Clearance plan and clearance documentation

After an ordnance survey, clients, planners and construction management need a traceable record of the service carried out and the limits of its conclusions. FONTANA-EOD connects preparation of clearance work with documentation of the scope actually addressed. Send your intervention plan and existing investigation documents so that we can agree the required planning or completion records with you.

Define the clearance objective

Define the clearance objective and scope.

Record the work

Document the work actually carried out.

Identify limits

Make conclusions and limits understandable.

Technical assessment

What the clearance plan and clearance documentation each record

The clearance plan describes the prepared task with its basis, methods and control requirements. Clearance documentation records the work actually carried out, results and limitations. Its conclusions apply to the stated geographical and depth scope under the documented conditions. Before the next construction task, an assessment establishes whether this status covers the planned intervention or further specialist work is needed.

Project references

Selected project examples

Project components

What documentation includes

The reports, plans and records needed are agreed for the commission. They must subsequently show what was planned, what was carried out and which questions remain unresolved.

Commission and assessment basis

Project name, client, working period and relevant documents provide the report's context. The investigation or clearance objective is stated. Preliminary findings and adopted third-party data remain recognisable as such so that new services and earlier findings are not conflated.

Areas, depths and geographical reference

Overview and detailed plans show the areas worked on. Coordinate references, boundaries and elevation or depth references must be understandable. Excluded subareas, obstacles and uninvestigated depths are identified separately so that later planning can use the conclusions correctly.

Methods and execution conditions

The documentation describes the methods used and the settings and conditions relevant to the result. Depending on the service, these include measurement arrangement, investigation geometry, working depth and interference identified. The information required depends on the specific method.

Measurements, suspected points and findings

Measurement documents, anomalies, investigated points and relevant finds are assigned spatially. Observations, assessments and subsequent measures must remain distinguishable. Where included in the commission, information on work and handover and the relevant records are also included.

Checks and deviations

Agreed checks and their results are recorded. For deviations from the plan, additional measures and changed conditions, the affected area or work step is identified. This shows which parts of the planned procedure were carried out or adjusted for professional reasons.

Final assessment and appendices

The conclusion answers the initial question within the scope actually worked on. Areas not conclusively resolved and necessary subsequent measures are identified. Plans, tables, relevant photographs and records support the conclusion without mixing different work statuses.

Implementation and coordination

Prepare, compare and retain documentation for later projects

Quality is demonstrated when professional conclusions can still be unambiguously assigned to an area, service and work status after handover.

Agree recipients, plans and data formats

Clarify recipients, required plans and data formats when commissioning. Construction management needs different overviews from a technical review. The agreed structure supports both ongoing coordination and later filing.

Prepare a coherent completion file

Compare planning and execution

The completion report is related to the clearance objective and actual execution. Changes, limitations and outstanding measures remain visible. This makes it possible to assess which conclusions the data support and where additional work is needed.

Compare the scope of conclusions with the intervention

Retain documents and reassess them for new interventions

Clients should keep the complete documentation permanently available. Later replanning requires a new assessment of whether earlier results cover the new intervention. The agreed documents provide an important basis but do not replace this assessment.

Assess further use of the documents

Before deployment planning: the basis is insufficient

Historical findings are missing for a new area or existing reports concern another intervention. The client and specialist company relate existing documents to the actual construction task. The suspected situation and outstanding investigation needs determine the next professional step. The project file shows the basis available and the investigation still required. A technical completion conclusion is not derived from historical assessment alone.

Clarify the grounds for suspicion and further investigation

During work: measurement limits or findings remain unresolved

Utilities, ground structure or metal interference sources can restrict the survey used. The responsible specialists assign these conditions to the affected areas. Measurement data, investigated findings and unresolved zones are documented separately. This determines the additional work needed before a specific intervention. The report retains limitations and remaining uncertainties; an incomplete investigation does not produce an unrestricted conclusion.

Assess survey results and remaining limits

Before the next intervention: construction plans have changed

A deeper foundation, relocated route or new excavation section may exceed the previous scope of conclusions. Planners and construction management compare the current geometry with documented areas and depths. The specialist company assesses whether existing results suffice or further investigation is needed. The records should provide a professional basis specific to the new intervention. Outstanding measures and residual risks remain visible for the next decision.

Coordinate the changed construction task within the project process

When are a plan or completion documents needed?

