Project pathway
The quickest route to the right decision.
Before fibre rollout, the route, crossings and network nodes are checked against the available explosive ordnance records. FONTANA-EOD plans suitable surveys according to working width, installation depth, construction method and access during individual phases. Send the route plan, standard cross-sections, crossing details and rollout sections so that services and documentation can be defined before trenching, milling or drilling.
Identify the backbone, local network and connections.
Distinguish trenching, milling and drilling.
Document the corridors addressed by chainage.
Before fibre civil engineering works, survey requirements are clarified using existing hazard indications and the planned installation methods. Open trenches, trenching, thrust boring, directional drilling, chambers and network distribution cabinets are considered with their working width, depth and excavations. Existing utilities and technical installations influence method selection; deep crossings and launch or reception pits are assessed separately. The documentation links surveyed areas to the route alignment, chainage, installation method and design revision.
Backbones, local networks, property connections and technical network nodes differ in length, construction depth, accessibility and method. The explosive ordnance assessment is therefore not described as a blanket service for the entire rollout area.
Each section is assigned clear location and chainage references so that fieldwork, the civil engineering crew and subsequent documentation relate to the same route geometry.

Connections between localities follow long corridors with changing surfaces, properties and crossings.
Section boundaries, kilometre references, working width and planned installation depth determine research, surveying and reporting.
Different areas may be planned concurrently but constructed at different times; documentation therefore remains separable by section.
Divide the backbone corridor into assessment sections
Streets, footways, ancillary areas and property connections create a finely divided network with numerous construction stages.
Existing utilities, local authority conditions, daily output and handovers between crews must match the status of work.
For framework contracts and multiple construction partners, a consistent chainage, contract section and file system is particularly important for subsequent project records.
Assess the local network and construction sections
Narrow milled slots reduce trench width but do not remove the need for a reliable assessment of the entire volume at depth through which work passes.
The surface, existing installations, milling depth and technical interference sources are related to the planned alignment.
A narrow trench must not be mistaken for automatically low technical requirements; the complete ground intervention geometry remains decisive.
Assess the method for the milling corridor
Low-excavation methods have a linear or point-specific underground working volume that is only partly visible from the surface.
Launch areas, installation alignment, reception area, depth and possible positional deviations are considered separately.
For alignments and pits not adequately surveyed, suitable supplementary methods and the survey access required are assessed.
Determine surveys for low-excavation works
Roads, watercourses, railway routes and sensitive surfaces are often crossed beneath using guided drilling.
The launch and reception pits, bore path, reaming, exit and work areas are assigned separate assessment and documentation volumes.
The assessment of a crossing is not inferred from documentation for the open route because depth, construction method and the volume of ground affected differ considerably.
Plan depth-specific surveys for drilled crossings
Network nodes, multifunction cabinets, chambers, joint bays and building entries add numerous individual points to the linear route.
Foundations, excavations, utility entries and assembly areas are recorded with point identifiers and depths.
Sets of distribution cabinets and chambers are maintained in a point register so that design changes and alternative locations remain traceable.
Coordinate survey requirements for connection pointsFibre projects are often delivered under substantial time and output pressures. A reliable explosive ordnance assessment nevertheless requires clear route revisions, defined construction methods and clear criteria for follow-up measures.
Before the final route is selected, historical indications, known finds and available authority information are related to the proposed corridors.
This allows route options to be compared in terms of additional assessment requirements, accessibility and effects on construction time or installation methods.
The historical assessment supports route selection and identifies further survey requirements. It does not replace a necessary technical survey of the subsequent installation or drilling volume.
Assess route options using historical evidenceThe route alignment, network level, standard cross-section, chambers, crossings and property connections are translated into specific volumes of ground affected.
The technical planning identifies not only areas requiring assessment but also sections subject to technical limitations and necessary alternative measures.
Design revisions are assigned unique version identifiers so that fieldwork is not based on an outdated alignment or depth.
Assess rollout planningQuantities, chainage, methods, enabling work, traffic phases, data formats and documentation must remain comparable across contract sections and contractors.
Provisional items are linked to traceable triggers such as interference zones, deep intervention points or changed construction conditions.
Consistent handover formats make it easier to check results from individual contract sections against the overall route.
