Explosive ordnance assessment for substations and transformer stations

Before work at a substation or transformer station, foundations, cable routes, earthing systems and ancillary areas are checked against the available explosive ordnance records. FONTANA-EOD plans suitable surveys according to the installation layout, depth of intervention, existing infrastructure and operational access. Send installation and foundation plans, point lists, depths and construction phases so that services and documentation can be defined before earthworks, drilling and foundation work.

Divide the installation site into assessment areas

Identify foundations, cable routes and ancillary areas.

Define the depth

Record piles, gantries and excavations.

Involve operations

Coordinate access, shutdowns and documentation.

Assess utility and energy projects

Before foundations, cable trenches and installation construction

Clarify survey requirements before foundations and cable trenches

Before earthworks and foundation work, existing hazard indications and planned ground interventions are used to clarify which explosive ordnance surveys are required. Foundations, cable channels, earthing systems, drainage, access roads and excavations are considered. The detailed construction geometry of each component is decisive; a general area figure for the operating site is insufficient for deep or individual point interventions.

Project references

Selected project examples

Divide installation construction by ground intervention geometry

Plan foundations, cable routes and ancillary installations separately

A substation consists of different construction and operational zones. Transformer foundations, gantries, cable channels, operational buildings, access roads, drainage and earthing systems differ in area, depth and interference from technical installations.

The explosive ordnance assessment therefore follows the specific installation layout and construction phase plan. Each volume of ground is assigned its own work status, which can subsequently be carried through into tendering, site management and project records.

Where operations continue, work boundaries, access conditions, shutdowns and safety zones are coordinated with the technical assessment. Inaccessible zones are not given a blanket assessment; they are identified for a later construction stage or a suitable alternative measure.

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Transformer and installation foundations

Transformers, compensation equipment and switchgear require load-bearing foundations, oil containment structures or deeper foundation elements. The assessment relates to foundation dimensions, excavation depth, piles and possible underlying structures.

Near-surface surveys do not automatically assess the full volume at depth. For pile or borehole locations, we check whether existing surveys cover the required depth and what additional work may be needed.

Assess foundation and deep intervention points
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Cable trenches and cable channels

Cable routes run between switchgear bays, transformers, operational buildings and grid connections. Depth, width, crossings and existing cables determine the actual volume of ground affected.

Existing cables, metal installations and earthing conductors can limit survey feasibility. The utility trench is therefore planned in sections and linked to the construction stage.

Select methods for cable trenches and channels
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Gantries, masts and steelwork alignments

Gantries, busbar supports, lightning protection masts and overhead line pylons involve numerous individual foundations. Point location, target depth, diameter and installation method must be consistent with the survey plan.

Relocated or additional points are not assumed to be covered by an earlier area assessment; they are reassessed against the documented survey geometry.

Prepare gantry and mast locations
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Operational buildings and technical rooms

Switchgear buildings, protection and control buildings, workshops and storage areas require excavations, ground slabs, service connections and often additional foundation points.

The building area is considered as a connected volume of ground affected, including external works, cable entries and drainage. This makes the interfaces between building construction and installation construction identifiable on the plan so that outstanding surveys can be checked.

Assess the building area
Two people discussing plans at a table beside a vehicle on a construction site.

Drainage, retention and ancillary installations

Swales, channels, chambers, retention basins, oil separators and firefighting water systems may lie outside the switchgear bays themselves while still involving substantial ground intervention.

These structures are included in the assessment area with their location, depth and excavation geometry. Later design changes are checked against the existing status of work.

Match ancillary installations to documentation
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Access roads, crane areas and temporary construction arrangements

Heavy-load access roads, crane standing areas, assembly areas and temporary cable routes may require ground improvement, excavation or load distribution measures.

Temporary areas are also assessed where ground intervention is involved. The documentation distinguishes permanent installation areas from temporary construction work zones.

Assess logistics and assembly areas
Planning, operations and construction stage

Prepare surveys for installation design, tendering and modifications

Substation projects develop from site and option comparisons to a detailed installation layout. Foundations, cable routes, excavations and temporary areas are defined more precisely at each design stage.

