Project pathway
The quickest route to the right decision.
If an object suspected to be ordnance is identified during surveying, area clearance or earthworks, construction management and the client must clarify reporting and further handling. An unexpected find requires work to stop immediately, the object to remain untouched and the immediate area to be vacated; the police are informed. For planned exposure and recovery tasks, send existing plans and survey reports so that FONTANA-EOD can assess access, the permitted activity framework and coordination with authorities.
Maintain the area and working state.
Clarify identity, condition and surroundings.
Document recovery and coordination points.
Whether a suspect point requires ordnance recovery is determined only after controlled exposure and specialist assessment. The condition of the find, access and responsibilities determine further action.
An unexpected find requires work in the affected area to stop and the locally competent bodies to be informed; the object remains untouched.
The Plattling report documents individual-point recovery and three bomb finds in September 2026. Defusing by the authorities remains separate from the private specialist company’s services. View project details.

Project documents connect the known location with the affected working area and existing investigations. Specialist participants receive the same information. The next task is agreed with its spatial reference. A general site name does not replace this identification.
Compile existing documents
If access or the construction sequence changes, those responsible are informed. Existing reports retain their original scope. The specialist company aligns its contribution with the current project situation. Further decisions are made by the respective competent bodies.
Coordinate supervised earthworks
Construction management, the specialist company and competent bodies need clearly identified contacts and documents. The project organisation brings existing information together. Transfers of responsibility and information supplied remain documented. Tasks are clearly allocated even under a tight schedule.
Assign responsibilities and documents
Further construction planning is compared with the documented work status. Unresolved areas and relevant conditions remain identifiable. A completed partial task is handed over with its actual scope. Additional interventions are assessed separately by specialists.
Identify further work on the areaA measurement signal, an exposed interference object and identified ordnance represent different work stages. Classification determines the specialist service, protective arrangements and communication with authorities required.
A spontaneous find during ordinary construction has a different starting point from a planned clearance operation. Work in the affected area stops immediately, the object is neither touched nor moved, and the reporting procedure to construction management and locally competent bodies is initiated. A private project enquiry does not replace this immediate communication about a find.
An anomaly initially describes a measurable irregularity. Before recovery, the point must be assessed by specialists using its current location, depth, data quality and possible source of interference.
If target-point work is necessary, exposure, access, nearby utilities and occupational safety are planned. Only visual and specialist assessment can establish whether the object is scrap, another interference source or an ordnance-related object.
Assess the anomaly dataA deep suspect point may lie immediately beside piles, sheet piles, anchors or drilling alignments. Positional uncertainty, depth range and structure geometry determine safe access and exposure planning.
Drilling or installation work is not continued in the affected volume until a specialist follow-up decision is available. Additional measurement profiles or adapted exposure may be necessary.
Assess a deep-ground findingDuring systematic area clearance, interference points are exposed and identified. If ordnance or another relevant object is revealed, the task changes from work on the area to handling the specific find.
The point identifier, location, depth, condition and handover are maintained in the same evidence chain. Further work on the remaining clearance area is coordinated with the protective area, handling of the find and clearance concept.
Identify the clearance processIf an unknown object or suspected ammunition becomes visible during earthworks, it must not be moved using construction equipment, cleaned or examined more closely. Work stops immediately and the immediate area is vacated; the local reporting procedure is initiated.
Further action depends on the initial specialist assessment and local reporting procedure. An existing construction-stage process helps quickly identify the find location, working depth and bodies involved.
Identify the role of excavation supervisionRepeated finds may indicate that work on individual points is no longer sufficient. The range of objects, their spatial distribution and the historical grounds for suspicion are reassessed.
Depending on the result, an extended survey, an adjusted clearance plan or work covering an area or volume may be required.
Adjust the clearance planIf the condition is unknown, a particular hazard may be present or the class of find falls within public-authority responsibility, the area is kept undisturbed and the competent body decides how to proceed.