Preparation, ongoing work and later use ask different questions of the same documents. Existing document status should therefore always be connected with the current purpose of the project.

Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

A measure needs preparation

Compile the planned use, areas and ground interventions. Identify investigations already available and gaps in knowledge. Preparation must show the task still to be resolved. State the desired later completion conclusion early so that service scope and documentation can be coordinated with it.

Assess the construction task and documentation needs
Two people discussing plans at a table beside a vehicle on a construction site.

A completed section needs handover

Assign the services carried out to the specific section. The report, plan and accompanying appendices must describe the same status. The next construction task needs an understandable conclusion about the areas covered and continuing limitations. A blanket status for the entire property cannot replace this assignment.

Place handover within the project process
Survey cart on an open construction area, with piles of soil in the background.

Earlier documents are to be reused

Assess the complete original task and work actually carried out. Compare documented areas and depths with new planning. Even an unchanged property may now be used differently or affected at greater depth. Additional findings or changes require professional assessment before old conclusions are related to the new project.

Have existing documentation assessed

Determine required records from the commissioned service

A completion document must answer the specific task. Historical analysis, depth-related investigation and a service during construction produce different bases. FONTANA-EOD agrees with clients and planners which conclusions are needed for the intended intervention and which documents should provide a traceable record of the service carried out.

Workstation with two screens showing aerial photographs and maps, and printed documents on the desk.

Historical findings as a basis

An existing analysis can explain the knowledge available for an area. Further use must retain its origin, investigated area and conclusions. Historical assessment does not become an execution record merely by being appended to the completion file. Identify the later investigation based on these findings and the questions actually addressed.

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Records for deep interventions

For individual foundations or other deep interventions, spatial references are particularly important. Documents must show which points or areas were investigated and how the conclusion relates to the intended construction task. A report title or general area description does not replace this comparison. Compare the final intervention plan with the investigation areas actually documented.

Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Documentation during excavation

Work during construction must be assignable to the affected section and work status. Describe the intended specialist activity and results to be handed over in the commission. Later documentation should reflect the procedure actually used. Changed excavation limits or working methods are considered with their effect on the agreed service scope.

Bring records together

From the initial basis to a supported conclusion

The record connects the specific construction task with the data collected for it and the professional assessment. Planning, actual work and conclusions remain distinguishable.

Initial information and investigation commission

The site plan, land parcel, construction area or route define the task. Historical documents and earlier investigations are adopted with their appendices. The commission records the question the new service should answer and the results needed. Missing information or contradictions are identified as unresolved matters.

Execution and findings records

Measurement data, survey results and investigated finding points are spatially assigned. Documentation also shows relevant operating conditions and deviations from planning. Where recovery or clearance form part of the commission, their findings and records are connected to each area. A single measurement does not replace professional assessment of a finding.

Report, plans and the next decision

The report, results plans and any clearance records relate to the same work status. The conclusion identifies areas, depths and remaining limitations. For a new construction task, this information is compared with the intended intervention. The Project documents and the Clearance plan retain their respective functions. For more detail, the page “ Survey report and clearance record ” explains the report structure, while the page “ Ordnance clearance confirmation ” explains the scope of its conclusions.

From the planned clearance objective to a usable completion file

The plan and completion documentation are produced at different times. Their connection becomes understandable when preparation, execution and later use of the same task remain traceable.

01

Clarify the construction task and desired conclusion

Describe the project, planned use and affected interventions. State the decision the documents should support. This starts professional coordination on the scope and limits of the requested service. Relate the question to the land parcel, construction area or route section and intended intervention depths. A later user must be able to recognise whether an entire construction area, individual borehole points or only a particular excavation section is to be investigated.

02

Compile existing findings

Provide historical analyses, earlier investigations and authority documents with their appendices. Their origin and geographical reference remain recognisable. Missing or unclear information is included as unresolved matters in further preparation. Historical research and aerial photograph analysis can establish grounds for suspicion but do not yet demonstrate technical work on the ground. Check that appendices actually show the area mentioned in the text. Contradictory area information or missing plans are clarified before an investigation based on them.

03

Agree the procedure and documentation

Professional planning connects the objective with suitable services and actual conditions. Agree at the same time which reports, plans and data are needed, so that later handover is considered when commissioning. Utilities, ground structure and possible interfering objects are assessed against search objective, depth and accessibility. This determines suitable surveying or another professionally planned method and its limits of use. The agreed documentation must then demonstrate precisely this execution.

