Two people with a survey trolley on a road construction site beside an existing carriageway.

Explosive ordnance investigation for structural foundations in civil engineering

Before piles, boreholes and other foundation elements are installed, the planned intervention is checked against the existing suspected hazard. FONTANA-EOD plans suitable investigations according to location, depth, cross-section, inclination and installation method. Send the foundation plan, point list, working platform details and installation dates so that services and documentation can be defined before the respective groundworks.

Assign points

Assign coordinates to the components.

Reflect depth

Record the drilling and installation volume.

Document execution

Record investigation status for each foundation.

Investigation requirements for structural foundations

Establish investigation requirements before foundation work

Before foundation work, existing indications of suspected ordnance are used to establish what investigations the planned piles, boreholes, anchors and foundations require. Point location, diameter, inclination, target depth and installation method determine the ground volume to be considered. Earlier investigations can be reused only insofar as their documented coverage matches the intervention. If the location, depth or construction method changes, the need for supplementary investigations is assessed.

Project references

Selected project examples

Explosive ordnance survey – Hannover (Mecklenheide) – freight terminal, new stabling tracks and lighting-mast foundations Hannover (Mecklenheide) / Deutschland

The scope of services for ‘Hannover (Mecklenheide) – freight terminal, new stabling tracks and lighting-mast foundations Hannover (Mecklenheide) / Deutschland’ included downhole magnetometry.

Service period: 2025-01

Service areas:Downhole magnetometry / deep-ground survey

View project details · Deep-ground and downhole surveys · Project location: Hannover

Foundation types and interventions

Which foundation elements require their own investigation geometry

Foundation elements differ in cross-section, depth, inclination, energy input and installation path. Explosive ordnance investigation is therefore coordinated with the actual ground corridor of each element.

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Bored piles and large-diameter bored piles

Bore diameter, target depth, casing, drilling method and any support fluid determine the technical working geometry.

The borehole starting point, pile axis and investigation points use the same survey reference. Changes to diameter or depth are updated before execution.

If supplementary depth investigation is needed, the need for several survey lines or boreholes is assessed to ensure technically adequate coverage of the entire cross-section.

Investigate bored piles and depth
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Driven piles and displacement piles

Driving and vibratory methods introduce considerable energy into the ground. Pile cross-section, embedment depth and installation path therefore form the basis of depth investigation.

An area survey covers a pile only if the documented investigation actually includes its required location and depth.

The actual pile path, including the displacement zone and any predrilling, is treated as a continuous ground volume of the works.

Investigate driven and displacement pile points
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Micropiles and grouted piles

Small diameters may involve considerable lengths, inclinations and drilling in confined areas around existing structures.

The starting point, inclination, borehole length and target area are considered in three dimensions; existing structures and utilities influence the possible survey and borehole geometry.

For existing foundations, a clear distinction is made between existing piles, planned additions and elements to be demolished.

Submit the micropile geometry
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Shallow and isolated foundations

The foundation base, excavation width, frost skirts, foundation sockets and working space determine the near-surface investigation zone.

For greater depths, pile caps or additional anchors, the adequacy of the existing investigation and the suitability of any supplementary method are assessed.

Excavation for pile caps or foundation slabs is treated as a separate near-surface task in addition to depth investigation.

Coordinate foundation excavation
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Sheet piles, shoring and anchors

Shoring alignments and anchors often form a functional part of the foundation or excavation support. They extend linearly or obliquely into areas outside the foundation footprint itself.

The alignment, embedment depth, anchor inclination and installation method are therefore planned separately.

Interfaces between shoring, foundations and the excavation base share a common spatial reference so that no gap remains between them.

Investigate shoring and anchor areas
Two people discussing plans at a table beside a vehicle on a construction site.

Well, caisson and special foundations

Large foundation bodies or bodies lowered in sections create changing depth and excavation volumes.

Suitable preliminary and depth investigations are planned for the individual installation steps. An explosive ordnance survey alongside construction is considered only if technically suitable for the intended excavation.

Special foundations are divided into their individual installation steps where sinking, excavation or grouting occupy different ground volumes.