Planning and construction management need clear information on the secured area, the work stoppage, project communication and the conditions for resuming work later.
Prepare the reporting procedureRecovery planning connects the status of the find, the permitted activity, protective measures and responsibility. The next work step is determined from the professionally assessed and documented condition.
Ordnance recovery does not begin with every measurement anomaly. First, a suspected point must be located under controlled conditions and exposed sufficiently for a qualified person to assess the object, its condition and responsibility for further action. This assessment determines whether a commercial recovery service may be carried out, additional safeguarding is required or the competent state body takes over further work.
Initial situation: Measurement data indicate a relevant point, but the actual type of object is unknown.
Technical step: The data, point location, depth, interfering surroundings and space required for exposure are assessed; work on the target point is then planned.
Result: A controllable work instruction for exposure and identification, with no recovery decision yet.
Interpret the measurement dataInitial situation: Its shape or material may suggest a connection with ordnance, but the object has not yet been professionally identified.
Technical step: The work area is kept undisturbed, further earth movements are controlled and the responsible specialist takes over the assessment.
Result: A documented decision on whether exposure continues, an authority is involved or another safeguarding procedure is chosen.
Provide the context of the findInitial situation: The type, condition and local framework of responsibilities permit recovery by specialists with the appropriate authorisation and certification.
Technical step: Safeguarding, collection, preparation for handover or handover are carried out in accordance with the agreed procedure and the agreed handover arrangements.
Result: A traceable recovery and handover record for the specific find point.
Clarify the handover recordInitial situation: The assessment establishes that defusing, demolition, destruction or a particular decision on averting danger is required.
Technical step: The secured condition and information on the find are handed over to the locally competent body. Its requirements determine further handling.
Result: A clear distinction between commercial project services and public-authority action.
Check local responsibility and handover arrangementsInitial situation: Several objects or recurring findings change the previous assumptions about hazards and clearance.
Technical step: The grounds for suspicion, clearance objective, division into sections and methods are updated on the basis of the new findings.
Result: An adjusted clearance or investigation plan rather than simply continuing work point by point.
Assess area-wide workInitial situation: The object has been dealt with and responsibility transferred, and the construction or clearance project is to continue.
Technical step: The find point, exposed area, handover, remaining suspicion and effects on neighbouring areas are assessed together.
Result: A project-specific decision on subsequent work that applies solely to the documented scope of work.
Complete the project fileRecovery is rarely the first work step. Historical assessment, technical detection, exposure and monitoring during construction provide the information needed to handle a find safely.

Aerial photographs, former use and existing find data support an assessment of the range of objects that may occur within a project area.
Historical assessment does not locate an individual object present today, but it influences priorities, protective planning and the spatial scope of investigation.
The source register, photograph dates, historical suspicion map and known findings are assigned to the present project area. Data gaps and positional uncertainties remain part of the assessment. This makes it possible to trace the range of objects on which the planned work at target points is based.
Open the grounds for suspicion
Ground-penetrating radar can reveal layer boundaries, installations and structural changes in the ground. It can therefore help assess the surroundings of a suspected point before exposure.
A radar image does not identify ordnance. Conductive or wet soils, complex made ground and numerous installations can limit interpretation.
Radar profiles, profile direction, positional reference and usable depth range are documented together with the assessed structures. Installations and possible access problems remain distinguishable from suspicion concerning a specific object. Ambiguous reflections are retained as unresolved findings.
Understand ground-penetrating radar
Magnetometry records variations in the Earth's magnetic field that may be caused by ferromagnetic objects. Georeferenced anomalies provide a basis for prioritising suspected points.
Utilities, reinforcement, vehicles, scrap and other magnetic sources of interference can obscure signals. Reliable identification requires controlled exposure.
Magnetic measurement traces, sensor arrangement and position data remain linked to the anomaly map. Interference zones and measurement gaps are shown separately from areas that can be evaluated. The target-point list records the measurement finding on which planned exposure is based.
