Explosive ordnance assessment for works extensions

For a works extension, we consider new foundations, utilities and connection areas separately by area and depth. FONTANA-EOD checks earlier investigations against the extension plan, existing utilities and local survey conditions. Send the extension boundary, depths of intervention, as-built plans and operational windows so that required surveys, access and documentation can be coordinated before ground interventions.

Existing assets

Clarify connections and utilities.

Construction section

Define the area and depth.

Operations

Coordinate access and working times.

Project situation

When a works extension should undergo an explosive ordnance assessment

Before a works extension, it is clarified which explosive ordnance investigations are needed for new foundations, excavations, utility connections and other ground interventions. The current extension plan is checked against existing indications of a suspected hazard and earlier investigation results. Existing utilities, foundations and operational processes also determine which access arrangements and methods are possible. Results and unresolved areas remain unambiguously assigned to the existing site boundary, new construction site and respective depths.

Technical terms

Technical terms for coordinating works extensions

The extension area, connection to existing structures and operational window describe different tasks in investigation planning.

Extension area

The extension area describes the specific area of the new intervention. It may include building axes, external works, civil engineering, utilities, site roads and connection areas.

Clarify the extension area within the project
Connection to existing structures

Connections to existing structures link new buildings to existing utilities, foundations, chambers or operational areas. For investigation, the new intervention and existing installations are considered together.

Have the connection to existing structures assessed
Operational window

Operational windows are times agreed with the operator for investigations or construction work. Production, works traffic and necessary closures are taken into account.

Coordinate operational windows
Interference conditions

The interference environment includes reinforcement, utilities, scrap metal, foundation remnants, steel components, fill or machinery foundations that can affect survey data and method selection.

Have the interference environment technically assessed
Intervention depth

The depth of intervention describes how far a foundation, borehole or excavation extends into the ground. It is stated with its level reference and considered during method selection.

Clarify intervention depth
Documentation objective

The purpose of the documentation defines whether documents are needed for procurement, site management, HSE, the operator file or a specific subsequent decision in the construction sequence.

Define the purpose of the documentation
Use and area

Check new working areas against the existing works site

For works extensions, the explosive ordnance question arises from the interaction of previous use, the existing facility, new planning and the actual ground intervention.

Connection to the existing site

Connections to existing buildings and installations form part of the investigation plan. New foundations, chambers, utility axes and traffic areas meet existing utilities, earlier construction conditions and operational installations. The commissioned investigation area also identifies these interfaces with the existing site.

Ongoing works operations

Production, maintenance, logistics, staff routes and safety zones determine when and how investigations can be carried out in practice. Working windows, access roads, exclusion areas and contacts are agreed before the investigation. Results and limitations remain documented even during tightly scheduled construction phases.

Utilities and supplies

Electricity, water, gas, compressed air, wastewater, fire-fighting water, data, earthing and process utilities often run in dense groups on works sites. Utility routes, depth, construction condition and possible interference with survey methods matter for the investigation.

Foundations and retaining structures

New column axes, machinery foundations, retaining structures, piled foundations or pumping chambers may involve substantially deeper interventions than the subsequent surface construction. These points need their own depth reference and should be checked against survey planning before execution.

Demolition and existing installations

Old ground slabs, chambers, foundations, ducts and demolition boundaries can greatly alter the ground. They influence the construction sequence, survey feasibility, survey quality and whether excavation should receive specialist supervision. Necessary investigations and protective measures are planned before ground interventions during demolition, breaking out, utility exposure or preparation of working areas.

HSE and works organisation

At active sites, explosive ordnance assessment forms part of the safety organisation. Access, instruction, exclusion areas, communication about finds, machinery use and handover to site management must be coordinated with operational processes before work begins.

Document subareas separately

A works extension often includes a new construction site, connection trench, utility diversion, site road, storage area and external works. These subareas differ in depth, interference environment and documentation needs and should be documented separately.

Project file for later alterations

Works sites are often altered several times. The documentation identifies investigated areas and depths for later utilities, foundation changes, maintenance and operator communication.