Define the service specification for the rolloutFor conventional civil engineering work or trenching, the alignment, working width, excavation depth, existing utilities and surface build-up are described.
Survey method selection depends on ground conditions and interference; a blanket route assessment is insufficient.
Microtrenching, footway construction and conventional trenches are described separately where their depths or survey conditions differ.
Assess the near-surface corridorLaunch and reception pits and the underground installation path may be considerably deeper than neighbouring open sections.
Drilling data, target depth, diameter, reaming and safety space form the basis for depth-specific assessment.
Documentation for the launch and reception pits does not automatically assess the entire bore path; conversely, a corridor assessment does not necessarily cover the pits.
Prepare the bore path and pitsExisting utilities, narrow footways, traffic, structures or volumes of ground changed at short notice can limit surveys in advance.
These zones are identified on the plan. Suitable supplementary methods and possible access after dismantling or exposure are defined. Necessary surveys and protective measures are planned before ground intervention during surface breaking, demolition or the creation of access.
Explosive ordnance surveying during construction is an option only if technically suitable for the planned excavation. Its result remains limited to the layers and sections actually surveyed.
Organise daily work sections and excavationLinear fibre routes alternate between open trenches, narrow milled slots, deep crossings and individual network nodes. The technical assessment is therefore differentiated by section and construction method.
Initial situation: The planned route has no sufficiently location-specific assessment of suspected explosive ordnance hazards.
Technical step: Historical sources and existing authority information are related to the alignment, rollout area and priority construction sections.
Documentation objective: Sections with suspected hazards, data gaps and priorities are shown traceably along the route.
Delineate the corridor of suspected ordnanceInitial situation: The volume of ground affected is openly accessible and has a clearly defined width and excavation depth.
Technical step: The target object, ground and surface conditions and interference determine the suitable linear or area-based survey method.
Documentation objective: Survey lines, coverage, interference zones and conclusions remain linked to chainage and the standard cross-section.
Assess the survey method for the trench sectionInitial situation: Utilities, paving, rails, reinforcement and previous excavations affect survey data.
Technical step: Known installations and the achievable depth of usable data are assessed; zones where data cannot be evaluated remain visible as separate tasks.
Documentation objective: Areas where data can be evaluated and those subject to technical limitations are identified separately. Suitable next steps are defined for outstanding areas.
Assess interference and survey feasibilityInitial situation: The planned installation path lies outside the near-surface zone reliably covered by surveys.
Technical step: The bore path, pits, target depth, diameter and possible deviations are translated into a depth-specific assessment geometry.
Documentation objective: The assessment describes the documented bore and pit volume and can be checked against the construction design.
Investigate the crossing volume at depthInitial situation: Structures, existing installations, traffic or technical interference prevent adequate surveying in advance.
Technical step: We assess which dismantling stage allows suitable survey access and whether supplementary methods are needed.
Documentation objective: Surveyed excavation layers and areas not addressed are clearly recorded for site management and the following crew.
Coordinate exposure and excavationInitial situation: An anomaly or suspicious object requires further clarification.
Technical step: measurement anomalies are interpreted by specialists. If an unexpected suspicious object is found, work stops immediately and the competent authorities are notified without delay.
Documentation objective: The anomaly, work, handover and remaining action requirements are updated in the route register.
Clarify investigation of findings and follow-up measuresLarge rollout programmes generate new work statuses every day. The documentation must therefore allow network operators, designers and site management to reliably distinguish route sections already addressed, subject to limitations or still outstanding.
The alignment, network level, section, chainage, street or land parcel references and design revision form the common spatial basis.
Property connections, chambers and distribution cabinets also receive unique point identifiers.
Consistent geometries make it easier to link GIS, construction progress and subsequent network documentation.
Historical assessments, authority information, known finds and historical records are documented with their scope.
Corridors not considered and missing data remain identifiable.
Historical indications remain technically separate from surveying, exposure and an actual find.
Trenching, milling, ploughing, impact moling, thrust boring or directional drilling are described by width, depth and the volume of ground affected.
The explosive ordnance method is related to this geometry and the respective sources of interference.
This allows the documented survey depth to be checked against the depth of each installation method.