Identify the role of magnetometry
TDEM evaluates the time-dependent electromagnetic response of conductive objects. In a suitable measurement environment, the method can provide additional information for selecting and investigating individual suspected points.
Several nearby objects, electromagnetic influences and unfavourable site conditions make signals harder to distinguish. The type of object is established only through exposure and professional identification.
Coil configuration, acquisition parameters and positional reference are assigned to the electromagnetic responses. Comparison with other measurement data shows what additional information TDEM provides. Areas with overlapping signals and ambiguous anomalies receive further professional assessment before recovery is planned.
Understand TDEM
Deep suspected points are assessed using measurement profiles, point geometry and depth references. Their position relative to the structure is particularly important for piles, retaining-wall alignments and boreholes.
The measurement does not automatically identify an object. A recovery decision may require separately planned exposure.
The point list, drilling and measurement geometry, achieved assessment depth and limitations remain linked to the depth profiles. Retaining structures, casing and utilities can restrict the volume that can be assessed. Planned exposure takes account of these actual limits of interpretation.
Assess the depth finding
A clearance area is worked systematically towards a defined objective. Relevant anomaly points are exposed, identified and directed to the appropriate further treatment.
Recovery of ordnance is a specific find procedure within this broader area-based service.
The anomaly identifier, exposure record, assessment of the finding and clearance plan retain the same positional and depth reference. Resolved points, ordnance-related finds and unresolved areas are given a traceable status. The find procedure thus remains part of the area record.
Explore the clearance objective
Where ordnance surveying during construction is professionally suitable, each layer is technically surveyed and the results professionally assessed before soil is removed under additional visual observation. Surveying is repeated before the next excavation stage. Anomalies lead to the defined stop points and a separate assessment of the find.
Monitoring does not replace the qualifications required for recovery; it ensures that the find area is transferred in an orderly manner to the appropriate specialists and authorities.
View construction monitoring
Following identification and clarification of responsibilities, permitted safeguarding, recovery and handover steps are carried out by persons with the appropriate authorisation and certification.
The find point, condition, work, bodies involved and effects on the project are documented traceably.
The responsible person establishes the identity and transportability of the ordnance found. If it cannot be transported, work at the find location is stopped and the competent ordnance disposal service arranges further measures. Collection, transport or handover are not determined from an anomaly assessment alone.
Discuss the recovery situationTreatment of a find point does not depend solely on an assumed object description. The condition of the find, its surroundings and the project situation determine which measures are permitted and technically possible.
In a planned project, ordnance recovery may follow a georeferenced survey, exposure at a target point, area clearance or work during construction. This requires unambiguous assignment to a point and area, controllable access, appropriate protective measures, qualified personnel and a documented decision on how the object is to be handled further or handed over.
A distinction is made between a measurement signal alone, a partially visible object and a professionally identified find.
This stage determines whether further detection, exposure, coordination with authorities or recovery is required.
Coordinates, elevation reference, orientation, soil cover and distance from structures or utilities are documented as far as possible.
Unclear location information is technically checked before planned exposure.
Visible condition, soil, water, corrosion, adjacent interfering objects and possible movement during discovery are taken into account in the professional assessment.
Only qualified persons carry out the assessment, which remains specific to the find in question.
The working space, retaining structures, slopes, dewatering and safe access must allow controlled work.
If access is inadequate, the necessary construction conditions are established first or the procedure is adjusted.
Utilities, foundations, traffic areas, buildings and other assets to be protected influence the secured area and organisation of work.
Current as-built information is checked against the actual find point.
The planned activity must be covered by the company's authorisation and the responsible person's certification.
Public-authority duties and responsibilities under state law are considered separately.
The project location and find situation determine which body must be informed and who decides on defusing, demolition, destruction or further measures to avert danger.
Contact details and the order of communication are clarified before planned work begins, wherever possible.
The receiving body, time of handover, find identifier, documents and further handling are recorded in a continuous chain of documentation.