Applications

Typical investigation situations for works extensions

The practical investigation follows the intervention. Extension areas, existing utilities, foundations, utilities, excavation and documentation need different specialist priorities.

Two people discussing plans at a table beside a vehicle on a construction site.

Extension area

The new construction site is checked against existing conditions, historical documents, construction limits and intended depths. This provides the basis for historical assessment, technical survey or monitoring during construction.

Check the extension area against existing documents
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Foundations and drilling points

Pile axes, ground improvement, retaining structures and machinery foundations need position, design depth and drilling method information. The investigation is related to these technical data.

Agree borehole positions
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Excavation and utility trenches

For utility trenches, excavations, chambers and retention structures with limited preliminary investigation, the suitability of explosive ordnance detection during construction is assessed. Technical investigation and assessment of each working layer are planned before controlled removal.

Plan excavation monitoring
Two people discussing plans at a table beside a vehicle on a construction site.

Distinguish a survey anomaly from a find

Survey anomalies are assessed by specialists and documented with location references. If an unexpected suspicious object is found, stopping work, keeping a safe distance and reporting it immediately take priority; in Germany, notify the police on 110, and outside Germany use the local emergency reporting procedure. The competent authorities determine the next steps.

Document communication about findings and location references
Two people discussing plans at a table beside a vehicle on a construction site.

Documentation for operators

The results documents must be usable for procurement, site management, HSE and the operator file. They identify investigated areas, methods, results and remaining investigation needs.

Prepare evidence
Decision situations

Coordinate investigations before procurement and construction starts

Even small connection areas are stated with their positions, depths and planned construction dates. Unresolved interfaces with the existing site can affect the sequence of the construction section concerned.

01

Extension planning before procurement

Before tendering, the construction site, construction phases, depths and existing documents are reviewed. This allows the explosive ordnance item in the specification to be described more clearly in technical terms.

Have your procurement documents reviewed
02

Drilling points and piles

Piled foundations, ground investigation boreholes and retaining structure axes must be coordinated with their positions, design depths, drilling methods and survey feasibility.

Clarify drilling points with specialists
03

Utility diversion

New utility routes, crossings and connection pits are compared with existing utilities on the plan. Depths of intervention and possible interference are considered before execution.

Coordinate methods for utility diversions
06

Findings during the works

If an unexpected suspicious object is found, stop work in the affected area immediately. Do not touch, move or further expose the object. Leave the immediate area and keep others away without putting yourself at risk. In Germany, notify the police immediately on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine the next steps. Inform site management and the client; internal reporting must not delay the emergency call. Survey anomalies are assessed by specialists using the survey data and assigned to a targeted follow-up investigation.

Document findings for further decisions
Project decision

Which information is still missing for the investigation

The extension plan is compared with earlier investigations and local conditions. Outstanding questions are clarified before the affected ground intervention.

Plan version and extension boundary

The outline design, construction design and actual construction section must align. If the building edge, utilities, trenches or drilling points move, the explosive ordnance assessment must be updated.

Have the plan version technically reviewed

Suspected hazard arising from previous use

Previous use, aerial photograph data, historical plans, demolition documents and existing reports may concern individual connection areas. A historical assessment defines the technical investigation needs.

Have the suspected hazard assessed

Survey feasibility within the existing site

Reinforcement, steel, old utilities, foundations, chambers and operational installations can obscure geophysical surveys. These sources of interference are considered during method selection and evaluation.

Determine a suitable service

Deep interventions

Piled foundations, retaining structure axes, pumping chambers, utility ducts and machinery foundations may require a depth-related survey.

Agree intervention depths

Excavation under operational conditions

For areas that cannot be adequately investigated in advance, the technical suitability of explosive ordnance detection during construction is assessed. Each working layer is technically surveyed and assessed before controlled removal in layers with supplementary visual inspection follows. These steps are repeated until the agreed excavation base is reached. Excavation layers, the stop signal, authority to give instructions, reporting procedures and documentation are coordinated with operations before work begins.

Plan excavation during operations

Documentation for HSE and site management

HSE and site management need a plan showing the working areas investigated, results, limitations and outstanding questions.