The explosive ordnance assessment is updated when components, depths or construction phases change. An early area assessment is checked against newly added deep intervention points or relocated installation alignments. This establishes what supplementary work is required.

Site and land development

Before securing land or preparing the outline design, we clarify whether historical sources, previous uses or known finds establish a spatially defined suspicion.

The early assessment supports layout options and prioritises technical survey areas without providing a conclusive assessment of the ground for later construction.

Assess the site using historical evidence

Design and approval planning

As soon as the locations of switchgear bays, transformers, operational buildings and cable alignments are defined, the suspected hazard areas are overlaid with the installation layout.

This creates specific area, linear and point assessment tasks for procurement, scheduling and HSE coordination.

Define the assessment scope for planning

Tendering and specifications

Areas, depths, methods, access, sources of interference, data formats and required documentation must be described consistently for all tenderers.

Generic explosive ordnance survey items are generally insufficient for installation sites divided into many different areas.

Prepare a service scope suitable for tendering

Deep foundations and borehole locations

Piles, boreholes, masts, gantries and shoring alignments require assessment of the actual volume of ground affected at each point and depth.

Coordinates, target depth, diameter, installation method and safety distances are brought together before fieldwork.

Investigate deep foundation volumes

Alterations during ongoing operations

Existing installations can restrict access and survey conditions. Dismantling, shutdowns and new construction are divided into stages so that newly accessible zones are assessed at the appropriate time.

Operational authorisation to work and the status of explosive ordnance work remain documented as separate decisions.

Coordinate modification phases and assessment timing

Anomaly or find during construction

A survey anomaly, a technical source of interference and an actual suspicious object must be distinguished.

If an unexpected suspicious object is encountered, work is stopped immediately and the responsible authorities are notified without delay. Work resumes in accordance with their instructions.

Document findings and subsequent decisions
Suspected hazards, survey feasibility and documentation

Record surveyed and outstanding installation areas

Historical indications, technical survey feasibility and the planned ground intervention geometry are initially considered separately. Suitable surveys are then selected for each installation area.

Area-based methods may be suitable on an open new-build site, while an existing installation area may be strongly affected by steel structures, cables and the earthing grid. The status of work is therefore recorded by component and section.

Area with historically substantiated indications

Aerial photographs, maps, archives or existing project records substantiate a possible suspicion in parts of the site.

The suspected hazard area is overlaid with the installation layout, excavations, cable routes and temporary areas.

The historical assessment leads to a prioritised technical assessment task; it does not yet describe an individual object whose presence has been demonstrated.

Define the spatial extent of the suspected hazard area

Open new-build area involving area-wide ground intervention

An accessible area without dominant technical interference can be surveyed geophysically over its extent.

The method and survey grid depend on the target object, ground and surface conditions, required depth of usable data and subsequent excavation.

Marginal zones that cannot be surveyed remain visible on the site plan and are assigned their own follow-up measure.

Plan an area-based survey

Existing installation area with steel and cable infrastructure

Switchgear bays, masts, earthing conductors, transformers and utilities can obscure survey data.

The area is divided according to accessible zones, dismantling stages and available work windows.

Suitable supplementary methods and later survey access are assessed for areas that cannot be surveyed adequately. Explosive ordnance surveying during construction is an option only where technically suitable.

Clarify assessments and alternative measures in existing installation areas

Deep ground intervention for a foundation or mast

A planned pile, borehole or mast base affects a clearly defined volume at depth.

The assessment relates to the point location, target depth, drilling or installation method and existing utilities.

The result applies to the documented assessment geometry, not to neighbouring points or the entire installation site.

Survey the point location and volume at depth

Excavation in a technically constrained zone

Cable trenches, foundation repairs or dismantling areas may become fully accessible only during construction.

First, the technical suitability of explosive ordnance surveying during construction is assessed for each excavation layer. The working layer is technically surveyed and assessed before controlled removal in layers with supplementary visual inspection. These steps are repeated down to the agreed excavation base. Equipment use, hold points, authority to issue instructions, communication channels and documentation are defined before work begins.

The documentation describes only the areas and depths actually supervised.