The project report distinguishes the find point dealt with from other suspected and remaining areas.
A traceable find file connects initial data, the actual condition of the find, responsible decisions and further handling. It must also remain understandable to project participants involved later.
The completion record describes the object recovered or handed over, the point dealt with, the surroundings of the find, the bodies involved and the effects on the project. This documentation makes no blanket statement about the entire area; neighbouring suspected points and uninvestigated areas must be assessed separately.
If work on the find forms part of a clearance operation, the recovery and handover record is linked to the clearance record and the current anomaly status. Recovery at an individual location does not extend conclusions to neighbouring or unworked areas.
The project, construction area, point identifier, coordinates, depth, construction condition and time of discovery establish the spatial and temporal context.
The find location is linked to the current site or clearance plan.
The survey method, anomaly number, measurement evaluation, grounds for suspicion and known interference factors are assigned to the find procedure.
For an unexpected find, the circumstances of discovery and the last working condition are documented.
Working space, access, equipment used, retaining structures, dewatering and key work steps are recorded so that the procedure remains professionally traceable.
Unplanned movements or changes in the surroundings of the find are expressly recorded.
The type of object, visible condition, responsible person and decision on further responsibility or work are documented.
Uncertainties are not concealed by blanket descriptions.
Permitted recovery steps, the receiving body, handover, preparation for handover and relevant communication are recorded with the date and find identifier.
Public-authority measures are documented as a separate stage of responsibility.
The conclusion describes which local work has been completed and whether further surveying, clearance or an authority decision is still required for neighbouring areas.
It is not generalised beyond the point actually dealt with and its surroundings.
The find file documents what information was available at each stage, who made the professional decision and how work on the find was connected to the remaining clearance or construction project.
The commissioned service, find or suspected situation, affected area and intended handover arrangements are recorded as the starting position.
Services outside the agreed or authorised scope are not silently included in the commission.
The responsible person, personnel deployed and their tasks are assigned to the specific find procedure.
The documentation distinguishes technical supervision, construction management, earthworks and authority decisions.
The time of the find, last equipment movement, safeguarding of the work area, further exposure and communication steps are recorded in chronological order.
This chronology supports later assessment of project interruption and resumption.
The find identifier, position, depth, visible condition, identification and professional assessment are documented in a suitable form.
The record contains only observations and assessments that were actually made.
Bodies involved, contact persons, time of handover and documents provided are recorded traceably. Clearance records and responses from authorities are assigned to the same find identifier and version of the area definition.
This makes it clear when responsibility passed to another competent body.
The completion record describes which local work on the find has ended and which further investigations or clearance work remain for the area.
Planning and construction management thus receive a clear basis for the next project step.
The specific process depends on the type and condition of the find, project location and responsibility. For planned work, data assessment, protective arrangements and the permitted scope of services are agreed before exposure.
Position, depth, project condition, previous measurements and circumstances of discovery are recorded without changing the object through unauthorised actions.
Local ground disturbance is stopped immediately. Access, equipment movement and further work are controlled in accordance with the risk assessment and reporting procedure.
Survey data, clearance plan, site plan, authority contacts and company authorisation or personnel certification requirements are brought together. Preparation of planned work also establishes which historical questions remain unresolved. Required aerial photographs and other historical sources are researched and evaluated for the area concerned. These findings are assigned to the find or suspected point and the planned work. They supplement the existing survey data and support preparation of further action that is professionally and legally permitted.
Access, excavation safety, utilities, dewatering, protective area and required equipment are tailored to the specific point.
Exposure takes place within the permitted scope of services and in a manner that allows identification and further professional decisions under controllable conditions.
A certified specialist assesses the type and condition of the object and the permitted handling. Where responsibility lies with a public authority, the locally competent body is involved.
Permitted recovery, preparation or handover steps are carried out; further authority measures depend on the find situation.
The find point, work, bodies involved, handover and effects on the remaining project area are documented and provided to the client and construction management.
