Two people discussing plans at a table beside a vehicle on a construction site.

Assess survey reports and clearance records

Survey reports and clearance records show the investigation or clearance service actually documented. For the next intervention, the task, measurement, evaluation and result are connected with the complete plan appendices. Send FONTANA-EOD the documents with your specific question and current intervention plan so that we can agree the professional contribution needed.

Measurement

Understand the method and result.

Execution

Assign the work actually carried out.

Handover

Keep the report and plan appendices together.

Briefly explained

What distinguishes a survey report from a clearance record?

A survey report documents an investigation with its measurement method, evaluation and professional assessment. A clearance record describes the clearance work actually carried out within its scope. Names may vary according to the commission and requirements. What matters is which questions the documents answer and whether they jointly relate to the correct area, depth and task.

Project references

Selected project examples

Read the documents

Compare the task, investigation and result in the report

Reviewing documents must be distinguished from the agreed technical acceptance of the service carried out. For the next project decision, the task, measurement or clearance work, geographical reference and result are compared. Missing or unclear information is professionally clarified with the report author using the complete appendices.

Task and document type

Is it clear which service was commissioned and which status the document describes? Distinguish an interim status from a final result. The summary should match the report and must not conceal its limitations through a broader conclusion.

Spatial reference

Can measurement areas and work carried out be located on the accompanying plan? Check boundaries, exclusions and assignment to subareas. A clear site plan helps only if its legend uses the same terms and markings as the text.

Survey and interpretation

A survey report should make the investigation underlying its assessment traceable. Read the notes on interference and unevaluable areas too. A list of equipment or a graphic alone does not establish a conclusion for the construction project.

Work actually carried out

Assign execution documents to the relevant area and documented period. Planned and completed services must not be silently equated. Changes should show where actual execution differs from the original plan.

Results and unresolved areas

Check that the conclusion is supported by the documented results. Limitations and outstanding tasks belong in further project planning. When several partial reports are combined, unworked intermediate or peripheral areas must not be overlooked.

Appendices and version

Compare the appendix register with the files actually handed over. Are plans, tables and additional records present and clearly named? Clarify which version is authoritative where several exist. Retain the relationship between report and appendices during digital forwarding.

Understand results

Distinguish findings, assessment and conclusions

Read measurement findings, professional assessment and conclusions together. A single marking or isolated sentence cannot convey their full scope.

Measurement signal and professional assessment of findings

The measured anomaly and its professional assessment must be read separately. Do not independently assert from a marked location on a plan that a particular item of ordnance is present. The documented interpretation and any further results are decisive.

Read the measurement finding and report conclusion

A result applies within the investigated scope

The absence of anomalies in a described measurement area says nothing by itself about neighbouring areas not covered. Read the conclusion together with investigation depth, method limits and possible interference. If the connection is missing, request an explanation.

Check the investigated scope in the report

A daily record is part of the whole

A daily record may demonstrate execution over a particular period. The associated documents must be brought together traceably for the overall status. Whether an Ordnance clearance confirmation is included or needed separately can only be clarified from the specific task and documentation scope.

Bring all partial records together

Before planning: the report does not match the new intervention

A new excavation, route or foundation may exceed the documented area. The client and planners compare the current intervention with the full report conclusion and results plans. Historical grounds for suspicion remain distinguishable from investigations actually carried out. The specialist company assesses outstanding investigation requirements and their conditions. Coordination identifies the professional contribution still needed for the next construction decision.

Determine outstanding investigation needs

During construction: an unclear measurement limit or assessment

Utilities, ground structure and metal interference can restrict measurability. For the affected section, measurement presentation, assessment and actual work are read together. Give the author of the relevant document the exact reference. Necessary additions and remaining limitations are assigned to the area. Explaining a plan marking is distinguished from carrying out an additional technical investigation.

Connect the enquiry with the next work step

At handover: partial reports do not yet establish the overall status

Construction management and the following trade need the authoritative documents for their section. Daily records and partial reports are assigned by area, period and version. Missing intermediate areas and outstanding appendices remain visible. The report author and client clarify whether a consolidated completion document exists and what it actually covers. The traceable status is handed over with its limits and remaining questions.

Consolidate documentation for handover

Make the report usable for the next project task

Different participants read complete documentation with different questions. Describe its intended use so the professional explanation addresses the right point.

Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

Planning and tendering

Further planning needs the spatial limits of existing results. Identify the intended intervention and mark differences from the investigated status. The report can provide a basis for further tasks; a new service must be selected according to the unresolved question.

Connect the planned intervention and report
Two people discussing plans at a table beside a vehicle on a construction site.

Construction management and section changes

A handover during ongoing construction concerns which work is documented in which section. Compile the complete partial status and identify remaining uncertainties. A brief verbal status update should be traceable to its associated documents.

Place report status within the construction process
Survey cart on an open construction area, with piles of soil in the background.

Project completion and later use

For later use, the report, appendices and additional explanations must remain retrievable together. Record the version handed over and the documents' original purpose. A later project needs a new comparison with its actual intervention.

Discuss the complete document set

Connect the report conclusion with the service actually provided

Start with the task stated in the report. Only then can you assess which information about investigation, execution and evaluation your specific enquiry needs.

Two people with a tablet beside a marked construction area; plans lie in the foreground.

An investigation is described

Check the investigation objective stated and the areas to which the results relate. Naming a method alone does not answer whether the present construction task is fully covered. Measurement presentation and the associated professional explanation should be available together for enquiries. The BFR KMR A-4.1 distinguish clearance objectives and methods. A method name explains the professional context but does not yet demonstrate the scope actually provided. This must be traceable in the report with results and accompanying appendices.

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Individual deep interventions were considered

For point-based documents, the connection between the named point, site plan and conclusion must remain recognisable. An overview of all planned points must be distinguished from a presentation of points actually worked on. For unclear matters, state the specific point identifier and report reference.

Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Work was monitored during construction

Assign records to the relevant section and period. The description of completed work should be distinguishable from the next planned excavation. If partial statuses are combined, unresolved sections must remain identifiable.

Completion and forwarding

Forward complete reports, plans and data

Agree early which documents and data the project needs. Not every handover has to use the same file structure.

Define recipients and purpose

Identify who needs completion documents for which task. Construction management needs an understandable reference to the next intervention; later planning must be able to trace the scope of the earlier measure. Therefore pass limitations on together with the result.

Hand over plans and data with their references

Clarify required exchange formats in the commission. Georeferenced data must have a traceable spatial reference. An additional exported graphic does not automatically replace the agreed specialist data. Conversely, an uncommented collection of data does not replace a readable report.

Formulate specific questions

If something is unclear, refer to the document, version, page or plan area. For an excluded subarea, ask about its documented work status and remaining clarification required. The documentation during construction places such partial statuses within the construction process.

From the received report to a clarified enquiry

An orderly review helps coordination with the author and other participants. It begins with the specific use of the documents and ends with a traceably handed-over status.

01

Identify the purpose and available documents

Describe the decision you want to prepare. State whether you have a complete report, partial record or only an extract. Name the location and construction task. Distinguish a question about understanding the existing report from a new technical task. If construction is planned in an uninvestigated area, a linguistic explanation of the old result is insufficient. The enquiry therefore identifies the affected part and contribution needed for the next construction decision.

02

Compare version and appendices

Compare the cover, version details and appendix register with the files actually available. Identify missing components. A similarly named file from an older procedure is not silently substituted. Check particularly whether the specified plan version was supplied and whether a later addition replaces individual appendices. A date from the filing system does not reliably describe professional status. Contradictory descriptions are clarified with the author and the authoritative version assigned to the existing document set.

03

Trace the initial information

Check the historical findings, plan versions or earlier investigations to which the report refers. Often an exact description of the missing basis is sufficient for an enquiry; assumptions about its content do not help. Historical analyses can explain the reason for investigation; survey data and clearance records document other work steps. An earlier conclusion quoted in a report is therefore read with its origin and limited scope. Ask the author which appendices underpinned the assessment and whether they were adopted for the current planning status.

04

Read the service carried out and its result

Assign the documented method and actual work to the described area. Read the result with its limitations. Record unclear connections as specific professional questions. Consider whether measurement presentation, assessment of findings and execution documents concern the same spatial status. A list of recognised anomalies and an overview of finding points actually investigated fulfil different tasks. The enquiry identifies the missing connection and the section or point to which the required conclusion should relate.