Structure the special foundation task with specialist input
Decisions before foundation work

What information is needed before design, tendering and installation

The more precise the foundation design, the more reliably the investigation geometry, effort and documentation can be defined. Unclear point lists and changes in method are reconciled before investigation so that the scope and possible additions are established.

Geotechnical and preliminary planning

At an early stage, the structure’s location, possible foundation systems, areas of historical suspicion and available working areas are brought together.

The assessment shows which options create additional explosive ordnance investigation requirements or require particular construction stages.

Preliminary planning assesses whether an alternative structure location or foundation type significantly changes the scope of deep explosive ordnance investigation.

Historically assess the structure’s location

Defining the foundation system

Pile type, diameter, grid, target depth, inclination and installation method are specified as binding parameters.

This data defines which points, alignments and depths require technical investigation.

Before these parameters are defined, test piles, static load tests and ground investigation works are also recorded as possible interventions.

Determine the extent of foundation investigation

Detailed design and construction drawings

Point numbers, coordinates, pile-head elevations, borehole starting points, casing and possible additional boreholes are checked for plausibility.

Different plan lists are brought to a common revision before mobilisation.

Before tendering, point lists from structural design, surveying and specialist foundation engineering are checked for identical identifiers.

Have execution documents checked

Tendering and procurement

Quantities, investigation depth, borehole construction, setting out, data format, quality control and the report are clearly defined.

For alternative foundation methods, a rule defines when the explosive ordnance investigation must be adapted.

The specification defines how to handle points where drilling is not possible, shortened survey paths and anomalous signals.

Prepare the tendering basis

Site establishment and preliminary work

Access, equipment position, utilities, existing foundations, drillability, dewatering and occupational safety are coordinated with investigation planning.

Inaccessible points are identified early and assigned to a technical alternative or a later construction phase.

Before mobilisation, equipment standing areas, the working platform, drilling sequence and available working width are agreed. Necessary investigations and protective measures are planned before groundworks to construct these facilities, and before vegetation clearance, demolition or surface removal.

Agree deployment conditions

Changes during installation

Point relocations, additional foundations, greater depths or changed pile types are checked against the existing documentation before the intervention.

Site management receives a clear status showing which elements remain covered and which require new investigation.

Additional or replacement piles receive a new specialist status check, even where they are immediately beside a point already investigated.

Update foundation changes
From suspicion to the foundation decision

Select the investigation method for each foundation point

The investigation that follows depends on the planned foundation volume and existing findings. Historical assessment of suspicion, technical surveying and actual findings remain clearly distinct.

The suspected hazard has not yet been reliably delineated

Historical sources are related to the structure’s location, foundation grid and site establishment areas.

The result describes suspected areas, data gaps and technical investigation requirements.

The area covered by historical investigation includes pile groups, the excavation edge and necessary working areas as well as the structure’s footprint.

Unobstructed area with near-surface works

Accessible areas may be investigated using a suitable area-survey method before excavation or shallow foundation work.

The statement applies to the zone technically covered, rather than automatically to deep piles or boreholes.

A near-surface survey is used only for the depth range demonstrated; deeper foundation components still require separate investigation.

Deep vertical pile points

The point location, diameter and target depth define the deep ground volume of the works. First, it is checked whether the required location and depth have already been sufficiently investigated. Any supplementary depth investigation needed is designed around this geometry.

Survey and execution identifiers remain identical throughout the project chain.

For borehole surveying, borehole spacing and survey paths are derived from the cross-section and target volume, rather than adopted indiscriminately from neighbouring projects.

Inclined piles or anchors

The relevant corridor extends spatially away from the starting point. Considering only the visible starting coordinate would give an incomplete picture of the subsequent intervention.

Inclination, length and target area are therefore incorporated into the investigation and documentation geometry.

For inclined elements, particular attention is paid to whether the deep end lies outside the construction site area originally investigated.

Existing area dominated by technical interference

Reinforcement, existing piles, utilities and foundations may interfere with survey data and limit survey drilling.

Areas not sufficiently investigated are shown on the plan. The suitability of supplementary methods and access options is assessed for these areas.