Prepare documentation for HSE
Quality assurance

Coordinate the plan version, investigation scope and handovers

Investigated areas and depths are related to existing conditions, operations and the required documentation. The plan version, actual execution and subsequent handover are linked. If axes, depths, construction phases or utility routes change, the previous investigation is checked to establish whether it still covers the new intervention.

Document the affected volumes of ground separately

For works extensions, the assessment should not be framed as a blanket review of the entire site. Building areas, drilling points, utility axes, excavation areas, access roads, demolition zones and subsequent connection areas may have different depths, interference and documentation needs. The records identify the volumes of ground investigated and the limits of the conclusions for each.

Relate the construction objective to investigation depth

State the respective design depths for the ground slab, cable trench, pumping chamber, piled foundation and ground investigation borehole in the investigation plan. These interventions create different requirements. The construction objective, depth and investigation method are therefore considered together before execution.

Assess the influence of existing structures and services

Existing utilities, chambers, old foundations, reinforcement, steel remnants, aggregate, recycled material and earlier construction conditions can affect survey results. These factors influence both the technically viable method and the limitations stated in the report, as well as being construction constraints.

Include operational organisation

At industrial and commercial sites, access, shift windows, safety zones, works traffic, contractor coordination and HSE requirements also determine practical execution. A technical assessment must include these points while keeping the investigation area and limits of the conclusions clear.

Clarify the reporting procedure before work begins

Before excavation, drilling or demolition, it should be clear how suspected hazards are communicated, who is informed, which work is stopped and what information is documented. An unexpected suspicious object requires work to stop immediately and immediate reporting through the local emergency reporting procedure; in Germany, notify the police on 110.

Keep documentation usable for subsequent work

The subsequent project file must also be understandable to people who were not present during execution. Location references, plans, method, conditions, assessment of findings and recommendations should therefore be structured so that site management, HSE, the operator and subsequent specialist designers can use them for further work.

Record changes to the plan version

Industrial and commercial projects often change between design, procurement, work preparation and execution. If axes, drilling points, utility routes, construction limits, levels or construction phases change, the explosive ordnance assessment should also be updated so that the report, plan version and actual intervention align.

Maintain clear interfaces in project communication

Project management, site management, HSE, design and execution use the agreed plan version and the same working limits. This includes clear contacts, unambiguous location references, understandable working limits and documentation that remains traceable after personnel changes or in later construction phases.

Prepare handover to subsequent trades

After the technical assessment, civil engineering, drilling, demolition, utility installation and building construction teams must know which areas were considered and what conditions apply. Plans, results and limitations are handed over to subsequent trades for their work preparation.

Make documents usable for later decisions

Industrial sites are often adapted several times. An assessment carried out today may later be important for additional utilities, building alterations, machinery locations or external works. Documentation should therefore enable later project participants to understand the area, method, depth, conditions and limits of the conclusions without relying on verbal agreements.

Technical assessment points

Technical investigation points for works extensions

Survey quality, occupational safety and the ability to document results depend on the specific construction work, existing conditions and access.

Existing utilities

Closely spaced utilities can affect safe execution and the ability to evaluate surveys. Utility positions, depths, protective distances and access should be known before survey work.

Foundation remnants

Old foundations, ground slabs and chambers can affect technical survey data and determine the excavation sequence. They are documented as conditions.

Pile and drilling points

Localised deep interventions need clear position and depth information. Without a design depth, the technical conclusion for the intervention is too imprecise.

Operational window

Access, shift operations, production, delivery traffic and HSE requirements determine when investigations and supervision can be carried out.

Steel and reinforcement

Reinforcement, steel components, railings, machinery foundations and scrap metal can obscure survey signals. Method selection must take this into account.

Handover points

The handover identifies investigated areas, results and remaining limitations. Site management and the operator check this information against the intended intervention.

Documentation

Documentation for works extensions, site management and operators

The documentation identifies investigated areas and depths, methods, results and limitations for procurement, HSE, site management and the project file. Following actual exposure or clearance work, the corresponding findings and clearance records are included in the project file.

