Borehole surveying on a construction site with a drilling rig, measurement grid, survey points and FONTANA-EOD specialist staff
Oliver Fontana – Managing Director Wednesday, 4 February 2026 by Oliver Fontana – Managing Director

How deep and borehole surveys reduce risks in deep groundworks

Deep and borehole surveys – investigating ordnance deeper in the ground

Deep-ground and borehole surveys investigate deeper areas where explosive ordnance is suspected. For deep excavations, drilling or foundations, the first step is to clarify which depths and areas are covered by existing documents and investigations.

Whether a borehole survey is suitable depends on factors including the suspected hazard, ground conditions, measurement conditions and proposed intervention. The investigation scope and limits of interpretation are defined and documented for each project.

Deep and borehole ground investigations

Borehole surveying is one option for investigating at depth

In ordnance work, deep surveying means investigating deeper parts of the ground. Borehole surveying is one way to do this, taking measurements at depth through boreholes. What the findings establish depends on the measurement principle, investigation geometry and site conditions. To clarify a project's requirements, FONTANA-EOD needs site and foundation plans, existing ordnance-related records, and details of the depth of the planned ground disturbance and existing structures.

What historical evidence means for deep surveying

Using historical evidence for the volume of ground involved

A deep investigation starts by defining what suspicion is to be investigated and in which area.

From historical context to the investigation objective

The air war, unexploded bombs, battlefield remnants or military uses may each prompt historical research. They do not lead to a general assumption about every property. What matters for planning is the evidence available for the affected area and the investigation task that can be justified from it. Provide existing assessments with their appendices and identified uncertainties.

Considering earlier ground surfaces

Present-day levels and earlier site conditions may differ. Filling, excavation and construction changes can make older records harder to relate to the site. Describe known changes and provide available level surveys and as-built plans. Specialist planners can then check which volume of ground the historical information and current works relate to.

Passing on the full existing evidence

An earlier report may contain historical assumptions, technical results and unresolved questions. For a new investigation at depth, these need to be read together. Its conclusion alone or a single map page is often insufficient. The handover should identify the report's underlying records and any later investigations or changes to the plans.

Terms, sources and professional assessment

Clarifying the suspicion, groundworks and survey conditions

What suspicion needs to be investigated?

Historical evidence and existing findings may indicate possible types of ordnance and their geographical relationship to the site. An unexplained survey signal is initially a finding, not a positively identified unexploded bomb. The investigation objective needs to be more specific than a general request for safety.

What intervention is planned?

Clearly describe the locations and depths of foundations, piles, excavations or utility sections. Depths need a vertical reference. If the plans change, check whether the existing investigation still covers the affected areas.

What can be measured under the site conditions?

Steel reinforcement, utilities, metal-containing fill and other sources of interference can affect measurements. Access, ground conditions and the characteristics of the object being sought help determine which method can provide usable data.

Bringing the probe closer to the area being investigated

Borehole magnetometry takes magnetic measurements inside a borehole. It records physical anomalies whose interpretation forms part of the professional assessment. A signal may also come from other ferromagnetic objects. The method does not provide a photograph of the ground and cannot identify an object from its signal alone.

The BFR KMR address the planning and execution of borehole magnetometry separately from other geophysical methods. Their specification concerns the search for unexploded bombs using particular gradiometers. It does not establish general suitability for every type of ammunition or every setting. The technical specification for borehole magnetometry describes the relationship between the investigation objective, site conditions and execution.

For clients, the central question is therefore not simply how deep drilling can go. Clarify which volume will be investigated, what can reliably be established and how areas that cannot be assessed because of interference will remain identifiable. The survey service page explains how to prepare a project-specific enquiry.

Defining an investigation at depth clearly for planning and assessment

The information should allow the design, completed investigation and report to be related to one another later.

Whether this access method is necessary and suitable needs professional justification. A surface investigation may be limited by the target size, depth or interfering structures. Conversely, a deep structure does not automatically justify the same borehole investigation in every case. The specific task determines what is needed.

Providing geometry and vertical references together

A position on a plan does not fully describe the required volume of ground. Provide the relevant plans, sections and depths with their vertical references. Identify whether a figure relates to the current ground surface, a planned excavation base or another reference. This prevents apparently identical depth figures from being used for different volumes of ground.

Distinguishing planned positions from positions actually investigated

Obstacles or access conditions may require changes during construction. Keep the originally planned position distinguishable from the position actually used. Clear identifiers connect the plan, work carried out and assessment. Document the change and its reason so that later participants can understand which planning question the available data addresses.