04

Record execution and changes

Documentation accompanies the service actually provided. Deviations are assigned to their section and cause. Additional work and new findings remain distinguishable from older documents adopted. Measurement data and investigated finding points are assigned to their locations. For work during construction, the section and technical procedure used remain identifiable. Merely observing an excavator does not become a technical survey record through a later log entry.

05

Assess results within the agreed scope

Completion answers the initial question from the work performed. Spatial and methodological limits remain part of the conclusion. Unresolved questions are described so that further professional needs can be related to the project. Assessment connects documented execution with the original objective. An anomalous measurement, investigation of a finding point and the conclusion drawn from it are professionally distinguished. Remaining measurement limits, inaccessible areas and unresolved findings stay visible for the next decision.

06

Hand over and reuse documents

The report and appendices are handed over with an identifiable status. Planners and construction management need the references relevant to their work. Later changes require assessment of whether the documented conclusion still covers the new intervention. Agree who receives the complete status and who coordinates questions on the next intervention. A later summary for a following trade must retain its source. It must neither extend a section-limited conclusion to a general property clearance approval nor omit existing limitations.

Keep the completion status traceable in the project file

A project file connects the commissioned task with the results actually handed over. It should remain understandable if other people take over planning or the project resumes later.

Commission and adopted information

Keep the relevant agreements and initial documents together. Adopted third-party reports retain their original sender and date. If only part of an earlier investigated area was worked on again, the documents must make this connection traceable. Older findings are thus not silently presented as a new service. Historical documents, measurement data and assessment of findings fulfil different functions. The file shows the basis for planning a new investigation and the findings added by later execution. An additional service receives its own reference to the commission and area worked on.

Report and appendices at the same status

A plan belongs to a particular report version. If appendices are supplemented or corrected, the version authoritative for further use should be identifiable. At handover, check that listed appendices are present and legible. An isolated plan or brief email cannot represent the context of complete completion documents in every situation. If the appendix register, plan name and file content disagree, the missing assignment is clarified before forwarding. Replaced and current versions remain distinguishable. Specify the change, such as an added area, corrected depth reference or findings record supplied later.

Trace subsequent decisions

Record which unresolved question the report should answer and whether additional coordination is needed. The professional completion conclusion, authority response and decision on the next construction section retain their own functions. Later use should show the documents on which each decision was based. For clearance actually carried out, the completion report and associated clearance record may contain different parts of the evidence. They are brought together with relevant location and results plans. The conclusion identifies the scope worked on and necessary subsequent measures. Competent bodies make the required authority decisions.

The area and depth covered by each plan version

A report's conclusion becomes usable only when its spatial reference is traceable. Names, boundaries and reference information must agree for comparison with construction planning.

Clearance documentation records what was actually carried out and established. As a professional completion record, it must match the agreed commission. A conclusion applies to the stated areas, depths, objectives and methodological conditions. It cannot be transferred generally to neighbouring areas or later, deeper interventions.

Whether an additional authority statement or decision is needed depends on responsibilities and procedural circumstances. The specialist company documents the commissioned service; competent bodies make required authority decisions. The BFR Kampfmittelräumung explain the role of the clearance plan and the evidential function of documentation within their scope on federal properties.

Land parcel, construction area and area worked on

A land parcel describes a property unit; the commissioned investigation area may differ. Even within a construction area, subareas may have been worked on differently. The report and plan should show these differences. For a later enquiry, identify the actual intervention and compare it with the documented working boundary. A matching address alone is insufficient. For a measurement grid, the limits actually covered are compared with intended excavation areas. Individual borehole points need their own position and depth reference. An overview must not combine these different investigation geometries into a continuously worked area without explanation.

Read a depth together with its reference

A depth is unambiguous only together with the reference surface or elevation used. Today's ground surface may have changed from the earlier work status. Planning must account for this in filled, excavated or progressively reshaped areas. Use the report's information and clarify unclear references from the complete documents before deriving a conclusion for the new intervention. Compare the current section with the corresponding results presentation. Compare the intended excavation base or foundation depth with the documented investigation scope. Planning and results documents are brought to the same elevation reference.