Source data

Documentation becomes usable only when the site plan, construction site boundaries, construction section, existing utilities, planned depths and existing documents are clearly brought together. For works extensions, subareas and interventions should be clearly distinguished.

Historical documents

Aerial photographs, historical plans, previous uses, demolition records, contamination data and existing reports are not considered in isolation. The decisive question is whether they raise a project-specific investigation or follow-up question.

Technical investigation

The methods used must suit the surface, interfering objects, ground conditions, access, survey feasibility and depth of intervention. Connections to existing structures, new foundations, utility diversions and excavations near operating installations may therefore require a combination of preliminary investigation, survey and monitoring during construction.

Findings assessment

Anomalies, interference and findings are described with location references, method, limitations and the subsequent decision. This makes it possible to trace whether an area is to undergo further work, deeper investigation or supervision during construction.

Report and project file

The documentation must be understandable to clients, site management, HSE, designers and later operators. It describes the result, investigation area, method, limitations and steps still required.

Handover to construction teams

Before ground intervention, site management and construction teams should know which areas were considered, what limitations apply, who is informed if a suspected hazard arises and which documents are needed during construction.

Prepare evidence for the project file
Supporting documentation

Documentation dossier for works extensions

Documentation is reliable only when the area, depth, method, conditions and subsequent decision are clearly described.

Plan revision

The plan version, revision numbers, construction sections, coordinate reference and planned depths are recorded so that subsequent conclusions relate to the actual intervention.

Investigation area

The area considered is described spatially as well as in words. Subareas, drilling points, routes, excavations and unresolved adjoining areas must remain identifiable.

Methods

Historical assessment, surface survey, deep-ground investigation, borehole survey or excavation supervision are documented so that the method and limits of the conclusions are traceable.

Conditions

Sealed surfaces, reinforcement, existing utilities, scrap metal, fill, operational restrictions and access are identified as influencing factors, keeping conclusions within their valid limits.

Findings and assessment

Findings are assessed by specialists and related to their location, survey context and proposed follow-up. This enables project management to arrange further steps in an orderly way.

Filing and handover

The documents are prepared for the project file, procurement, site management and later ground interventions so that they serve as a reliable basis for decisions, rather than merely as an individual report.

Project process

Technical assessment sequence for works extensions

The sequence follows the project circumstances: documents, suspected hazard, method, execution, assessment and documentation are brought together step by step.

01

Review documents

At the outset, the site plan, construction objective, subareas, previous use, utility data, ground information, existing reports and planned depths for the works extension are brought together.

02

Clarify the project question

It is established whether documentation is needed for procurement, site management, HSE, the operator, drilling points, excavation or a specific subsequent decision.

03

Assess suspected ordnance

Historical assessment and existing information are checked against the planned intervention. This establishes which areas should undergo more detailed technical consideration.

04

Determine the method

Surface investigation, deep-ground survey, borehole survey, excavation supervision or a combination are considered according to the surface, depth, interference and construction sequence.

05

Prepare the work

Access, exclusion areas, operational windows, equipment use, utilities, contacts and safety organisation are coordinated with project participants before work begins.

06

Carry out the investigation

The commissioned investigation is carried out with location references, survey data, recording of findings and communication during construction, as required by the project stage.

07

Assess findings

Survey data, indications of a suspected hazard, interfering objects and limitations are assessed by specialists. Where necessary, follow-up measures or further coordination are prepared.

08

Hand over records

The documentation describes the investigation area, method, conditions, result and next technical step for site management, procurement, HSE and the project file.

Technical detail

Technical conditions for works extensions

Technical quality depends on the surface, depth, access, existing conditions, utilities and interfering objects. These conditions determine the limits of the conclusions.

Extensions to existing works sites combine new interventions with earlier construction conditions, ongoing operations and many technical interfaces.

Mark building footprints, drilling points, utility trenches, excavations and traffic areas separately on the site plan. State the construction condition, depth of intervention and known interference. Reinforcement, utilities and fill can affect surveys on a sealed surface differently from those on an open extension area.