The find point is a spatially limited but safety-critical unit of work. Any change to the object or its surroundings may affect the professional assessment and is therefore controlled.
Project management must also distinguish between work on the find and resumption of construction. Local recovery may be complete while adjacent areas still require surveying or clearance. Construction management and the client therefore receive a spatially limited conclusion with clear conditions for subsequent ground disturbance.
Planned ordnance recovery begins with an unambiguous point identifier. It may originate from an anomaly list, depth profile, clearance section or find report during construction. Coordinates, depth reference and data source must agree before access to the object is established.
Exposure is planned to keep the surroundings stable and accessible. Utilities, retaining structures, water ingress and adjacent structures may have a greater influence on the work method than the presumed object size. The construction condition is documented before and during the work.
As soon as the object can be professionally assessed, the responsible person decides how to proceed. This involves three questions: Is further exposure permitted? Can the object be recovered within the scope of commercial activities? Or does the competent state body take over the work? An anomaly description used in advance must not replace this decision.
During recovery, the find identifier and object remain linked through all subsequent steps. Preparation, transfer or handover are documented so that the recipient, time and transfer of responsibility are traceable. Defusing, demolition or destruction are carried out only by the bodies responsible and authorised to do so.
After the find procedure, the local work area is reassessed within the area-wide or construction context. Recovery of one object does not automatically answer the question of further ordnance. An accumulation of finds, historical circumstances and remaining anomalies may require additional surveying or clearance.
Where several companies are involved, handover must also be organisationally clear. The earthworks company confirms the current working condition, the specialist company documents the find point and work, and construction management carries the information into the site diary and scheduling. This makes it clear which activities at the find point have ended and which sections remain undisturbed pending a further decision.
The anomaly, find report and documentation use the same unambiguous identifier and positional reference.
Soil, water, utilities, structures and the last equipment movement are recorded as part of the professional assessment.
The space for exposure, slopes, retaining structures and access route must permit a controlled assessment.
Qualified specialists assess the actual type of object; it is not inferred from a measurement signal.
Condition, type of find, authorisation, certification and regional requirements determine the further handling permitted.
Access and construction work are adapted to the specific find point and its surroundings in accordance with the risk assessment.
The receiving body, time, find data and documents handed over remain part of the same chain of documentation.
After the individual find, an assessment determines whether remaining anomalies or suspected areas require further clearance.
Explosive ordnance disposal comprises several professionally distinct steps. Clear assignment prevents confusion between detection, clearance, recovery and public-authority measures.
Answers: Whether there are spatially substantiated grounds for suspicion and what range of objects may be present.
Does not answer: Whether an object is currently present at the specific find point.
Answers: Where measurable anomalies or relevant signals occur within the defined area.
Does not answer: The actual type of object behind an anomaly.
Answers: Which object is present and which specialist or responsible body takes the next steps.
Does not answer: Whether work on the entire project area has been completed.
Answers: How an identified find that may be handled within the specific framework was safeguarded, recovered or handed over.
Does not answer: Public-authority defusing, demolition or destruction outside the scope of commercial duties.
Answers: How a defined area or soil volume was systematically worked towards a clearance objective.
Does not answer: Every further measure concerning a particular individual find.
Answers: Which public-authority measure is ordered and carried out for the relevant find situation.
Does not answer: The preceding private planning and technical work on the remaining project area.
Magnetometric measurements record local changes in the Earth’s magnetic field and can map ferromagnetic anomalies spatially.
Steel, reinforcement, utilities and scrap may mask signals. Anomaly and interference-zone plans identify the survey area and restrictions; these alone do not determine the object type.
TDEM records time-dependent electromagnetic responses from conductive bodies. This information can supplement selection and assessment of suspect points.
Coil geometry, distance to the object, depth and technical installations influence interpretation. Measurement data and the site plan document evaluated anomalies; they do not establish a certain object identification.