Exceptions and unresolved subareas

Obstacles, inaccessible areas and methodological limitations belong to documented work status. They should not appear only in an isolated paragraph but remain identifiable for the affected area. Further planning must establish which next activity touches this limitation. An additional investigation or other measure is agreed for that specific question; general completion of a measure does not automatically resolve outstanding subareas. A utility may justify an excluded zone or an interfering object limit evaluation. The location is spatially identified for the next construction step. Clarification of actual investigation requirements and, if necessary, additional execution provide a new basis for the affected work.

Prepare the next step from existing document status

Further work depends on the information already available and the decision still outstanding. Describe this starting position as specifically as possible in your enquiry.

No clearance plan yet available

Provide the construction task and current knowledge. Professional preparation must clarify the task and missing information. A general request for clearance approval does not yet identify the planning scope required.

Compile planning information for the enquiry

A plan exists and execution is forthcoming

Provide the plan with its accompanying drawings and current construction sequence. Identify changes compared with the earlier status. The connection between planned services and completion documents needed later should be clarified before implementation.

Assign the required completion documents

A completion report already exists

Provide complete documents including appendices and describe the next construction task. Area, depth, objective and limitations matter for the comparison. A title or single sentence from the summary is generally insufficient.

Read spatial references and limits of conclusions

Planning has subsequently changed

Identify new areas, other depths or changed use compared with the previous status. Describe the work affected. FONTANA-EOD can clarify with you which professional assessment or additional work should be commissioned.

Coordinate changed planning with documents

Traceability through a precise working method

FONTANA-EOD connects the professional task with the documents required for it. A report is useful when clients, planners and construction management can correctly relate its conclusions to their project. Scope, work status and remaining questions are therefore described understandably.

Task before scope

The desired conclusion is connected to the actual intervention. This provides a professional justification for the required service scope and distinguishes it from general statements about a property.

Data origin

New results and adopted preliminary findings remain recognisably separate. The project file shows the basis used for each conclusion.

Limits in context

Limitations are explained with the affected area and task. They remain part of the professional conclusion at handover and during later use.

Referenced changes

Additional work is assigned to the previous status. A new version shows which documents are supplemented or replaced.

Understandable handover

The report, plans and appendices form a coherent status. Required recipients and file formats are agreed for the actual further use.

Safe communication

A new suspicion or find is addressed through the prescribed immediate reporting procedure. Later written work does not replace the necessary response on site.

Use documents at the appropriate coordination points

Different participants need the same documentation for different tasks. The professional conclusion should be retained even where a shorter overview is produced for construction.

Client and project management

They need a traceable connection between the commission, service provided and documents handed over. Identify who receives the completion file and ensures its later availability. Unresolved matters should be assigned to a responsible contact. Handing over a report alone does not decide every subsequent organisational or authority question.

Planning and construction management

For the next construction task, documented areas must match the current plan. When conclusions are adopted into working documents, spatial or professional limitations must not be lost. Unclear matters should be queried using the complete report version. Changed interventions are compared with the existing basis before the affected work.

Specialist company and competent bodies

The specialist company documents the commissioned work and its results. Further coordination or statements needed for the project depend on the specific procedure. Authority correspondence and private specialist reports remain clearly identified. Forwarding does not change a document's sender or function.

Include location and project context in handover

A professional completion record is prepared for a specific project. Location-related procedures and other participants' requirements must therefore be compared with actual documentation needs.

Illustration of a map of Germany marking Wesseling and Gersheim in front of a construction area, with construction plans and a hard hat beside it.

Location-related coordination

Identify the project location and bodies already involved. Existing correspondence with appendices forms part of the starting position for further work. Additional statements or coordination follow from the specific procedure. An application procedure from another jurisdiction should not be adopted indiscriminately.

Assess the region and existing requirements
Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

Requirements arising from construction

A development site, traffic area or technical installation may include different interventions and handover points. Assign documents to the areas actually affected. Other specialist tasks, such as ground investigation or utility planning, retain their own subject and responsible participants.

Assign project context and interventions

Read terms in the plan and completion documents correctly

Precise terminology helps comparison between planning, services carried out and the next construction task. The specific conclusion of the complete document remains decisive.

Clearance objective

It describes the intended task in relation to use, the affected area and defined scope. The objective must be distinguished from the actual work documented later.