A deep borehole at a column axis raises different questions from topsoil removal or a utility connection. The report therefore identifies the method, conditions and results that can be used for the next construction section for each subarea investigated.

Surface

Surfaced areas, asphalt, concrete, aggregate, vegetation, demolition condition and temporary storage affect whether a technical preliminary assessment for works extensions can be carried out reliably.

Depth

Piled foundations, chambers, utility trenches, retention facilities, machinery foundations and excavations may extend deeper than near-surface investigations. The design depth must be known in advance.

Interference

Reinforcement, steel remnants, scrap metal, old foundations, operational installations and utilities can obscure survey signals. These factors must be included in method selection and assessment.

Existing utilities

Earthing, electricity, water, gas, utilities, drainage and communication routes are both safety factors and influences on surveys. Utility plans should be checked before work begins.

Access

Operations, access roads, safety zones, storage areas, machinery locations and shift windows determine when and how investigation services can be carried out in practice.

Documentation

The report must show which subarea was considered, which method was used and which limitations remain for later construction phases.

Select an investigation

Select investigations for the extension area and interfaces with the existing site

Two people discussing plans at a table beside a vehicle on a construction site.

Distinguish new foundations from documented existing structures

The extension plan shows foundations, excavations, utility connections and temporary working areas with their depths. These volumes of ground are compared with existing investigation results. Overlaps with existing structures and areas not previously covered are described separately.

Compare new foundations with existing results
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Consider access beside ongoing operational areas

Existing utilities, foundations and operational routes can affect survey work and execution. Suitable methods are therefore coordinated with the working areas and construction conditions actually available. Connection areas that become accessible later remain explicitly identified in the investigation sequence.

Relate method selection to available working areas
Method comparison

Select methods for the extension area and connections to existing structures

Method selection depends on the suspected hazard, investigation objective, required depth and survey conditions. For each construction section, the assessment the investigation is intended to provide is defined.

Historical aerial photograph analysis

It assesses previous use, identifiable indications of a suspected hazard, existing structures and site history. It does not replace a technical investigation, but can define the investigation area much more precisely.

Surface survey

It is suitable for accessible areas with adequate survey conditions. Sealed surfaces, reinforcement, utilities and scrap metal can affect the conclusions and must be taken into account.

Magnetometry

Magnetometry detects ferromagnetic anomalies in accessible areas. Reinforcement, steel remnants, utilities, earthing networks and machinery foundations can obscure survey data in industrial surroundings. Areas that can be evaluated and survey limitations are documented separately.

TDEM

TDEM detects time-dependent electromagnetic responses from conductive objects. The target object, ground conductivity, required depth and electrical infrastructure determine suitability for the particular extension area or connection to existing structures.

Ground-penetrating radar / GPR

GPR records reflections at material and structural boundaries and can provide supplementary investigation of utilities or installations. Soil, moisture, surface coupling and reinforcement affect data depth. A reflection does not uniquely identify ordnance.

Deep-ground survey

For boreholes, piles, chambers and deeper foundations, it is assessed whether a surface survey adequately covers the required depth range or a deep-ground survey is necessary. Positions and design depths must be provided for this purpose.

Downhole survey

It may be relevant to defined drilling points or deep interventions. Position, diameter, drilling method, spacing, casing and purpose of the documentation are decisive.

Excavation supervision

Where explosive ordnance detection during construction is technically suitable, each working layer is surveyed and evaluated using technical methods. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base. Excavation layers, hold points, authority to issue instructions, reporting procedures and documentation are established before work starts.

Ordnance recovery

Survey anomalies undergo a targeted follow-up investigation or exposure. Recovery of confirmed explosive ordnance is coordinated with the permitted scope of activities and local responsibilities. An unexpected suspicious object must not be further exposed independently; stopping work, keeping a safe distance and immediate reporting take priority.

Project routes

Further services for the works extension

Depending on the project stage, the next step may be a document review, technical survey, excavation supervision or coordination of documentation.