Survey lines, borehole locations, anomalies, daily sections and excavation layers are maintained in a consistent register.
The plan, field records and digital data use the same identifiers.
Section handovers remain traceable even when several civil engineering crews work in parallel.
Inaccessible zones, zones affected by technical interference and zones beyond the assessment depth are marked spatially.
The supplementary work required before the subsequent ground intervention is identified for each section.
Outstanding zones are assigned a responsible person and a time reference for the next project decision.
The final status links the technical assessment to the route and point geometries actually addressed.
Changed alignments, additional connections and later rollout clusters can be checked against this status.
The conclusion is not extended to areas not surveyed, relocated areas or areas planned at a greater depth.
The current daily work sections are checked against the route plan and survey results in the project records. Each dataset receives a clear reference to the route, construction method, depth and work status.
Preliminary designs, approval revisions, construction alignments and later changes are maintained under revision control.
This makes it traceable which plan forms the basis of historical and technical assessments.
Design changes are assessed not only graphically but also for their technical effect on areas already surveyed.
The backbone, local network, rollout clusters, street sections and property connections are maintained in a consistent hierarchy.
Handovers between contract sections or crews retain the same spatial reference.
The identifiers show the contract section to which a completed daily section belongs and which neighbouring areas remain outstanding.
Survey lines, assessment sections, crossings, launch and reception pits and individual points receive unique identifiers.
Position, target depth and work status remain linked.
For trenchless methods, the bore path and pits are recorded separately even though they belong to the same construction section.
Anomalies, known installations, interference zones and technical data gaps are assessed separately.
Each outstanding point is assigned a follow-up measure and project status.
This allows outstanding points to be incorporated specifically into the construction programme, a variation or an additional commission.
Working conditions, excavation layers, interruptions and lengths actually addressed are documented continuously. After actual exposure or clearance work, the corresponding findings and clearance records are included.
This supports site management, quantity reconciliation and handover to subsequent crews.
Field records reflect actual construction conditions rather than merely the planned route.
Maps, lists, records and technical conclusions are handed over in an agreed data structure.
Later additions can be incorporated without losing the original status of work.
Agreed file names, coordinate systems and attachment registers facilitate integration into network documentation.
The work follows actual rollout progress. Corridors needed early are prioritised, while later rollout sections are examined in greater detail only once route and depth designs are sufficiently reliable.
The backbone, local network, rollout sections, crossings, network nodes and decision deadlines are taken from the current design revision.
Prioritisation follows approvals, construction design readiness and the actual construction programme requirements.
Historical assessments, authority information, utility plans, ground investigation data and previous excavations are organised spatially.
Missing or outdated documents are recorded as specific clarification tasks.
Alignments, standard cross-sections, construction depths, chambers and boreholes are translated into specific assessment areas.
Different installation methods are assigned separate geometries even where they run along the same street.
Surface methods, depth-specific assessment, dismantling stages and excavation supervision are selected according to the construction method and interference.
The method follows the project question; no method is applied indiscriminately solely because it offers high daily output.
Access, traffic phases, setting out, daily quantities, hold points and data flows are prepared.
The timing and format in which the civil engineering crew receives results are agreed.
Surveys, point assessments or excavation supervision are carried out by chainage and in relation to actual construction conditions.
Inaccessible zones and departures from the plan are recorded immediately in the section status.
Survey data, anomalies, changed alignments and technical limitations are checked against the intended ground intervention.
An anomaly is not classified as explosive ordnance or a harmless installation without technical assessment.
Reports, status lists and outstanding measures are handed over to designers and site management and updated for further rollout sections.
The handover describes the status achieved, rather than a blanket assessment of the entire rollout area.
Fibre networks combine linear corridors with individual excavations and network nodes. A reliable explosive ordnance assessment must traceably represent both geometries and the chosen installation method.
For open trenches, the route alignment, working width, slopes or shoring, excavation depth and lateral working spaces are described. Microtrenching or minitrenching also requires milling width, milling depth and the actual alignment. Cable ploughing and impact moling involve an underground working volume that must not be equated with the equipment's surface travel path.