05

Coordinate the explanation with participants

Provide the relevant passage together with its plan appendix and the current intervention. Identify the scope of answer needed. Additional professional work can then be tailored to the question actually remaining. The report author can explain a term or legend. Whether the present construction task needs an additional investigation is assessed instead against the new intervention and the actual existing scope of conclusions. These different questions should remain distinguishable so an explanation is not treated as evidence of an additional service.

06

Pass on the clarified status

Connect additional answers with the original document. Tell participants which version is used for the discussed task. Outstanding questions remain expressly identifiable at handover. Name the answered question and associated appendices. If only one passage is explained, the other original limitations remain. A professional correction or replacement plan is assigned to its actual scope of change; a larger investigation area must be supported by the corresponding execution records.

Compile a readable document set for the project file

Filing should preserve the professional context. A later reader must be able to trace which documents belong together and which question they answered. The measure-specific documentation under BFR KMR A-6.1 connects report structure, scope, data quality, data structure and formats within the relevant scope. Handover therefore clarifies which documents are agreed and which information recipients need for professional use.

Report and appendix register

Keep the full report with its unambiguous version. Assign the appendices listed and identify missing files. An additional brief overview may ease access but should refer to the originals. This makes it traceable whether a conclusion comes from the report itself or a later explanation. With several partial reports, areas, periods and functions remain distinguishable. If, for example, the listed measurement presentation is missing, request the corresponding version from the author; another results graphic is not an unambiguous substitute.

Plans and agreed specialist data

Keep site plans, results presentations and specialist data together in the agreed arrangement. Additional viewing files should have a recognisable function. A screen view may help discussion, while a complete file is needed for another task. Clarify which data each recipient should actually use and which extra details are needed. Spatial data may require coordinate and elevation references and the meaning of object labels. A simplified view does not automatically include all specialist information. Where presentations disagree, clarify their function and version first; participants do not alter the professional conclusion through their own redrawings.

Additions and handover note

Add professional answers and revised appendices with a traceable connection to the previous version. Document which status was handed to whom. This supports enquiries where participants work with different extracts. The handover note makes results findable; it extends neither their spatial scope nor professional conclusions. Record whether a new file replaces an earlier one or supplements a defined matter. When responsibilities pass between planning, construction management and the following trade, the document set describing the discussed task must be clear. Complete initial documents remain connected to the addition so that limits and unresolved questions are not lost.

Follow a conclusion from report to plan appendix

Choose a specific statement for an enquiry. Follow its reference through the named appendix to the area shown. This reveals whether only an explanation is missing or the document set contains an actual gap.

Description and spatial presentation

Compare the section or point description in the text with the legend. Similar names may concern different work statuses. Give the exact document reference and plan number in an enquiry. Ask for a marking's professional meaning if unclear. Reinterpreting a colour or symbol yourself would change the original report. A finding number may identify a measured anomaly, while an execution record describes work at that point. Both are read according to their functions. For several symbol types, clarify whether they identify measurements, worked points or final assessments. These levels must not be mixed when transferred to construction plans.

Depth, reference and limitation

Read depths with their stated reference. A number without an understandable assignment is insufficient for comparison with a planned excavation or borehole point. Obstacles, interference and uncovered areas belong to this interpretation. Describe the missing connection between report and construction planning rather than deriving a broader conclusion from one value. Comparing a new excavation with an older results plan also requires matching ground conditions. Changed elevations or differing section descriptions can impede comparison. The enquiry therefore identifies the specific pair of depths and their references rather than comparing numbers without spatial context.

Planning, execution and assessment

A plan may show intended work, the area actually covered or a professional assessment. Check the function of the specific appendix. If presentations do not visibly agree, identify the difference and ask for the authoritative status. The explanation should also establish whether a later addition replaces earlier content or merely adds information. Legend, plan date and report references show which presentations belong together. Point investigations distinguish intended from actually worked points; phased clearance distinguishes worked areas from unresolved areas. An overall plan is usable as an overview of documented status only with these assignments.

Plattling report example: assign measurement findings and clearance results

The completion documentation for track 20 distinguishes three bomb-find points from the September phase from the 294 GPR anomalies. The site plan defines the areas worked on; measurement presentations, clearance work and checks are described separately. A finding number can thus be assigned to its respective purpose.