Review documents before procurement

The site plan, construction section, depth, existing conditions and existing reports are brought together before tendering. This allows the scope of services to be described more precisely in technical terms.

Have project documents assessed

Assess the historical basis of the suspected hazard

Previous use, aerial photograph data and historical documents are related to the planned intervention rather than used solely for a general statement about the site.

Have previous use assessed

Include excavation in the construction sequence

Where survey feasibility, existing conditions or interfering objects limit the preliminary investigation, specialist supervision of defined earthworks may be useful.

Plan excavation monitoring

Hand over results to site management and the operator

The documents relate results, limitations and unresolved investigations to the relevant construction sections.

Prepare evidence

Ordnance assessment for industry and commerce

Further information on explosive ordnance assessment for logistics projects, conversion sites and former sites can be found in the industry and commercial sector section.

Industry and commercial sites
Working approach

Who prepares the investigation and connection to the existing site

Works designers, FONTANA-EOD and site management coordinate the plan version and investigation limits before ground intervention.

Project-specific assessment

The assessment starts with the site plan, use, construction objective, depth, interference environment and existing documents. Investigation areas and suitable methods are defined on this basis.

State method limitations clearly

The surface, existing utilities, reinforcement, fill, scrap metal, construction condition and access can affect the conclusions. These limitations are taken into account in assessment and documentation.

Clarify interfaces early

Site management, specialist designers, HSE, the operator and contractors receive a common basis for working limits, contacts and subsequent decisions.

Keep documentation usable

Reports, location references, findings and recommendations are structured to remain usable for procurement, site management, the project file and later ground interventions.

Consider the construction sequence

Survey work, excavation supervision, assessment of findings and documentation are adapted to time windows, access, exclusion areas and actual construction phases.

Respect the operational environment

At active industrial and commercial sites, access roads, production, safety zones, shift windows and HSE requirements are incorporated into sequence planning.

Request a technical review of project records
Coordination

Roles and interfaces for works extensions

Industrial and commercial projects need clear responsibilities between the client, operator, designers, HSE, site management, specialist company and competent authorities.

Specialist contractor

FONTANA-EOD

FONTANA-EOD carries out the project-specific technical assessment, considers documents, survey feasibility, depth of intervention and construction sequence, and produces traceable documentation for the commissioned scope of services.

Client and operations

Client and operator

The client and operator provide site data, plans, the construction objective, time windows, contacts and existing documents, and make project decisions on that basis.

Design and coordination

Design and project management

Designers and project management relate construction phases, procurement, drilling points, civil engineering, the programme, existing utilities and documentation needs to the explosive ordnance assessment.

Construction execution

Construction and civil engineering contractors

Contractors need clear working limits, agreed reporting procedures, communication about findings and information on which areas were considered before each intervention.

Occupational safety

HSE and occupational safety

HSE personnel consider access, barriers, machinery use, procedures on finding a suspicious object, instruction and communication within the operational safety organisation.

Competent authorities

Competent authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and, where applicable, building control are involved according to their project-specific responsibilities. Conditions, contacts and reporting procedures are assigned to the actual extension areas and connections to the existing site.

Regional context

Clarify competent authorities and site documents

The project address, site plan and existing documents enable local contacts and the required information to be clarified.

Project enquiry for ordnance assessment and surveys.

Project location and site data

The address, land parcels, site plan, construction site boundaries and construction sections form the basis for regional assessment. Without an unambiguous location, documents, responsibilities and existing files cannot be reliably assigned.

Send the project location
Illustrated map of Germany with location markers on a construction site.

Federal state and procedure

Procedures, contacts and administrative routes differ between federal states. FONTANA-EOD prepares the technical project data to suit the location, construction phase and communication channel.

Check the project region
Documentation and records for explosive ordnance investigation.

Municipal interfaces

Municipal interfaces may become relevant early in building applications, site servicing, demolition, traffic safety or public infrastructure. The explosive ordnance assessment should provide the required information in a structured form.

Prepare interfaces
Project enquiry for ordnance assessment and surveys.

Construction phases around the site

Access roads, neighbouring properties, existing use, working windows and site logistics influence practical execution. These points belong in the planning of survey work, excavation and documentation.