Provide controlled supervision of an excavation section

Anomaly, exposure and follow-up decision

Areas with anomalous readings are assessed at their exact locations and compared with known installations and the project geometry.

Survey anomalies undergo technical follow-up investigation or exposure. Recovery of confirmed explosive ordnance is coordinated with the permitted scope of work and local responsibilities. Necessary changes to the construction sequence are related to the affected installation area.

Findings, work and handover remain linked to the original volume of ground affected in the project records.

Record survey results and further measures
Project records by installation area

Documents demonstrating the status of work at the substation

Substations require documentation linking the installation layout, construction phases and specialist work. Areas, lines, points and depths receive the same identifiers as in design and construction.

In addition to results, the documentation describes inaccessible zones, technical interference and the resulting follow-up decision. This makes clear which assessment applies to which construction stage.

Project and spatial reference

The project designation, land parcel, coordinate system, installation layout, construction area, construction section and limits of work form the spatial basis.

Transformer locations, gantries, cable routes, operational buildings and ancillary installations are recorded with unique asset identifiers.

Basis for suspicion and assessment

Historical assessments, authority documents, earlier reports and known finds are documented with their source, date and scope.

Conflicting or missing information remains visible as an outstanding project task and is not replaced by general assumptions.

Survey and working conditions

The survey principle, grid, survey direction, assessment depth, borehole geometry, surface, ground conditions, accessibility and sources of interference are described by section.

For existing installations, steel structures, cables, the earthing grid, vehicles and operating conditions are recorded as factors affecting data evaluation.

Survey data, anomalies and findings

Raw data, evaluations, anomaly lists, site plans, field records and exposure findings must cross-reference one another.

Anomalies receive unique identifiers so that further work remains traceable through to the follow-up decision.

Areas that cannot be investigated and changed areas

Lack of access, existing utilities, technical interference or a different construction stage can limit the survey.

These areas are identified on the plan. Suitable supplementary methods and later survey access are assessed for them.

Final and handover documentation

The final report describes the area, points and volume at depth actually addressed, the methods used and remaining limitations.

Design changes and additional components are checked against this status before existing documentation is reused.

Design revision, fieldwork and project communication

Keep installation plans and survey results at the same revision

The project records contain historical evidence, technical survey results, findings and construction progress information. All documents relate to the same design revision and asset structure.

For extensions carried out in several phases, it remains clear which areas have already been addressed, which become accessible only after dismantling and which new components need supplementary assessment.

Baseline data and installation layout

Site plans, land parcels, switchgear bays, transformers, gantries, buildings, cable routes and ancillary installations are retained as the shared project basis.

The design revision and change index identify the geometry to which a result applies. Before a new construction section begins, this revision is checked against the current design.

Historical data basis

Sources, suspected hazard areas, previous uses and known find information are related spatially to the site.

The historical assessment remains distinguishable from technical survey results and actual findings.

Survey and point data

Survey areas, borehole locations, depths, lines, field conditions and quality checks are documented with georeferencing.

File naming and asset identifiers allow links to the foundation plan, cable plan and construction sequence.

Findings and action status

Anomalies, exposures, technical sources of interference and actual finds are assigned a work status that can be updated.

Outstanding points are recorded with the planned follow-up measure, responsibility and reference to the next construction section.

Communication and handovers

The client, designers, site management, HSE, contractors and responsible authorities receive the documents needed for their roles.

Handovers document the design revision, asset register, outstanding areas and the agreed next decision point.

Project file and updates

Reports, site plans, data lists and records are brought together in an auditable project record. After actual exposure or clearance work, the corresponding findings and clearance records are included.

Extensions, replacement installations and additional utility alignments are included as updates without extending the scope of earlier results.

From site assessment to installation assembly

Schedule surveys and handover of results within the construction phases

The sequence follows design readiness, construction conditions and the actual ground intervention geometry. Early assessment of suspected hazards provides orientation; as the design becomes more detailed, the technical assessment is related to individual components and construction phases.

At operational sites, dismantling, access and operational authorisations are coordinated with survey dates. This records when each volume of ground becomes accessible.