Ground penetrating radar shows subsurface reflection contrasts and can provide suitable information on layers, utilities, installations or fill.
Ground conductivity, moisture and heterogeneous ground restrict range and interpretation. Profile and site plans distinguish identifiable structures, uncertainties and survey limits.
Deep suspected points, piles, anchors and retaining-wall alignments are investigated using measurement geometry suited to the volume affected by the works.
Borehole position, arrangement, measurement length, casing and interference determine the volume considered. Point and depth references remain part of the result; an anomaly is not yet an identification.
Under suitable working conditions, technical surveying and a professional decision are followed by layer-by-layer excavation under additional visual observation. A further survey is carried out before the next layer. Anomalies are assigned to the specific construction condition and assessed separately.
Observation alone is insufficient. The record relates to the layers and sections actually investigated. Anomalies lead to the agreed stop points and appropriate further action by specialists or authorities.
Recovery planning identifies the find point, available findings, permitted scope of activities and responsible contacts. Decisions and handovers are documented together with the working condition at that stage.
FONTANA-EOD undertakes planned exposure and recovery services only on the basis of a clear task. Measurement data, surroundings of the find, regional reporting procedure and existing clearance documents are brought together before work begins.
The responsible specialist decides within their certification and the commissioned scope of activities. As soon as subsequent public-authority action is required, the condition of the find and information are handed over to the competent body.
For the client and construction management, documentation covers more than the object. The area dealt with, project interruption, remaining suspicion and conditions under which adjacent work can continue are equally important.
The measurement signal, exposure, find and handover remain assigned to the same location identifier.
Identification and further handling are carried out by appropriately certified persons.
Commercial services and public-authority duties are clearly distinguished according to the find situation.
Access, equipment movement and construction work are coordinated with the secured area and risk assessment.
The receiving body, time, find data and communication procedure are recorded traceably.
The individual find, remaining anomalies and further clearance requirements are assessed separately.
Before planned work, reporting of finds, protective measures and permitted specialist services are coordinated with named contacts. In an unexpected find situation, work is stopped immediately and the competent bodies are informed.
Commercial companies work within the authorisation and certification framework under explosives law. Depending on the federal state and find situation, state ordnance disposal services and other authorities undertake public-authority duties, particularly where defusing, demolition, destruction or special measures to avert danger are required.
Provides project documents and grounds for suspicion, commissions permitted specialist services and ensures the necessary project participants are involved.
Stops or restricts work in the affected area, keeps the surroundings of the find undisturbed and coordinates personnel, equipment and information on site.
Checks documents, plans permitted exposure and recovery steps, carries out the commissioned specialist service and documents responsibilities, handover arrangements and results.
Assesses the object and its condition, manages safety-critical work steps and decides within the scope of their appointment, certification and specific task.
Receive reports of finds under local procedures, secure public areas where necessary and coordinate the competent specialist or state bodies.
Depending on the federal state and find situation, undertakes public-authority duties such as specialist handling of finds, defusing, demolition, transport or destruction.
Depending on the project location, the public order authority, KBD, KMBD or KRD are involved in information enquiries, reporting finds and subsequent hazard response. Building control may be involved in the construction approval process. Responsibilities, contacts and existing requirements are clarified for the specific proposal.
Found ordnance involves explosives law, occupational safety, state law on averting danger and, where applicable, other areas of law. The specific procedure is therefore determined by the activity, object, condition and project location.
For found ordnance, the German Explosives Act covers activities including searching, exposure, recovery and storage. Commercial companies require appropriate authorisation under § 7 SprengG for activities subject to authorisation; responsible persons must meet the requirements of § 20 SprengG for the relevant tasks. The 1. SprengV supplements the organisational and professional framework.
State ordnance disposal services act within the responsibilities defined by the respective federal state's law. The body that takes over a find, the reporting required and who decides on defusing or destruction vary according to the federal state and specific find situation.