Guided drilling is represented through the launch pit, reception pit, pilot bore, reaming, target depth and expected positional deviations. Network nodes, chambers and distribution cabinets receive point geometries. Property connections may follow short, changing alignments and must be checked against the overall route assessment.
The status of work remains linked to the current construction drawing. Where the route changes sides of a street, a crossing is relocated or an additional chamber is added, we check whether existing documentation covers the new geometry. This keeps route documentation reliable during a changing rollout.
The alignment, chainage, standard cross-section and actual working width form the basis of the linear assessment.
Constrictions and lateral working spaces are not left outside the documented corridor.
The areas described include excavation and other relevant ground interventions by the proposed construction equipment.
Open trenches, trenching, ploughing, thrust boring and directional drilling have different depth and influence zones.
The technical assessment relates to the entire volume of ground affected by the subsequent work.
Shallow trenches and narrow milled slots do not replace assessment of actual ground conditions and suspected hazards.
Individual excavations are described with coordinates, dimensions, excavation depth and shoring where applicable.
They receive their own documentation even where they form part of the same crossing or route.
The bore path and pits may require different methods and construction dates.
PoPs, MFG multifunction cabinets, chambers and joint bay areas involve foundations, assembly areas and cable entries.
Design and as-built locations are updated using unique identifiers.
Relocated distribution cabinets or chambers are checked against the existing point status before construction.
Services, rails, reinforcement, rubble and previous excavations affect survey feasibility and data evaluation.
Known installations are considered in the site plan and method selection.
Sections where data cannot be evaluated reliably are assigned specific supplementary work or an agreed construction stage.
Lengths addressed, interruptions, outstanding points and handovers are recorded by section.
Site management checks the planned daily section against these documents and the current design revision.
Status records support programme planning, quantity reconciliation and traceable handover to subsequent crews.

The backbone, local network and connection areas are compared with existing hazard information. Relocated property connections and additional distribution cabinet locations may also affect new areas. Their locations therefore form part of the current survey commission.
Check existing documents against the route plan
Trenching, standard trenches and drilled crossings affect different volumes of ground. Crossings require alignment, depth profile and pit details; open sections require working width and excavation base. Method suitability is assessed separately for each volume.
Select suitable methods for trenches and crossingsThe methods are not interchangeable. They are selected according to the physical and spatial question that must be answered for a trench, bore, chamber or inaccessible section.
Assesses suspected hazard areas and data gaps along the rollout corridor.
It does not establish which objects are actually present in the ground today.
The historical assessment determines the priority and scope of technical follow-up assessments.
Detects ferromagnetic anomalies along suitable route sections with sufficiently low interference.
Utilities, vehicles, rails and metal installations can limit survey feasibility.
Rural open land and urban utility corridors may require different methods within one project.
TDEM detects time-dependent electromagnetic responses from conductive objects. Target size, depth and survey geometry help determine which anomalies can be evaluated.
Ground conditions, target object, depth and technical infrastructure determine the information gained.
The active method is not used indiscriminately; it is selected for the additional technical information it can provide.
Shows reflections at material and structural boundaries and can add structural information in paved areas or areas containing many utilities.
Radar profiles do not automatically identify an object as explosive ordnance.
The depth of usable data, coupling and ground conditions must be checked against the installation depth before deployment.
Assesses defined volumes at depth for crossings, pits, chambers and other deep intervention points.
The survey geometry must match the subsequent drilling or construction method.
For HDD and thrust boring, the launch and reception pits and the installation path are considered separately.
Where explosive ordnance detection during construction is technically suitable, each working layer is surveyed and evaluated using technical methods. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base.
Excavation layers, stopping points, authority to give instructions, communication procedures and documentation are defined in the work instruction before work begins. Merely watching the excavator at work is insufficient.
Sections not supervised or changed later remain outside the assessment.
Before a crew starts, it must be clear which lengths have been surveyed, the depths to which results apply and where tasks remain outstanding.
FONTANA-EOD first reviews the current route plan and clarifies what you need the results for. In preliminary design, the spatial extent of suspected hazards is the focus. Before procurement, the service scope, methods, data formats and follow-up items are defined more precisely. For construction, alignment, depth, daily work section and construction method are checked and agreed.