01

Record the project and construction conditions

The site, new construction or extension, installation layout, construction phases, operating conditions and required decision are clearly described.

The initial comparison shows which areas are ready for construction and where design or existing asset data are missing.

02

Review records and the suspected hazard

Site plans, historical assessments, authority documents, earlier reports, utility plans and known finds are compared spatially.

This identifies prioritised investigation volumes and visible data gaps.

03

Define the volumes of ground affected and depths

Foundations, cable trenches, gantries, buildings, drainage and temporary areas are described by area, point location and target depth.

The geometry forms the basis for tendering and fieldwork planning.

04

Select methods and supplementary measures

The target object, ground and surface conditions, interference, accessibility and required depth of usable data determine the suitable service.

Supplementary methods are planned in advance for deep areas or areas subject to technical limitations.

05

Organise access and work

Operational authorisations, shutdowns, exclusion zones, briefings, setting out, equipment and communication channels are coordinated before mobilisation.

The deployment plan takes account of concurrent civil engineering and installation work.

06

Carry out surveying and monitoring

Area-based surveys, deep-ground surveys or excavation supervision are carried out at the relevant locations using the agreed methodology.

Departures from the plan and inaccessible zones are documented immediately.

07

Assess data and findings

Readings, anomalies, exposures and interference sources are assessed for plausibility against the basis for suspicion and the construction geometry.

A technical follow-up decision is formulated for outstanding areas.

08

Hand over and update results

The report, plans, point lists, limitations and status of measures are prepared for project records, site management and subsequent trades.

New design revisions or additional components are checked against the documented scope of work.

Link areas, lines and deep intervention points

Show foundations, cable routes and foundation points on the installation plan

The explosive ordnance task follows the combined planned ground interventions rather than the property boundary. Areas, cable alignments, excavations, individual foundations and temporary work zones are therefore recorded separately.

An installation layout may change several times during detailed design and tendering. Each change is overlaid with the existing status of work before results are applied to new geometries.

Specify the area, depth and construction method for each component

Transformer foundations, switchgear bays and operational buildings involve area-wide excavations. Cable trenches, earthing conductors and drainage form linear interventions. Gantries, masts, piles and boreholes involve point-specific tasks at depth. These geometries share a common location reference but are addressed using different methods.

For each geometry, the top and bottom levels, working width, slopes or shoring, installation method and possible positional deviations are described. For deep individual ground interventions, the full working and safety space around the subsequent component matters, not just its centreline.

Existing cables, earthing grids, steel structures and transformers can obscure geophysical signals. We therefore distinguish open survey areas, areas subject to technical limitations and zones accessible only after dismantling. The report shows these differences spatially and links them to a specific follow-up measure.

Area-wide installation works

Excavations for transformers, switchgear bays, buildings or retention structures are recorded with their actual extent and depth.

Marginal zones, working spaces and future extension areas remain distinguishable from unaffected operational areas.

Linear cable and drainage alignments

Cable trenches, channels, drains and pipelines are described with their alignment, width, depth, chambers and crossings.

Changes between sections and existing utilities are considered when selecting methods. Explosive ordnance surveying during construction is an option only where technically suitable.

Individual foundations and gantries

Mast, gantry, pile and borehole locations are assigned coordinates, target depth, diameter and installation method.

The documentation remains limited to this recorded point geometry and is updated if locations change.

Earthing grid and metal interference

Earthing conductors and steel structures affect magnetic and electromagnetic surveys.

Existing plans and actual construction conditions are used to identify areas where data can be evaluated and to establish method limitations.

Dismantling and modification stages

In existing installations, foundations, cables and steel structures may become removable or accessible only after defined dismantling steps.

The assessment is linked to these construction stages so that outstanding zones are not mistakenly treated as completed. Necessary surveys and protective measures are planned before ground intervention during dismantling or the creation of access.

Temporary construction and logistics areas

Crane areas, heavy-load access roads, storage and assembly areas are included where ground improvement, excavation or foundations are planned.

Permanent and temporary volumes of ground addressed are assigned separate identifiers and handover points.