The depths also have different references: documented GPR evaluation depth up to 0,80 m and local excavation up to 2,50 m in subareas G1/G2. The specialist company's declaration applies within the documented working area. It does not provide a blanket statement about the whole station.

The Plattling documentation example connects these statements with the project process and original measurement images. The page “ Ordnance clearance confirmation ” explains the scope of such declarations.

Open the Plattling report extract with a sanitised site plan (PDF, 10 pages)

Working boundaries of individual clearance phases

Working boundaries of construction monitoring and volume clearance at track 20 in Plattling.
Cleaned original illustration of the working boundaries at track 20 in Plattling. Green marks the construction-monitoring clearance boundary, red the volume-clearance boundary; contact and coordinate fields were removed.

The marked boundaries belong to the named working phases at track 20. They indicate neither clearance of the entire station nor an equivalent overall ground-penetrating radar area.

Determine the appropriate next step from a specific gap

A targeted enquiry identifies the missing information and its purpose. This distinguishes obtaining documents, explanation and further professional needs.

An appendix is unavailable

Identify it by number, title and associated report version. Ask for that exact component. Record that the file is not yet available so later forwarding does not accidentally appear complete.

Identify the missing appendix in the enquiry

Text and plan cannot be assigned unambiguously

Mark the statement and unclear location in the appendix. Name the section, point or area. The enquiry should show which connection the planned work needs.

Compare text and plan references specifically

Several partial reports are available

Compile individual versions with their respective areas. Check whether a consolidated status exists and which parts it actually covers. Unresolved intermediate areas or missing appendices are identified separately.

Organise partial reports into a document set

A new intervention is planned

Submit the existing documents with current planning. Describe the difference from the earlier project. FONTANA-EOD can agree with you which professional assessment or additional service this question requires.

Discuss documents for the new intervention

Assess reports using specific statements and references

FONTANA-EOD focuses professional coordination on the available documents and required project decision. Unclear information is identified with its exact reference. Work remains tied to the agreed commission and knowledge actually available.

Task before document title

The original task is read alongside the report. A familiar title alone does not determine the conclusion the document actually contains.

Results with limitations

Findings, assessment and limits are considered together. A shortened summary must not turn a limited result into a comprehensive conclusion.

An enquiry with its exact reference

Coordination identifies the document, version and passage. The associated plan area makes the spatial question traceable.

Keep changes traceable

Additions remain assigned to their original document. A new filename alone does not explain what changed from the earlier status.

Address the appropriate participants

Questions about the report, current construction planning and authority requirements are assigned to the appropriate contacts.

Take specific suspicion seriously

New indications during construction are handled according to their actual meaning. An older positive summary does not replace a response to a new specific find situation.

Who contributes which information to clarification

An understandable enquiry makes it easier to combine professional, planning and organisational contributions. Identify existing contacts and the specific purpose of assessment.

Client and document holder

Provide the complete existing document set. State its origin and who can obtain additional files. Professional coordination also needs to know which next decision is being prepared. Selected extracts should remain recognisable as such.

Report author and private specialist company

An explanation of the original report relates to its task and work status. A new commission may concern a different professional question. Describe whether an existing conclusion is to be explained or a further service prepared. The specific commission determines the private company's contribution.

Planning, construction management and competent bodies

Planners and construction management explain the current intervention and information required. Existing authority correspondence is included in full. The body responsible for a procedural question depends on the actual issue and location. The private company explains the commissioned professional conclusion; competent bodies make procedural decisions. The ordnance clearance service/KBD, local public order authority and building control are involved for their respective duties where the specific procedure requires.

Identify report status and project location together

The enquiry needs the actual location and existing procedural documents. This keeps the report assigned to a particular procedure and construction task.

Illustration of a map of Germany marking Wesseling and Gersheim in front of a construction area, with construction plans and a hard hat beside it.

Location-specific procedures

State the address, affected area and existing file references. Provide additional correspondence in full. Similarly named documents for another location may concern a different purpose and procedural scope.

Assign the location and existing procedure
Montage showing building construction, a railway, a utility trench, energy facilities, industry and road construction.

Purpose within the project

Describe whether the report is needed for a new section, changed planning or project completion. This helps explain the specific question about the documents. Later readers should also recognise the connection to the construction task.

