matters is its technical relationship to the planned approach. Relevant conditions may include a particular excavation geometry, an accessible working area or the planned removal of a structure causing interference. If such a prerequisite changes, the planning step affected can be reassessed specifically. A partial decision that remains suitable thus stays clearly distinguishable from areas that actually need adjustment.

An agreed revision for further planning

Combine the report and appendices with a clear revision status. Additions should show what has changed from earlier versions. At handover, it must be clear which revision is to be used and which prerequisites still need clarification. An appendix list links plan references to their respective revisions. References in the explanatory report must lead to these documents, not to superseded interim versions. When the planning is updated, affected areas and decisions are visibly amended; the previous version remains identifiable as an earlier revision.

Define the planning assignment from the current situation

The contribution required depends on whether new planning is being developed or an existing concept is being continued. Describe this starting point and the outstanding decision in your enquiry.

The underlying information is held in different places

Compile the available documents and identify different design revisions. The first task may be to establish whether they can be used for the specific project. Link missing information to the planning question affected.

Link unresolved information to the planning

A solution is to be prepared for procurement

State the planning result required and any existing requirements for the specification and documentation. The concept, subsequent detailed execution planning and tender documents must be coordinated while retaining their different functions.

Prepare the transition to further planning

An existing concept no longer matches the design

Mark the changed areas and provide the complete previous version. The specialist review establishes which information and decisions are affected by the change. A revised cover sheet does not replace this substantive update.

Check spatial requirements against the change

A new planning assignment is to be commissioned

Describe the project, current knowledge and decision required. Identify the planners involved and the documents available. FONTANA-EOD will agree with you the specialist contribution requested and its boundaries in relation to other services.

Agree the planning scope with FONTANA-EOD

A traceable solution for the specific construction task

As a private specialist company, FONTANA-EOD relates the commissioned planning to the actual ground interventions and the information available. A usable concept makes the decision, its basis and its limits clear to the other parties involved.

The task is defined

The concept is directed at the planning decision required. A property name or equipment name does not replace a technical description of the project.

Uncertainty remains visible

Established information, technical assessment and provisional assumptions are distinguished from one another. Missing information is considered together with its possible consequences.

The choice of method has a reason

The intended solution is linked to the actual conditions. Limits and necessary preliminary work remain part of the planning.

Construction phases fit together

Dependencies on other work are taken into account. Required feedback and handover points are placed in a traceable context.

Documentation requirements are prepared

Planning takes account of the documents needed later. However, a record of execution can only be produced from work actually performed.

Changes are assessed specifically

A changed ground intervention is checked against the relevant underlying information. The update shows which decisions had to be adjusted.

Coordination and documentation

Define roles, quality criteria and handover from the outset

Before execution, establish who makes which decision, which checks are planned and which documents will be handed over. Include these arrangements in the planning and the commission.

Assign tasks and powers

Distinguish the client, specialist planner, contractor, site management and, where applicable, local site supervision. Identify who provides the underlying information, reviews technical decisions and initiates changes. Official decisions are made by the competent authorities; the commission describes the respective specialist contributions. The interfaces with authorities must be clarified separately for the location and matter concerned. Depending on the procedure, the ordnance clearance service/KBD, local public order authority or building control authority is involved within its respective remit. Identify the competent authority and the contribution required from it before the relevant decision.

Coordinate the construction sequence and other requirements

The planned sequence must fit with other trades, access arrangements and operational use. Necessary permits, notifications, approvals or contributions from other specialist planners must be determined for the specific measure. Occupational health and safety and protection of neighbours are specified in the relevant specialist documents; the concept must show their significance for the solution selected.

Define assessment criteria before execution

For the specific project, establish how the required quality and coverage are to be demonstrated. This may include criteria for spatial referencing, completeness, measurement quality and areas that can be assessed. Describe how a decision is made if criteria are not met: for example, further assessment, adjustment of the planning or recording a limitation. General promises about percentages or accuracy do not replace these arrangements.

Assign checks and acceptance procedures

Which documents are reviewed by whom, and when? What feedback is required before the next work step? The BFR treat quality checks and acceptance conditions as planning content. Responsibilities, prerequisites and the handling of outstanding points should be agreed clearly in the commission. An administrative signature does not in itself extend the scope of a technical investigation.

Keep plans, data and the report together

Agree the required result documents, file formats and coordinate and elevation references to suit the project. The report, plan and any specialist data must concern the same areas. Differences between planned and completed services and unresolved sub-areas remain traceable. The survey and clearance records subsequently document the actual result.

Prepare the transition to tendering

The next planning steps and service items required can be derived from the reasoned solution. A clearance concept is not automatically a complete bill of quantities, however. Before later detailed execution planning, its revision must be checked for currency. The tender structure describes the service, interfaces and documentation more precisely on this basis.

Specify the location and construction task for planning

The geographical location and operational setting determine which parties and constraints must be considered. The enquiry therefore needs to relate to a specific project.

Illustration of a map of Germany marking Wesseling and Gersheim in front of a construction area, with construction plans and a hard hat beside it.