Select an investigation

Select surveys according to existing installations and accessibility

Two people with a tablet beside a marked construction area; plans lie in the foreground.

Record survey conditions in the existing substation

When existing substations are extended, steel structures, transformers, switchgear bays, earthing grids, cables and paved surfaces can substantially affect geophysical surveys. We therefore define early which areas are freely accessible before installation construction, which can be surveyed only after dismantling and where depth-specific assessment is needed.

Choose suitable methods for the survey conditions
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Plan new construction and operational modifications separately

New-build sites, brownfield sites and modifications at operational installations have different planning conditions. A historical assessment clarifies the spatial extent of suspected hazards; the technical survey is then related to transformer foundations, gantries, operational buildings, cable routes, firefighting or retention facilities and temporary assembly areas.

Determine survey requirements for new construction and modifications
Select methods according to the project question

Which specialist service addresses which volume of ground at the energy installation

Historical sources and technical surveys provide different information about the site. Selection depends on the installation area, target object, depth and sources of interference.

01

Historical aerial photograph analysis

Substantiates and defines the limits of a historical suspicion at the site.

It does not establish which objects are actually present in the ground today.

02

Magnetometry

Responds to ferromagnetic objects and can be effective in open areas with little technical interference.

Steel structures, the earthing grid, vehicles and utilities can severely limit data evaluation in an existing substation.

03

TDEM

Records time-dependent electromagnetic responses from conductive objects.

The effects of electromagnetic installations, cables and ground conditions are assessed before deployment.

04

Ground-penetrating radar / GPR

Shows reflections at material and structural boundaries and can provide supplementary information on suitable paved areas.

The reflection alone does not permit unequivocal identification of an object as explosive ordnance.

05

Deep-ground and downhole surveys

Assesses defined point locations and volumes at depth for piles, gantries, boreholes and deep foundations.

Borehole geometry, casing, target depth and subsequent construction method must be coordinated.

06

Excavation supervision

Where explosive ordnance detection during construction is technically suitable, each working layer is surveyed and evaluated using technical methods. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base.

Excavation layers, stopping points, authority to give instructions, communication procedures and documentation are defined in the work instruction before work begins. Merely watching the excavator at work is insufficient.

Coordination before fieldwork

Check installation plans against survey results before earthworks

Designers, the specialist contractor and site management define which areas and depths are to be surveyed and which documents are needed before each construction section.

Energy installations also involve operational safety requirements, technical interference and short construction windows. These constraints are incorporated into the sequence before fieldwork.

Hand over results for foundations, cable routes and foundation points

FONTANA-EOD starts by asking what assessment is needed for each installation area. For each transformer foundation, cable trench and gantry point, we check whether existing results cover the planned area and depth.

Methods are selected according to the suspected hazards, target object, ground and surface conditions, required depth and technical surroundings. At existing installations, steel structures, cables, the earthing grid and operational access are treated as actual limitations.

During the work, survey areas, point lists and construction sections remain linked to the applicable design revision. Changes are assessed before an existing result is used for a new geometry.

Anomalies are communicated with precise locations. A survey anomaly, a technical source of interference and an actual find remain distinguishable so that site management and the responsible authorities can decide on a clear information basis.

The final documentation describes the status achieved and its limitations. It can therefore support procurement, site management, HSE and later extensions without implying a broader assessment of areas not surveyed.

Define the area and depth

The installation area, ground intervention, depth, construction stage and required assessment are defined before work begins.

Select suitable methods

Methods are deployed according to technical suitability, rather than equipment availability alone.

Coordinate access with the operator

Access, shutdowns, exclusion zones and concurrent trades inform deployment planning.

Locate results on the installation plan

Survey areas, points, findings and limitations remain linked to the current installation plan.

Document design changes

Design changes and new components are checked against the existing status of work.

Identify outstanding tasks

The report shows which areas have been surveyed and which tasks remain outstanding before the next ground intervention.

Prepare the next construction section

Coordinate the survey commission with the construction phases

Describe the volumes of ground affected and the results needed

For a reliable commission, the area, point location, ground intervention depth, construction method, existing utilities, construction conditions and documentation objective are clearly described. FONTANA-EOD uses this information to define the surveys and documentation required. Methods are selected according to their technical suitability.