Coordinate the construction phase
Two people discussing plans at a table beside a vehicle on a construction site.

Existing data from previous projects

Industrial and commercial sites often have older reports, utility data, ground information or previous assessments. These data should be checked in relation to the site before new measures are planned.

Review existing data from previous projects traceably
Documentation and records for explosive ordnance investigation.

Documentation for project participants

The documents identify the location, construction section, investigation method, responsible contacts and steps still required.

Assign documentation
Procurement and site management

Embed explosive ordnance assessment for works extensions in procurement and site management

The earlier the investigation area, depth, method, conditions and purpose of the documentation are described, the better the explosive ordnance assessment can be integrated into work preparation and construction.

Tendering

The specification should clearly identify investigation areas, depths, methods, conditions and documentation. Unclear lump-sum items make subsequent execution more difficult.

Work preparation

Access roads, exclusion areas, drilling points, utilities, equipment access, contacts and operational windows are coordinated on site and using the project documents.

Scheduling

Survey work, assessment, earthworks and documentation must suit the sequence of demolition, civil engineering, building construction, utility connections and production operations.

Construction management

Site management needs clear limits, reporting procedures and documents. It must be able to identify which work can be carried out under which conditions.

HSE

HSE needs reliable information on working areas, procedures if a suspected hazard arises, barriers, instruction, machinery use and communication.

Project file

For the client and operator, what matters is a traceable file identifying the area, method, conditions, assessment of findings, limitations and subsequent decision.

Existing utilities

Existing utilities, chambers, earthing systems, cable routes and drainage must be included in planning as safety factors and influences on surveys.

Plan changes

If construction limits, depths, drilling points or routes change, the explosive ordnance assessment should also be updated. Otherwise, the report and execution no longer reliably align.

Specialist report data

Ground investigation, contamination, survey and demolition data can improve explosive ordnance assessment when shared early and checked against the planned interventions.

Bidder queries

Questions on investigation depth, documentation, interference, access, working windows and follow-up services should be capable of receiving a technical answer before work begins.

Risks of variations

Unclear investigation areas, missing depth information and unaccounted-for interference can lead to later discussions about construction time and scope of services.

Handover to construction teams

Plans, investigation areas, contacts, procedures for findings and documentation requirements should be available during work preparation before work begins.

Coordinate documents for procurement and site management
Project context

Review documents and record the investigation

Existing documents and technical investigation results are assigned to the extension area and its connections to the existing site.

Person with a tablet on a marked construction area in front of an industrial building.

Industrial and commercial site

Existing investigations are compared with the new construction sites and connections.

Assess the sector context
Two monitors displaying aerial photographs and maps; further aerial photograph printouts lie on the desk.

Historical assessment

Previous use, aerial photograph findings, historical plans and existing indications of a suspected hazard are brought together before the technical investigation.

Assess previous use
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Deep-ground survey

Drilling points, foundations, retaining structure axes and deep utility trenches require an investigation that takes account of the design depth and construction method.

Agree borehole positions
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Excavation supervision

For remaining areas, it is assessed whether explosive ordnance detection during construction is suitable. Excavation layers are technically investigated before removal.

Plan excavation
Two people discussing plans at a table beside a vehicle on a construction site.

Documentation

Reports, location references, findings and subsequent decisions are prepared for site management, HSE, the operator and procurement. Following actual exposure or clearance work, the corresponding findings and clearance records are included.

Prepare evidence
Survey cart on an open construction area, with piles of soil in the background.

Project enquiry

The site plan, depths and construction phases enable the investigations and further documents required to be clarified.

Send project documents
Four people in orange high-visibility vests in front of two excavators on a construction site.
Person with a yellow survey cart on a footpath in front of a hedge.

Technical information

Industry and commerce: brochure

Work on industrial and commercial sites combines existing installations, operational processes and new ground interventions. The brochure explains how ordnance assessment is coordinated with these conditions.