Linear routes and individual network nodes are linked through the same coordinate and identification system. Even with several contract sections, this makes it traceable which length, crossing, pit or distribution cabinet location was assessed and which areas have technical limitations or remain outstanding.
Changes are not merely updated on the plan; their effects on the explosive ordnance assessment are evaluated. This keeps site management and network operators informed about which results remain applicable and where supplementary surveys are needed.
The route, crossings, network nodes and depths are checked before fieldwork.
This avoids surveys being carried out on an outdated or merely provisional route.
The installation method, surface, ground conditions and interference determine the technical service.
No method is selected solely for expected daily output or equipment availability.
Survey data, borehole locations, excavation and reports use the same location references.
Clear geometry supports quantity records, handovers and technical quality control.
Changed alignments and new points are checked against the existing status of work.
The rollout can thus remain flexible without applying earlier assessments to new volumes of ground without control.
Zones where data cannot be evaluated and anomalies are assigned a specific next step.
Responsibility and timing for supplementary work are recorded in project communication.
Project record data formats are coordinated with network documentation requirements.
Agreed file formats, coordinate systems and naming conventions facilitate later use.
Access, utility data and required preparatory work are assigned to rollout sections. Construction planning takes account of when surveys and data evaluation are possible. Unresolved areas remain visible in the sequence before the next ground intervention.
Relocated connections, new pits or a different installation method are checked against the documented scope before construction. The updated plan shows which results remain applicable and where supplementary surveys are required.
Network operators, local authorities, designers, principal contractors, civil engineering crews, specialist contractors and responsible authorities need clear handovers. For design changes and anomalies, it is defined who is informed and who takes on each task.
Defines the network objective, rollout clusters, data requirements, priorities and decision deadlines.
Provides existing design and hazard documents and manages overall project communication.
For framework programmes, it is defined who maintains the central status of work and documentation.
Coordinates permits to break out surfaces, traffic areas, municipal utilities and local requirements.
Existing authority information and regional contacts are incorporated into planning.
Local authority approval and specialist explosive ordnance services fulfil different functions and are documented separately.
Translates the network structure into alignments, cross-sections, crossings, chambers and construction phases.
Tracks design revisions and changes so that their technical effects can be assessed.
The route plan must identify the geometry actually authorised for construction.
Implements work areas, construction depths, methods and hold points.
Reports departures, obstacles and additional ground interventions before construction.
Daily output and construction progress must not outpace the agreed assessment and reporting procedures.
Assesses suspected hazards, survey feasibility and the service scope and carries out the commissioned assessment.
Documents corridors addressed, technical limitations, findings and follow-up measures.
FONTANA-EOD carries out the commissioned technical investigation and documents its result. If ordnance is found, the responsible authorities decide on further action.
In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.
For fibre contract sections, the reporting chain, contacts and spatial references are defined before civil engineering work starts.
The local public order authority and, where applicable, building control are involved according to their project responsibilities. Conditions and contacts are assigned to the actual fibre contract sections and route sections.
The service scope, qualifications, risk assessment, traffic and civil engineering organisation, and documentation are related to the specific fibre section and regional procedures.
In Germany, § 7 SprengG concerns the commercial authorisation for activities requiring authorisation; § 20 SprengG concerns the certificate of competence of responsible persons. Under § 1b SprengG, searching for found munitions also counts as handling them. The requirements applicable to the project depend on the activity actually commissioned and the allocation of responsibilities.
The risk assessment considers civil engineering methods, traffic, existing services, machinery, personnel, exclusion zones, briefings, escape routes and communication. For sites progressing along a route, these requirements must be applicable to each daily work section.
DGUV Information 201-027 supports risk assessment and protective measures for explosive ordnance clearance work. The Baufachliche Richtlinien Kampfmittelräumung contain requirements for historical and technical investigation, clearance concepts, procurement and documentation within their defined federal remit. Their application to the specific fibre project is clarified separately.
If an unexpected suspicious object is encountered, stop work in the affected section immediately. Do not touch, move or continue to expose the object. Leave the danger area and keep others away without putting yourself at risk. In Germany, notify the police immediately on 110; outside Germany, use the local emergency reporting procedure. The responsible authorities determine the next steps. Then inform site management and the client.