Keeping limitations with the results

For an area affected by interference or not investigated, explicitly record that it remains unresolved. Planning needs both the findings and the limits of what they establish. Record the area affected, the decision still needed and the relevant records. This makes the open question clear to the next contractor rather than losing it in a general summary. Missing or uninterpretable data must not be passed on as a finding with no anomalies.

What the investigation report establishes for your construction plans

A traceable report connects survey locations and vertical references with the method, data quality and professional interpretation. It needs to identify the areas investigated and any limitations. Gaps not investigated and data that cannot be interpreted because of interference must not silently be treated as having no anomalies.

Anomalous measurements may require further investigation. A finding with no anomalies applies within the investigation objective and what the survey could reliably establish. Neither the number of boreholes nor the greatest drilling depth replaces that assessment.

If the result is to support clearance of a construction section, the actual investigation scope needs to cover the planned works. The pages on Survey report and clearance record and the meaning of an ordnance clearance statement explain this handover.

Comparing existing surveys with the planned works at depth

A surface survey with no anomalous findings relates to its original objective and what it could actually establish. For deeper groundworks, compare the target object and required volume of ground with that scope. This identifies where existing results provide a sound basis and where further investigation is needed.

Where a base slab or other structures are present, assess access, interference and the investigation objective together. This determines the choice of a suitable method. A borehole investigation is an option where it can address the particular task at depth under the conditions present.

If depths change, new areas are added or the construction method changes, assess whether the existing results remain applicable. The BFR KMR describe the approach for federal government properties. Other projects are based on the applicable project specifications and requirements of the responsible authorities.

Keeping the terms used in commissioning and assessment distinct

A clear task description distinguishes suspicion, measurement, professional assessment and the evidence needed for the project.

Suspicion and suspected area

A suspicion concerns information requiring professional assessment. A suspected area connects that information to a defined location. For deep groundworks, also clarify the volume of ground and investigation objective. A general description of suspicion does not prescribe one standard survey method.

Distinguishing terms for suspected ordnance

Surveying

A survey investigates a defined volume of ground using a suitable technical method. The task specifies location, depth and the investigation objective. Ground conditions, structures, access for surveying and technical interference affect which methods are suitable.

Comparing technical investigation tasks

Clearance and recovery

Clearance concerns planned work on a defined area towards a specified objective. Recovery concerns an item that has been found, within the professionally planned approach. A survey anomaly is therefore first documented as a finding, together with the further clarification needed.

Understanding clearance and recovery

Clearance statements and documentation

When a statement is described as clearance, read it alongside the area, depth, method and limitations. The documentation connects these details to the commission and findings. For later planning, the statement's actual scope must remain clear.

Understanding the scope of the evidence

EOD and UXO

EOD stands for Explosive Ordnance Disposal and refers to specialist ordnance disposal work. UXO stands for Unexploded Ordnance: ordnance that has not detonated. Using these terms replaces neither a precise investigation task nor professional assessment of an individual survey anomaly.

Understanding EOD and ordnance disposal

KBD and local coordination

KBD stands for Kampfmittelbeseitigungsdienst, the ordnance disposal service. The responsible state and local authorities are involved according to the applicable procedure. When making an enquiry, provide existing correspondence, file references and details of previous contacts so that the private specialist service can be coordinated appropriately.

Distinguishing the responsibilities of those involved

BFR KMR and DGUV

The BFR KMR construction guidelines for ordnance clearance set out technical principles and requirements within their scope. DGUV refers to German Social Accident Insurance. When preparing the work, consider the relevant principles together with the specific task and site conditions.

Understanding the relevant guidance

Excavation supervision

Excavation monitoring accompanies suitable groundworks under defined conditions. It follows a professional decision about the particular task. A gap in the records no more prescribes this approach than a general mention of wartime damage nearby.

Understanding tasks during construction

Assessment requires the plan, survey and report together

The records explain the relationship between the original task and the documented findings.

The historical starting point

An existing assessment is read with its geographical reference and appendices. It helps formulate the investigation objective and is considered alongside the planned groundworks.

Locating historical evidence

The investigation task at depth

Location, vertical reference and working space form the basis for technical coordination. Describe known structures and access conditions in the enquiry so that the task can be assessed for the actual site.

Preparing an investigation at depth

A traceable handover of results

Pass on a report with its maps, associated identifiers and clear limitations. All these elements are needed when comparing it with the construction plans. A depth or a count in isolation does not describe the volume investigated.

Handing over findings with their scope

What needs to be clarified for your project

Determining the next professional decision from the starting conditions

Start with what is known and how the findings will be used.