Working boundary

It defines the spatial scope of a service. Property boundaries, construction limits and working boundaries need not be identical and must not be equated without assessment.

Completion conclusion

It summarises the professional results within the scope worked on. Methodological conditions, depth references and limitations remain part of its use.

Additional work

It relates to a further professional task, such as a plan change or previously unresolved subarea. Its results must be unambiguously assigned to the previous status.

Read initial information and results documents together

Historical findings and new investigation results remain recognisable in the documentation with their respective origins. For further construction, the service actually carried out is connected with its results documents.

Workstation with two screens showing aerial photographs and maps, and printed documents on the desk.

Knowledge before work

Historical analyses can contribute to preparation. Their conclusions must be read in geographical and professional context. Completion documentation makes clear which findings were adopted and which results were obtained through the new commissioned work.

Trace the historical basis
Two people with a tablet beside a marked construction area; plans lie in the foreground.

A service with an appropriate result

The type of investigation determines the information essential to the result. A general description replaces neither the actual procedure nor its connection to the construction task. The report should show which specialist service was provided within the agreed scope.

Connect services and documentation
Survey cart on an open construction area, with piles of soil in the background.

Documents for the next step

Provide the report and appendices together with an enquiry. Describe the question to be answered for planning or construction. Existing work status can then be compared with the actual next intervention.

Submit documentation for assessment
Person wearing an orange high-visibility vest on a marked construction area with small piles of soil
Person wearing an orange high-visibility vest with a MALÅ survey cart on grass

Questions about the clearance plan and completion documentation

The commission, work status and intended intervention remain decisive for professional assessment. The clearance plan, execution records and later reuse fulfil different tasks.

When should the scope of completion documentation be agreed?

Agree the required reports, plans, data and recipients when commissioning. The desired later conclusion must match the service scope and intended intervention. Changes during work are coordinated with regard to their effect on the documents needed.

Does a clearance plan replace completion documentation?

The plan describes the prepared task and intended procedure. Completion documentation records work actually carried out and the results. The two documents must relate to one another but fulfil different functions.

Does a conclusion automatically apply to the entire property?

The documented areas, depths, objectives and conditions are decisive. Working limits may differ from property boundaries. Assess the complete documents, including appendices and limitations, against the specific intended intervention.

How are unworked subareas considered?

They must remain identifiable with their geographical reference. Further planning must establish whether the next construction task affects these areas. Any necessary additional work is agreed according to the specific unresolved question.

Can an earlier report be used for new planning?

It may provide a basis if its origin, content and scope of conclusions are traceable. Compare the earlier work with the new areas, depths and uses. Changed interventions or new findings may require further professional clarification.

Is an authority decision needed in addition to the specialist report?

This depends on location, the specific procedure and the task to be clarified. Authority responses and private specialist reports must be clearly distinguished. Provide existing correspondence in full and clarify the further coordination required for your project.

Which factors determine the work required for documentation?

The scope and type of service, existing data, required plans, recipients and agreed output formats are important. Preparing older or incomplete documents may also require work. A reliable assessment needs the specific commission and document status.

What applies if a suspicious object is found despite existing documents?

Stop work immediately, do not touch or move the object and leave the immediate area. Keep others away without putting yourself at risk and contact the police on 110. Existing documentation can later be included in the professional assessment.

Enquire about the clearance objective and documentation needs with specific documents

A development site, a route or an individual foundation can place different requirements on the plan and completion documents. Send FONTANA-EOD the site plan, intended use, intervention depths and existing investigations. Add client or competent-body requirements where already available. We clarify with you which planning and completion documents your commission requires. We assess existing reports to establish whether they cover the intended areas and depths.

Construction task and interventions

Provide the project location, site plan and affected areas. State intended depths, construction phases and planned use. Mark changed areas compared with earlier plans. Show the land parcel, route and individual borehole points where available. Construction dates, utility plans, aerial photograph analysis and known requirements are assigned to their respective status, allowing documentation scope to be coordinated with the actual construction task.

Available documents

Include reports, results plans and authority correspondence with appendices. State the version currently used and whether documents are missing. Adopted third-party reports remain recognisable as such.

Decision required

Describe the unresolved professional question and intended next work step. Identify contacts, required recipients and known scheduling dependencies so that the requested scope can be agreed. Also state the requirements agreed for your project concerning Quality and safety.

GPR on a construction site
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.