Identify the next construction task for report review

Four terms for precise enquiries

Clear terminology helps coordination on missing or unclear information. Each term relates to the document set actually available.

Work status

It describes the task status represented in the document. It may concern a completed subarea while other areas remain outstanding.

Plan appendix

It presents the spatial context of a conclusion. Its names, version and legend must be read with the report.

Addition

It adds information to an existing document. Its reference should make clear whether it replaces, corrects or merely explains earlier conclusions.

Document set

It comprises documents belonging to a particular task. These may include the report, plans, records, data and additional explanations.

Distinguish the different bases of a report

Historical information, investigations actually carried out and later project decisions retain their different functions. The conclusion for the next intervention follows from the complete documents and their geographical and professional context.

Workstation with two screens showing aerial photographs and maps, and printed documents on the desk.

Historical information in the report

Historical analyses can explain the reason and initial question for further work. Check the actual underlying document and whether it is clearly identified. A later investigation has its own documented scope.

Assess the historical basis of an investigation
Two people with a tablet beside a marked construction area; plans lie in the foreground.

The technical service described

The service overview helps assess an investigation or monitoring activity mentioned in the report. For an enquiry, however, the specific execution and its results remain decisive. A general method name does not replace them.

Assign report content to a specialist service
Two people discussing plans at a table beside a vehicle on a construction site.

Documentation within the project process

Partial statuses, completion documents and later explanations fulfil different functions. Keep their relationships recognisable when forwarding. A complete context helps relate the next project decision to the appropriate status.

Read documents in their project context
Person wearing an orange high-visibility vest on a marked construction area with small piles of soil
Person wearing an orange high-visibility vest with a MALÅ survey cart on grass
Questions and answers

Frequently asked questions: survey reports and clearance records

Is there a standard clearance record for all of Germany?

The required content and formats depend on the applicable specifications and the commission. The BFR KMR contain specific documentation requirements within their scope.

Is a survey report automatically a clearance confirmation?

No. Assess the professional conclusion it contains and its scope. A measurement report can describe results and further clarification needed without yet documenting clearance for all planned interventions.

Can plans be passed on separately from the report?

An extract can help provide an initial overview if clearly marked as such. For professional decisions, however, the associated report and its limitations must remain available. An isolated plan extract may narrow the scope of conclusions.

What should be done if an appendix is missing?

Identify the missing appendix from the register and request the version belonging to the report. Do not attempt to fill gaps with results from other projects or an older plan. The document set must remain internally assignable.

Which documents should be retained for later construction?

Keep the complete authoritative document set with its plans and limitations so it can be found and assigned again. Whether it covers later planning must be assessed separately. Applicable retention periods must be clarified separately under the relevant requirements and agreements.

How should I ask about a marking on a plan?

State the report version, plan number and location concerned. Ask what the marking means and how it relates to the report's conclusion. Also describe the planned work for which you need the information.

Can a newer file simply replace the whole report?

A more recent file date alone does not establish this. Check whether the file is identified as a replacement, correction or addition and which part of the document set it concerns. If the relationship is unclear, ask which version is authoritative.

What information helps resolve contradictory partial reports?

Compile the affected versions with their appendices and identify the contradictory passages. Show whether they concern the same area, period and commission. Professional clarification should address this specific difference.

Submit the report with a specific enquiry

For initial coordination, FONTANA-EOD needs existing documents and their intended use. An exact reference helps professional preparation.

Include complete documents

Send the report, appendix register and available appendices with version information. Identify missing files and possible contacts for obtaining them. Include authority correspondence and earlier investigation documents where the report refers to them. Also state whether you have a completion report or a partial status still requiring additions.

Describe the affected intervention

Identify the location, subarea, route or borehole points and intended depths and dates. Include the current plan and show relevant changes from the documented status. Project address, land parcel and construction area define the location. Existing utility plans, aerial photograph analysis and known requirements are stated with their status. This shows which conditions may affect use of older documents for the present construction task.

Define the answer needed

Identify the unclear passage or missing assignment. Describe the decision to be prepared and contacts for professional or organisational questions. Give the exact page and affected plan area. A marked passage with document version and plan number allows a targeted professional enquiry; the answer requested should relate to the specific forthcoming decision.

GPR on a construction site
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.