1 / 8
Industry and commerce: brochure – page 1

German · 8 pages

Project questions

Frequently asked questions about explosive ordnance assessment for works extensions

When should a works extension undergo an explosive ordnance assessment?

An assessment is useful as soon as foundations, drilling points, utility trenches, retaining structures, excavations, traffic areas or changes to ground levels affect a subarea that has not been adequately assessed. The suspected hazard, depth of intervention, existing utilities, interference, construction phase and purpose of the documentation are decisive.

Which documents does FONTANA-EOD need for an initial assessment?

Useful documents include a site plan, extension boundary, land parcels, as-built plans, utility plans, planned depths, drilling points, construction times, earlier reports, aerial photograph assessments, demolition documents and information on HSE or operational windows. Authority information and conditions should be supplied with their dates, complete attachments and geographical scope.

What should be done if a suspicious object is found during earthworks?

If an unexpected suspicious object is found, stop work in the affected area immediately. Do not touch, move or further expose the object. Leave the immediate area and keep others away without putting yourself at risk. In Germany, notify the police immediately on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine the next steps. Inform site management and the client; internal reporting must not delay the emergency call.

Which methods may be considered for works extensions?

Depending on the project, historical aerial photograph assessment, surface survey, magnetometry, TDEM, ground-penetrating radar, deep-ground survey, borehole survey, ordnance specialist supervision of excavation or explosive ordnance recovery may be relevant. Selection depends on the surface, interference, ground conditions, investigation depth and construction sequence.

How is work during ongoing site operations taken into account?

Investigation areas, exclusion areas, access roads, operational windows, utility axes, contacts and HSE requirements are incorporated into planning. Works management and site management coordinate these conditions with the specialists involved before the investigation.

What role do existing utilities and old foundations play?

Existing utilities and old foundations may be safety-relevant and affect survey data. Before method selection, they should therefore be checked against position, depth, material, access and planned intervention.

What documentation is produced for site management and the operator?

Typical documentation includes location references, the document version used, survey records, assessment of findings, limitations, photographic records and specialist recommendations for the next project step. Its form depends on the scope of services and project phase.

What determines the effort and cost of an ordnance assessment?

Decisive factors include site size, access, sealed surfaces, interfering objects, existing utilities, ground conditions, depth of intervention, construction phase, operational windows, available documents, required methods and extent of documentation.

Preparing an enquiry

Which documents we need for your works extension

Place the extension plan and existing as-built documents side by side. Mark new interventions, connections and outstanding information.

Site and area

Address, land parcels, site plan, construction site boundaries, subareas, existing areas and affected construction sections.

Ground disturbance and depth

Excavation, drilling points, piles, foundations, chambers, utility trenches, demolition and planned design depths.

Existing structures and utilities

Utility plans, utility axes, earthing, chambers, reinforcement, existing structures, exclusion areas and access roads.

Available documents

Aerial photograph assessment, historical plans, ground investigation data, contamination documents, demolition plans, previous reports and conditions.

Construction phase and dates

Design stage, tendering, procurement, work preparation, construction times, shift windows and simultaneous trades.

Documentation objective

Procurement, site management, project file, HSE, operator communication, subsequent decision or coordination with competent authorities.

Send project documents together

Send the existing documents with the location, construction site, planned work, depth and construction phase. Distinguish the building footprint, external works, utility trenches, drilling points, demolition zones and later connections. Where documents are incomplete, identify the gaps and the decision for which you need a result.

State whether operations, delivery traffic, shift changes, demolition, civil engineering or assembly will continue during the investigation. Access, exclusion areas, machinery use and coordination depend on this. FONTANA-EOD uses this information to assess which historical assessment, survey, deep-ground investigation or excavation supervision is suitable for the next step.

Identify the recipients of the results and outstanding questions about the method, timing, access or further services. Report subsequent changes to the plan version, construction limit and design depth. This enables the report and execution to be kept at the same stage.

Telephone

+49 (0) 6843 - 999 499 7

Email

info@fontana-eod.de

Project documents

Site plan, depth, construction phase, suspicion indicators

Contacts

Site management, designers, HSE or project management

Have project documents assessed
Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.