The historical basis is still unclear

First relate the available information, earlier reports and historical records to the project. A justified investigation question is needed. Naming an instrument in the specification alone defines neither the basis for suspicion nor what the investigation needs to establish. If reliable historical evidence is missing, specify the archival research and historical aerial photograph assessment needed as separate specialist tasks. Their findings help justify the investigation objective and volume of ground involved.

Clarifying the historical basis for investigation

Existing results do not clearly cover the foundations

Compare the area investigated with the current design, including its levels and depths. Request missing appendices or clarification of uncertain references. This comparison establishes which decisions are already supported and which questions need further work.

Comparing existing results for separate areas

Existing structures limit survey conditions

Describe utilities, reinforcement and other structures together with survey access and the investigation objective. Specialist planning identifies an approach suitable for the actual conditions. A limitation at one location does not prescribe a general method for every other part of the site.

Choosing methods within technical limitations

The report leaves some areas unresolved

Further coordination addresses the areas specifically identified and the reason for each limitation. Retain existing results. State the decision still needed and its significance for the next works so that supplementary tasks can be commissioned appropriately.

Documenting unresolved areas at handover

Separating historical assessment, technical investigation and comparison of results

The three tasks may build on one another; their scope depends on the project's actual stage.

Assessing historical evidence for the groundworks

Bring earlier assessments and available historical records together with current site and foundation plans. Define the unresolved historical questions for professional assessment. A general account of the location does not by itself replace an existing technical survey.

Clarifying the historical basis for work at depth

Planning a justified investigation at depth

Once the required volume of ground and investigation objective are defined, agree access and the method against the site conditions. The enquiry needs to cover geometry, vertical references, existing structures and available findings. The service page describes project-specific survey preparation.

Discussing investigation requirements at depth

Comparing existing reports with the plans

To use earlier findings, read the report, site plan, data references and limitations together. Identify the current plan revision and the decision the findings are intended to support. Keep unresolved or changed work areas distinguishable from areas already investigated.

Relating the investigation scope to the evidence

Coordinating borehole positions and the required depth

Set out the proposed borehole positions or work areas with the depths of ground disturbance and their vertical references. Include a site plan, existing investigations, utility records and known access limitations. FONTANA-EOD will discuss the scope needed for the particular works at depth and any information still outstanding.

Discussing borehole positions, depth and records

From the task description to a usable handover

Coordination brings the available information together step by step.

Defining the project question

Describe the decision that needs to be prepared for planning or construction.

Gathering the records

Provide existing findings with complete reports and appendices.

Defining the working space

Identify the location, depth, vertical reference and current plan revision.

Agree the site conditions

Tell us about existing structures, access, obstacles and relevant construction stages.

Define the technical scope

Agree the investigation required and how the results will be handed over.

Use the result for the specific project

Match the documented investigation volume to the work actually planned.

Prepare the commission from the current project information

A focused enquiry describes the outstanding task and the information already available.

Complete the preliminary investigation

Historical records and existing assessments are considered alongside the planned ground disturbance.

Add to the historical evidence

Commission a depth-specific investigation

For defined points or working volumes, provide the geometry, vertical datum, existing structures and investigation objective.

Agree the survey scope for deep ground disturbance

Reuse existing results

Compare the report and plans with the new design. Keep unclear spatial references and unresolved areas identifiable.

Compare the report with the current design

Send the documents for technical coordination

FONTANA-EOD will discuss the appropriate scope of services and any further information needed with you.

Send a specific investigation question

Describe deep ground disturbance by its actual geometry

The type of structure alone does not determine the investigation. Identify each working volume for the technical discussion.

Point foundations and individual work locations

Describe the location and depth of piles, wells or other individual ground disturbances. Include adjacent working areas and known obstacles in the plans. Evidence for another position must not be reused solely because the structure has a similar name.

Discuss depth-specific tasks at individual points

Retaining-wall alignments and linear structures

For an alignment, the actual width and depth of the ground disturbance matter as well as its route. Show changes to connections or individual sections in the current drawing revision. Investigation planning needs the required ground volume and known limitations along the route.

Plan linear ground disturbance with its depth

Excavations and changed foundation designs

An excavation can include different formation levels, deeper sections and working areas at the sides. Assign existing results to those areas. For new designs, explicitly check whether additional or differently positioned volumes are affected and what further technical clarification is needed. This applies to underground car parks and tunnel sections as well as new uses on industrial or redevelopment sites. Describe the ground volumes affected by the base level of the structure, retaining works, connections and preparatory utility works. For transport and infrastructure projects, also clearly distinguish the investigated section from the remaining existing structures.