The First Ordinance to the Explosives Act (1. SprengV) includes requirements concerning specialist competence and state-recognised training courses. For fibre rollout, the required qualification relates to the activities actually commissioned in each route section.
DGUV Rule 113-003 concerns the dismantling or destruction of explosives or corresponding objects and also includes the disposal of found munitions. It applies according to this field of activity; it does not replace a risk assessment specific to the planned ground intervention.
The company, responsible individuals and specific task must match the scope of activity.
Surveying, exposure, clearance and recovery may have different organisational requirements.
Installation methods, traffic, utilities, construction equipment, work zones and reporting procedures are assessed together.
A changing daily work section still requires clearly assigned responsibilities and protective measures.
Route sections, depths, methods, enabling work, data formats and documentation are clearly described.
Provisional and follow-up items receive a technical trigger and a clear quantity basis.
The work scope, data, limitations, findings and next measure are brought together by section.
The assessment is not extended to relocated routes or routes planned at a greater depth.
The basis for suspicion, current alignment, construction depth, installation method, existing utilities and required documentation are assessed.
This allows specialist services to be incorporated into the construction programme and approval procedures before crew mobilisation.
Design changes, additional chambers, interruptions and inaccessible areas are communicated and assessed promptly.
The crew works only to the design revision and work status documented for the relevant section.
Stop work immediately, do not touch, move or uncover the object further, leave the immediate area and keep others away without putting yourself at risk. In Germany, notify the police immediately on 110. Outside Germany, use the local emergency reporting procedure.
Further measures depend on the find circumstances, local reporting procedure and regional responsibilities.
Maps, point lists, survey data and daily records must represent the rollout so that later construction or design revisions can be checked against the geometry actually addressed.
The overview links the backbone, local network, crossings, chambers and property connections to their respective assessment and work status.
Assess the fibre section within the utility project
The mapping shows supported suspected areas and data gaps as a basis for further investigation.
Assess historical evidence along the route
The depth-specific documentation applies to the documented volume of ground and the installation method considered.
Survey deep crossings and pits
The suitability of construction-phase ordnance surveying is assessed for each excavation layer. The documented investigation area limits the statement’s scope.
Provide specialist supervision of trenching and excavation
The project file distinguishes measurement anomalies, technical interference objects, actual finds and outstanding measures.
Document findings and outstanding measures
The final report describes the initial situation, surveys, technical limitations and further steps still required.
Document project records and construction sections

Historical hazard assessment, technical surveys, depth-specific assessment, surveys during construction and documentation relate to the same fibre sections and network points.
Plan ordnance assessments for transport, utility, energy and other infrastructure projects according to their ground interventions.
Assess the project environment
Distinguish utility corridors, crossings, foundations and installation areas by construction method and intervention depth.
Assess the utility project as a whole
Provide a spatial basis for sections with suspected hazards, data gaps and technical priorities for fibre routes and network rollout.
Clarify historical suspicion indicators
Assess boreholes, chambers, masts, crossings and foundations for fibre routes and network rollout by point location and depth.
Investigate deep work volumes
Establish the suitability and sequence of construction-phase ordnance surveying for remaining excavation areas.
Prepare the excavation sequence
Coordinate recovery of confirmed ordnance with the permitted activities and local responsibilities.
Coordinate the processing of findings
Define the specification, data structure, quality checks and partial handovers for fibre routes and network rollout.
Prepare tendering and documentation
Have the site plan, route, ground intervention geometry, design revision and decision deadline assessed for fibre routes and network rollout.
Enquire about a fibre route with supporting documents
State the project location, rollout area, contract section and street section. The route alignment, property connections, crossings and distribution cabinets receive unique identifiers. Existing requirements and survey results are included with the same design revision and their actual spatial references.
A shallow surveyed route does not automatically cover a deeper crossing planned later. Compare the installation method, excavation base and pit geometry with existing results before the relevant crew starts.
Check evidence against the interventionEven a relocated property connection or new distribution cabinet may lie outside the recorded corridor. Record the change with its design revision and section identifier and clarify additional survey requirements before construction.
Explore the technical principlesTechnical information
Utility routes, substations and energy installations place different demands on ordnance assessment. The brochure shows the design information needed and how investigation, construction sequence and documentation fit together.