Coordinate access before dismantling and installation assembly

Survey dates are linked to the installation areas actually accessible. Where cable channels, earthing systems or foundations become accessible only during dismantling, this later survey requirement is explicitly recorded in the construction sequence. Necessary surveys and protective measures are planned before preparatory ground interventions. Operational prerequisites are coordinated with the operator.

Responsibilities and interfaces

Who manages design, operations, construction and communication about finds

Grid operators, designers, civil engineering contractors, installation contractors, HSE, specialist contractors and responsible authorities have different tasks. Before construction, it is defined who provides documents, reports design changes and receives survey results.

Client and operator

Grid operator, municipal utility or project company

Define the project objective, installation layout, construction phases, operational constraints and documentation required.

They provide existing asset records and hazard information and commission the necessary specialist services.

Design

Engineering, electrical and geotechnical design

Translate the project into specific areas, cable alignments, foundations, borehole locations and ground intervention depths.

The specialist design incorporates the explosive ordnance assessment into the design, specification and key project milestones.

Operations and HSE

Installation personnel and safety organisation

Regulate access, shutdowns, exclusion zones, briefings and operational authorisations to work.

Their requirements determine when and under what conditions individual installation areas are accessible.

Construction execution

Civil engineering, foundation and installation contractors

Construct excavations, cable trenches, foundations and assembly areas within the agreed volume of ground.

Changes to location, depth or construction method are reported to the relevant specialists before construction.

Specialist service

FONTANA-EOD

Assesses documents and suspected hazards, develops the commissioned approach and documents results and limitations.

The service is linked to the design revision, construction stage and specific project decision.

Competent authorities

KBD, KMBD, KRD and local authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and, where applicable, building control are involved according to their project responsibilities. Conditions and contacts are assigned to the actual installation areas and construction sections; reporting procedures are defined before work begins.

If an unexpected suspicious object is found, notify the police immediately on 110 in Germany; outside Germany, the local emergency reporting procedure applies. The competent authorities determine the next steps.

From the installation site to project records

Documents used in practice for substation projects

Typical deliverables link the installation layout, basis for suspicion, fieldwork and construction progress. They show not only survey results but also their spatial scope and the resulting decision.

Historical assessment, deep-ground surveys, excavation supervision, investigation of findings and the final report remain identifiable as separate specialist services and are brought together for each installation area.

Four people in orange high-visibility vests in front of two excavators on a construction site.
Person with a yellow survey cart on a footpath in front of a hedge.
Identify the project location

Clearly locate installation areas and construction sections

Illustrated map of Germany with location markers on a construction site.

Identify the site and applicable requirements

State the project location, installation designation and affected switchgear bays, transformer areas or cable sections. The site plan, foundation list and operational access plan must identify the same design revision. Existing requirements are assigned to the relevant volumes of ground affected.

Use results correctly

Use existing results for an installation extension

Assess foundation changes spatially and at depth

A new transformer or a changed gantry may require different foundation dimensions and depths. Compare the current foundation geometry with the documented survey volume and mark areas extending beyond it.

Check evidence against the intervention

Record cable routes and earthing work separately

Even smaller cable or earthing works may lie outside previously surveyed areas. Show their routes and planned depths on the installation plan so that the work does not focus solely on the large foundation areas.

Explore the technical principles

Technical information

Utility and energy projects: brochure

Utility routes, substations and energy installations place different demands on ordnance assessment. The brochure shows the design information needed and how investigation, construction sequence and documentation fit together.

1 / 8
Utility and energy projects: brochure – page 1

German · 8 pages

Common project questions

What should be clarified before foundations, cable trenches and installation construction

Before each construction section, grid operators, designers and contractors need information on surveyed areas and outstanding tasks. The installation layout, ground intervention depth, construction stage and technical survey feasibility remain decisive.

When should a substation or transformer station be assessed for explosive ordnance?

The assessment should begin as soon as the site and main construction geometries are known. Before ground investigation, foundation excavation, cable trenches, piles, gantries and temporary heavy-load areas, the suspected hazards and specific volume of ground affected must be assessed.