Choose methods for the planned working volumes

Account for local requirements and project stages

Relate the technical task to the actual location and the coordination already completed.

Provide location-specific documents

Give the municipality, address and any local information already obtained. Include case references and the authorities or other bodies already involved. This places the private specialist service within the current project context, without adopting unverified procedural assumptions from another region.

Establish the project location and local coordination

Document separate working volumes individually

A project can cover different areas, levels and construction stages. Use clear identifiers and provide the associated plans together. This keeps results and limitations assigned to the correct area, even when several parties reuse the documents.

Document individual volumes and the status of results

Documents and construction area

Person wearing an orange high-visibility vest on a marked construction area with small piles of soil
Illustration: two people review plans and documents at a table beside a construction vehicle.
FONTANA-EOD drilling rig beside a railway track; a person wearing an orange high-visibility vest stands on the left.

Frequently asked questions

Are deep investigation and borehole surveying two separate methods?

Not necessarily. Deep investigation describes the investigation of deeper ground. Borehole surveying is one way to carry out measurements below ground for that purpose. The measurement principle used must also be stated.

At what construction depth is borehole surveying always required?

There is no single depth that applies to every project. The suspected ordnance situation, possible target objects, construction design and the capabilities of existing investigations must be assessed together.

Can the probe identify every metal object as explosive ordnance?

No. Physical anomalies require specialist interpretation. Other metal objects or installed structures can cause signals or interfere with measurements. Suitability depends on the measurement principle and the specific task.

Is the maximum drilling depth enough to describe the result?

No. The measurement locations and vertical datum, methods, data quality, assessment and identifiable limitations must be clear. Only then can the investigated volume be compared with the planned ground disturbance.

Can an existing deep investigation be reused for a changed foundation design?

This must be checked against the documents. If new ground disturbance extends beyond the investigated area, goes deeper or takes place under different conditions, the earlier conclusion must not automatically be applied.

What determines the cost of a borehole survey?

The estimate depends on the required investigation volume, drilling access, ground conditions, utilities and other obstacles, as well as the planned data collection and analysis. Further investigation of anomalous areas or areas with limited measurability can change the scope. A well-founded enquiry therefore describes the existing information and the conclusion needed. Any preparatory work or official measures requiring separate allocation of responsibility are clarified for the project location.

What should I do if I find a possible item of ordnance?

Stop work in the affected area. Do not touch or move the object. Leave the area and keep your distance. Keep other people away without putting yourself at risk. In Germany, immediately call the police on 110 and follow their instructions. The competent authorities will arrange further identification and handling.

What information helps with the initial discussion before commissioning?

Provide the project location, current site and foundation plans, ground disturbance depths with a vertical datum, existing reports, and information about existing structures and access. Also state the decision that the investigation is intended to support. Discuss the requirements before the first planned ground disturbance. Official requirements are clarified with the authority responsible for the project location; technical investigation services are clarified with the specialist designer or contractor. Existing correspondence and case references help establish the context.

Records for your enquiry

Discuss borehole surveying for your project

Gather site and foundation plans, ground disturbance depths with a vertical datum, and existing explosive ordnance records. Also describe access and known utilities and installed structures. We use this information to assess with you the scope of investigation needed for the project.

FONTANA-EOD: +49 6843 9994997 · info@fontana-eod.de

Discuss the investigation needed

Clearance concept and investigation planning

Prepare project documents

Task

The investigation objective and the decision needed remain clearly stated.

Location

Planned and actual positions are clearly matched.

Elevation

Depths have a clear, shared reference datum.

Conditions

Existing structures, access and relevant interference are described.

Result

The assessment and its limitations are handed over together.

Updating the assessment

New designs are compared with the existing investigated volume.

Describe the depth-related task for an initial response

The clearer the question and the available evidence, the more precisely the required scope of services can be discussed.

Location, positions and depths

Give the address, region and land parcel. Include a current site plan showing the construction area, route, excavations and borehole positions. Add the ground disturbance depth with a vertical datum and any known differences between the current and proposed ground surface.

Existing documents and structures

Send historical records, aerial photograph assessments, previous investigation reports and utility plans with their appendices. State known installed structures, access conditions and requirements. Missing information or information that cannot be clearly assigned should remain identified as outstanding.

Project stage and the decision needed

Describe the project status, construction schedule and next stage of work. Explain which decision is to be supported, which authorities or other bodies are involved, and whether positions or depths have changed since earlier investigations.

GPR on a construction site
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.