The technical assessment should take place as soon as the route corridor, installation methods and planned ground interventions are sufficiently described. Historical indications can initially be assessed for early route options. Before construction, open trenches, milled slots, crossings, chambers and network nodes must be considered with their respective depths and survey feasibility.
Although microtrenching has a narrow intervention width, a reliable assessment is needed for the full milling depth and actual planned alignment. The surface, existing utilities and technical interference sources can affect survey feasibility. The suitable approach is therefore derived from ground conditions, suspected hazards and the required confidence of the assessment.
If an unexpected suspicious object is found, stop work. Do not touch, move or uncover it further. Leave the immediate area and warn others without putting yourself at risk. In Germany, notify the police on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine what happens next; a project enquiry does not replace reporting the find.
Route plans should be as up to date as possible and show chainage, standard cross-sections, construction depths, crossings, chambers, distribution cabinets and rollout clusters. Utility and existing asset plans, historical assessments, authority correspondence, ground investigation data, installation methods, traffic phases and the desired handover date are helpful.
Information and requirements from authorities are supplied with their date, complete appendices and geographical scope. In Germany, the competent ordnance disposal service, local public-order authority and, where relevant, building-control authority are identified for the project location; outside Germany, local responsibilities apply.
Sections are assigned a consistent system of chainage, contract section references and identifiers. Survey lines, borehole locations, daily work sections, limitations and outstanding measures refer to the same design revision. This allows network operators and site management to update work status consistently across several crews and contractors.
Suitable supplementary measures are defined for areas not adequately surveyed in advance. Where explosive ordnance surveying during construction is technically suitable, each working layer is technically surveyed and assessed before controlled removal with supplementary visual inspection. These steps are repeated down to the agreed excavation base. Excavation conditions, layers, hold points, reporting lines and documentation are defined before work begins. Necessary surveys and protective measures are also planned before ground intervention during surface breaking or dismantling; areas not covered remain outstanding.
In Germany, state explosive ordnance disposal services and the locally responsible authorities carry out hazard prevention and find-handling duties. Outside Germany, local responsibilities apply. The privately commissioned specialist contractor carries out the agreed survey and documentation. Reporting procedures and contacts are clarified for each section before earthworks begin.
Factors include route length, number of rollout clusters, surfaces, existing utilities and interference, construction depths, crossings, deep intervention points, accessibility, construction windows, data formats and documentation scope. Reliable costing therefore needs current alignments, installation methods and clear boundaries for the sections actually to be addressed.
An initial enquiry can be based on an early design revision. The rollout area, priority sections, construction method and required decision must be identifiable.
Send site or GIS plans showing the backbone, local network, sections, chainage, street or land parcel references and priority construction clusters.
Mark route options, alignments not yet defined and areas with different approval or construction dates.
For several contract sections, the intended section and file naming should already be identifiable in the enquiry documents.
Describe open trenches, trenching, ploughing, impact moling, thrust boring, directional drilling, chambers, distribution cabinets and property connections.
State the standard cross-section, excavation depth, pit dimensions, bore paths and possible working areas outside the alignment.
Crossings and deep intervention points are considered separately from the near-surface standard route.
Include utility plans, historical assessments, authority documents, ground investigation data and known areas of interference.
Specify construction phases, daily output, closure or traffic windows, data formats and the decision deadline.
Incomplete documents are also relevant because they show which baseline information still needs to be obtained or coordinated.
For an initial assessment, a route plan, rollout clusters, standard cross-section, installation method, maximum depth, number of crossings and network nodes, planned construction start and existing explosive ordnance indications are often sufficient. FONTANA-EOD then identifies the required service scope and data.
For large rollouts, work can be phased according to construction design readiness and priorities. This provides reliable assessments early for imminent rollout sections without prematurely fixing later route sections or those still subject to change.
Alignment, chainage, rollout cluster, contract section, street or land parcel and current design revision.
Trench width, excavation depth, milled slot, bore path, launch and reception pits, and chambers.
Existing utilities, traffic areas, structures, rails, technical interference sources and accessibility.
Construction phases, crews, daily quantities, approval status, data handover and decision deadlines.
Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.
FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.