If an unexpected object is found during ordinary construction work, it is not touched, moved or cleaned. Work is stopped immediately and the immediate area is vacated. In Germany, the police are contacted on 110; outside Germany, the local emergency procedure applies. For planned clearance operations, the risk assessment, clearance plan, occupational safety and documentation govern cooperation before work begins.
DGUV Information 201-027 supports risk assessment and the definition of protective measures during ordnance clearance work. For a planned recovery task, these protective measures are related to the actual activity and work area.
DGUV Rule 113-003 concerns dismantling or destroying explosives or corresponding objects and also includes disposal of found ordnance. The requirements relevant to recovery or subsequent activities are assessed according to the specific commission and the responsible organisation.
The Baufachliche Richtlinien Kampfmittelräumung (BFR KMR) structure investigation, planning, execution and documentation within their scope on federal properties. For a recovery task, the commission, find point, work status and remaining follow-up questions are connected traceably.
The company and commissioned activity must be covered by the required commercial authorisation.
Technical supervision and specific tasks are assigned to persons with appropriate specialist knowledge and appointment.
Reporting finds, public-authority work and handover follow the locally competent structure.
The find location, work, handover, unresolved areas and further project decision are documented together.
The clearance plan, data basis, responsibility, access, protective arrangements and communication with authorities are clarified before exposure.
Work in the affected area is stopped, the object is left unchanged and the local reporting procedure is initiated without avoidable delay.
The documentation places the find point in the context of the entire suspected area and identifies further investigation or clearance tasks.

The find location remains linked to the anomaly identifier, position, depth, construction condition and responsible procedure.
Assess the finding and project context
After handling the find, completed, unresolved and reassessed points are updated in the clearance plan.
Compare the clearance area and work status
The last equipment movement, excavation layer, affected area and project interruption are recorded as part of the chronology of events.
Coordinate monitoring during construction
Borehole data, suspected depth and structural geometry are brought together before controlled exposure.
Assess depth-related investigation
New findings may change the previous assessment of suspicion and require an extension of the technical investigation.
Assess historical indications
The report shows which service has been completed and which assessment or clearance tasks remain within the area.
Assign find and handover documents

Ordnance recovery forms part of a broader project process. Depending on the initial situation, assessment of suspicion, technical surveying, area clearance, excavation monitoring or more detailed documentation may be required.

Understand recovery in relation to investigation, surveying, clearance and documentation.
Compare services
Compare the find situation with former use, known events and other suspected areas.
Investigate suspicion further
Select ground-penetrating radar, magnetometry and TDEM according to target object, soil and interference.
Select a method
Assess the spatial position of deep anomalies, pile locations and retaining-wall alignments more closely.
Survey at depth
Provide professional, documented monitoring of earthworks in areas that cannot be fully assessed in advance.
Supervise excavation
Work on several suspected points or affected soil areas towards a defined clearance objective.
Understand clearance
Prepare the find record, handover chain, clearance plan and project-specific conclusion.
Clarify documentation
Understand reporting procedures, responsibilities, project duties and frequently asked questions.
Open guidance
Understand work on finds in civil engineering, route infrastructure, energy, industry, municipal projects or site development.
Choose the project settingThe enquiry includes the project location, affected area and existing reports. Identify the responsible contacts and current work status. FONTANA-EOD can relate its specialist contribution to this information. Missing information is identified for further coordination.
The participants agree the scope and handover arrangements of specialist work. Plans used and information provided remain assigned to the task. Changes are communicated in good time. The documentation makes clear which information was available for each stage of specialist coordination.
The handover connects the documented work status with the affected areas and conditions. Construction management compares this information with the forthcoming work. Further specialist or authority decisions remain assigned to their respective subjects. Outstanding tasks are addressed separately.

State the location, project area and affected section. Add the contacts for construction management and specialist bodies already involved. The regional overview helps with orientation. Existing documents and the current information remain decisive for specific coordination.