Location-related coordination

State the project location and any authorities or other bodies already involved. Provide existing correspondence together with its subject matter and the applicable appendices. The application or coordination procedure required is checked for the specific location.

Identify the region and competent interfaces
Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

Construction task and operational conditions

Describe the ground interventions intended and whether site use or construction phases require particular coordination. The project context helps to assign access arrangements, handover points and contributions from other specialist planners clearly.

Determine requirements arising from the project setting

Distinguish the terms used in clearance planning

Clear terminology helps to agree the commission and expected planning result. The terms describe different contributions to preparation and subsequent execution.

Establishing the planning basis

This clarifies the task and the information available for planning. Missing information, or information that cannot be used adequately, is linked to the specific decision.

Preliminary work

This addresses gaps in knowledge that are important for further planning. Its type and scope are determined by the technical needs of the project.

Preferred solution

This is the reasoned result of the project-specific comparison. Its prerequisites and limits remain traceable for further planning.

Updating the assessment

This updates the information and decisions affected when changes occur. The new version should show what has changed technically from the previous revision.

Consider the available knowledge and intended service together

Planning links existing knowledge to the further action required. Each document retains its provenance and its own technical conclusions.

Workstation with two screens showing aerial photographs and maps, and printed documents on the desk.

Historical information

A historical assessment may help to evaluate suspected ordnance. Its spatial scope and conclusions are linked to the current construction task. Any further knowledge required follows from the specific planning question.

Place historical findings in the planning context
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Deep interventions at specific points

Foundations and other deep ground interventions require traceable location and depth references. Planning considers the actual working area together with the technically required investigation scope.

Identify investigations for deep ground interventions
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Work alongside construction

Where specialist work and the construction sequence depend on one another, the technical approach, protection requirements and handover points must fit together. The specific service is tailored to this task.

Identify requirements alongside construction
Person wearing an orange high-visibility vest on a marked construction area with small piles of soil
Person wearing an orange high-visibility vest with a MALÅ survey cart on grass
Questions and answers

Frequently asked questions about clearance concepts

When should a clearance plan be commissioned?

If the project requires clearance planning, it should be scheduled so necessary preliminary work and coordination can be considered before the affected intervention. This does not establish a fixed general lead time. Available data, scope, responsibilities and construction sequence are decisive.

Does every construction project need the same clearance plan?

No. The purpose, suspected situation, planned use and interventions determine the task. The BFR KMR describe planning content for their defined scope. Which requirements are binding for another project and how much detail is needed must be clarified from applicable specifications and the commission.

Are aerial photograph analysis and a site plan sufficient?

They may provide important initial information but do not automatically cover all relevant conditions. Intervention depths, ground conditions, utilities, existing installations, earlier investigations, accessibility and construction phases may also be decisive. Initial information gathering checks whether documents are complete and usable for the specific task.

Can a clearance plan be prepared with missing information?

First clarify which decision depends on the missing details. Preliminary work may be needed. If significant gaps remain, uncertainties, provisional assumptions and possible consequences must be clearly presented. Missing knowledge must not be portrayed as an established basis.

Is there a standard depth or method for all projects?

No. The clearance objective must be coordinated with the specific use, interventions and knowledge available. Method selection also considers actual site conditions and their limits. Numbers or methods from another project cannot be transferred without professional assessment.

Which appendices belong to a clearance plan?

Depending on the task, they may include traceable overview and detailed plans, relevant specialist maps, technical drawings, construction and cost documents, sources and records. Content and scale must support the report's conclusions. All appendices should be clearly named and match the planning status stated.

Does the finished plan already permit earthworks?

No. It describes the intended measure and its conditions. Investigations and clearance actually carried out must subsequently be documented and assessed within their respective scope. A clearance conclusion follows those results, the relevant specifications and expressly documented limits.

What happens if construction planning changes?

The change is assessed against the plan's basis and decisions. Other areas, depths or conditions may change clearance requirements and require further coordination. Affected content and plans must be updated traceably before being used for further execution.

Describe the planning contribution required clearly

In your enquiry, state the current project status and the decision that needs to be prepared next. The available documents help to define the specialist work required.

New planning or revision

State whether a concept is to be prepared for the first time or an existing version needs adjustment. Provide the project location, address, land parcel, construction area, contact person and planning decision required. For a revision, both the old and current design revisions are needed. Site plans, sections, route alignment, borehole points, intervention depths and particular foundation or working areas describe the actual construction task.

Decision and recipients

Describe how the result will be used and who will take it forward. Provide correspondence from authorities, historical assessments, aerial photograph analysis, investigation reports and previous clearance confirmations in full, including appendices. State the desired report and plan formats, recipients and requirements for checks and documentation for handover. This allows the contribution to focus on the next decision and its actual prerequisites.

Unresolved information and contacts

Identify known gaps and the parties who can provide further information. Link utility, existing-structure and ground investigation documents and known access conditions to the current revision. Construction times, phases, specialist planners involved, conditions imposed and outstanding coordination issues describe the interfaces. Mark the specific question on the plan so that a query can be assigned to the section affected and the intended ground intervention.

GPR on a construction site
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.