Is a historical aerial photograph assessment sufficient for installation construction?

The historical assessment substantiates and defines the limits of a possible suspicion, but does not detect objects currently in the ground. Where relevant indications exist, a technical assessment follows, related to the foundations, cable routes, buildings and other ground interventions in the installation layout.

How is an existing earthing grid taken into account in surveys?

Earthing conductors, steel structures, cables and technical installations can affect magnetic or electromagnetic surveys. Existing asset plans, construction conditions and accessible survey areas are therefore checked before deployment. Suitable supplementary methods and later survey access are assessed for areas that cannot be evaluated adequately.

When is a deep-ground or borehole survey required?

Piles, masts, gantries, shoring and ground investigation boreholes may extend beyond the area covered by near-surface surveys. We then assess which method can cover the planned volume of ground down to the required depth. Coordinates, diameters, installation methods, ground conditions and technical interference are considered when selecting the method.

Can the assessment take place while the installation remains operational?

This depends on the project. Access, shutdowns, exclusion zones, electrical installations, survey interference and concurrent work are coordinated with the operator. Areas that cannot be accessed reliably in their current condition are assigned to a suitable later construction stage.

What documentation do grid operators and site management need?

The documentation must include the task, design revision, installation and point references, methods, survey and working conditions, data, anomalies, findings, areas that cannot be assessed, limits of work and the technical follow-up decision for each construction section.

What determines the effort and cost of an ordnance assessment?

Key factors are the area, number and depth of foundation and borehole locations, cable routes, accessibility, ground and surface conditions, technical interference, operating conditions, required methods, data formats and the scope of project and final documentation.

What should you do if a suspicious object is found?

Stop work in the affected area immediately. Do not touch, move or further expose the object. Leave the danger area and keep others away without putting yourself at risk. In Germany, notify the police immediately on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine the next steps. Then inform site management and those responsible for the installation.

Documents for specialist assessment

Information required for installation layouts, foundations and cable routes

An initial enquiry can be based on an early design revision. It should identify the site, installation layout, planned construction phases, main ground interventions and the next decision required.

For extensions, distinguishing existing installations, dismantling, modifications and new construction is particularly important. This allows assessment requirements to be related to work that actually involves ground intervention.

Incomplete or conflicting documents can be included. They show which design or existing asset information needs clarification before a reliable specification can be prepared.

Site and installation layout

Send the address, land parcel, site plan, coordinate system, switchgear bays, transformer locations, buildings and planned extension areas.

Mark existing installation areas, dismantling zones, construction sections and provisional layout options.

Where several design revisions exist, clearly identify the revision relevant to the assessment.

Ground interventions, depths and construction methods

Describe foundations, piles, masts, gantries, cable trenches, drainage, excavations, boreholes and temporary heavy-load areas.

Specify target depths, diameters, slopes or shoring and the planned construction sequence.

Deep individual ground interventions should be listed with coordinates and target depths.

Existing structures, operations and earlier documents

Include utility, earthing and existing asset plans, historical assessments, authority documents, previous survey reports and known findings. Information and conditions from authorities are included with their date, complete attachments and spatial scope.

State access conditions, shutdowns, exclusion zones, construction windows and concurrent trades.

Describe whether the result is needed for planning, tendering, site management or project records.

For initial technical assessment

For an initial assessment, a site plan, brief project description, foundations and cable routes, maximum ground intervention depths, current construction conditions and existing hazard information are often sufficient.

FONTANA-EOD checks your documents to identify which surveys are required and what information is missing. For projects with several phases, work can be divided by construction section and decision deadline.

Areas, point quantities, depths, access, data formats and required documentation are then defined more precisely for reliable costing.

Areas and construction sections

Installation area, switchgear bays, buildings, temporary areas and inaccessible zones.

Points and depths

Transformer foundations, masts, gantries, piles, boreholes and target depths.

Existing assets and operations

Cables, earthing grid, steel structures, shutdowns, exclusion zones and construction windows.

Documentation objective

Documents for planning, procurement, HSE, site management, the operator or project records.

Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.