Reports and project-specific information are provided with their spatial appendices. The responsible participants clarify outstanding questions for the specific case. Information concerning other areas or earlier measures remains distinguishable. This gives the specialist company's current contribution an unambiguous context.
The report and spatial appendices are used together. They show the area actually dealt with and the applicable conditions. The next construction activity is compared with them. A short completion label alone does not fully describe the professional status achieved.
Explore results and terminologyThe ordnance specialist company documents its agreed contribution. Further decisions are provided by the bodies responsible for them. The project organisation brings together the necessary information. Different tasks remain recognisably assigned even within a shared process.
Understand the service scopeAdditional areas or different intervention depths are compared with the existing documents. Earlier results retain their original scope. Any new specialist requirement is assigned to the specific change. The responsible participants agree further work.
Explore results and terminologyTechnical information
The brochure explains the process from an anomalous measurement point to professional investigation and recovery. It describes coordination of the work and documentation of the results.

Surveying locates and assesses measurable anomalies. Clearance means systematically working an area or soil volume to a defined clearance objective. Recovery concerns the specific handling of an identified object, including permitted safeguarding, collection and handover steps. These services may follow one another but have different evidence and responsibilities.
Work in the affected area is stopped immediately. The object is not touched, moved or cleaned. Access and further equipment movement are prevented, construction management or those responsible for the project are informed, and the local reporting procedure to the police, public order authority or competent ordnance service is initiated.
Leave the immediate area and, in Germany, call the police on 110; outside Germany, the local emergency procedure applies. Others are warned without putting oneself at risk. The competent authorities determine further action; a project enquiry does not replace reporting a find.
Commercial activities involving found ammunition require a suitable company authorisation framework and appropriately certified responsible persons. The steps a private specialist company may carry out depend on the activity, object type, condition and rules of the German state. Public-authority tasks are performed by the respective competent state bodies.
Defusing, detonation and destruction are not automatically included in a commercially commissioned recovery service. Depending on the find and German state, these tasks belong to state ordnance disposal services or other specifically competent bodies. The private specialist service prepares find data, the working area and handover so that the transfer of responsibility is traceable.
It includes the find point, time, position and depth, original data, circumstances of discovery, exposure and working state, specialist identification, responsible persons, safeguarding and recovery steps taken, bodies involved, handover and effects on further surveying, clearance or construction work.
Key factors are find status, position and depth, access, ground and water, shoring, utilities, people and assets requiring protection, necessary exposure, object type and condition, qualifications and equipment required, coordination with authorities, handover procedure, project interruption and documentation scope. For unresolved or urgent finds, a blanket time or cost commitment is not technically reliable.
In an acute find situation, the local reporting procedure takes priority. For planned work following surveying or as part of a clearance operation, professional assessment requires unambiguous information on the find and project.
Provide the project address, site plan, find or anomaly identifier, coordinates, elevation or depth reference, current construction condition and affected work area.
For a point not yet exposed, the data source should be clearly identified.
Helpful documents include aerial photograph analysis, survey report, raw or evaluated data, anomaly list, clearance plan, field records, photographs of the working surroundings and previous professional assessments.
Previous reports of finds or contacts with authorities are specified with the contact person and current status.
Information is required on retaining structures, slopes, groundwater, utilities, buildings, traffic areas, construction machinery, access and possible restrictions on the working space.
This information determines exposure planning, protective arrangements and coordination with the construction company.
The existing work status is decisive: an unresolved anomaly, a suspected point to be exposed as planned, an object identified during clearance or an unexpected find during construction. FONTANA-EOD uses this to assess which commercial specialist service is possible, which qualified responsibility is required and which state body must be involved.
Measurement signal, partially exposed, professionally identified or already assessed by an authority.
Coordinates, depth, excavation, utilities, water, retaining structures and adjacent assets to be protected.
Responsible specialist, client, construction management and authority already contacted.
Exposure, recovery, handover, extended clearance or further technical investigation.
Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.
FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.