Outstanding questions about these points are clarified before pile installation. A changed foundation design or later exposure is coordinated with the planners and site management.

Anomalous point requiring further clarification

Survey signals are checked for plausibility against drilling data, information on existing structures and neighbouring points.

Depending on the specialist assessment, survey anomalies receive supplementary detection or exposure. Recovery of confirmed explosive ordnance is coordinated with the permitted scope of activity and local responsibilities. If an unexpected suspicious object is encountered, work stops immediately and the responsible authorities are notified without delay.

The decision on findings is assigned to the specific foundation element and remains outstanding in the point register until its completion is documented.

Documentation for foundation designers and site management

Which documents clearly describe the depth volume investigated

A reliable project file links the point list, setting-out survey, survey and drilling data, findings and execution. The documented statement remains limited to the foundation recorded and its actual geometry.

Project and structure reference

The project address, structure, alignments, coordinate system and current plan revision form the common framework.

Construction sections and temporary foundation solutions are clearly distinguished.

Structure and pile designations are maintained so that component structures and foundation sections can also be clearly distinguished.

Pile and borehole point register

Each element receives an identifier, coordinates, diameter, target depth, inclination and installation method.

Removed, relocated or additional points are updated traceably.

Design and actual data are documented separately because setting-out or borehole starting points may differ from the design.

Basis for suspicion and existing conditions

Historical assessment, known finds, utilities, existing foundations and earlier investigations are documented with their scope.

Unresolved data gaps remain visible as a planning risk.

The origin of utility and existing-condition data is recorded so that its positional accuracy can be assessed by a specialist.

Borehole and survey data

Drilling depth, casing, survey paths, equipment configuration, sources of interference and quality checks are recorded for each point.

Raw data and evaluation revisions remain relatable to each other.

The borehole log and survey file are assigned to the same point identifier and checked together for completeness.

Findings and status overview

Anomalies, areas that cannot be surveyed, exposure work and further measures are recorded with their point identifier and spatial reference.

Site management can identify which foundations have been investigated and which remain outstanding.

Anomalous, inaccessible and technically disturbed points receive different status markers and measures.

Final and handover documentation

The report states the investigation depth, result, limitations and follow-up decision for each element.

It is updated specifically when the geometry changes, rather than applied indiscriminately to new points.

Before pile installation, the latest valid status is checked against the current execution plan and documented.

Deep-foundation documentation dossier

Keep the pile list and investigation results at the same revision

For large pile fields or several construction sections, the investigation status must always be clear. The data structure links the foundation element, survey point, result and subsequent execution.

01

Foundation dataset

Pile plans, lists, borehole starting points, depths and installation methods are stored with their plan revision and origin.

Different specialist designs are assigned a common point identifier.

In addition to design parameters, the foundation data register includes the planned installation date and assignment to the respective construction section.

02

Survey reference

Design and actual coordinates and elevations are documented before and after fieldwork.

Deviations between setting-out and design remain traceable.

Survey data includes a height reference because excavation or filling may alter the actual investigation depth.

03

Drilling and survey records

Borehole construction, casing, survey paths, interference and checks are recorded for each foundation element.

This allows the technical statement to be reviewed by a specialist later.

Drilling and survey records also document depths not reached, obstructions and replacement boreholes required subsequently.

04

Anomaly and action list

Anomalous signals, known interfering objects and further investigation steps receive a clear status.

Outstanding points are not mixed with surveys showing no significant anomalies.

The measures list distinguishes anomalous signals, technically disturbed surveys and points still awaiting investigation for organisational reasons.

05

Execution check

Before piling or drilling begins, the element, depth and method are checked against the documented revision.

Changes trigger a clearly assigned decision on supplementary investigation.

The execution check takes place immediately before each foundation package, rather than only once at the start of the project.

06

Project completion

Reports, point lists, site plans and handovers are combined in a consistent schedule of attachments. Where exposure or clearance work has actually taken place, the corresponding findings and clearance records are added.

The stage of investigation achieved remains traceable after the structure has been built.

The final documents show which points were actually installed, omitted or replaced by another foundation solution.

Structural foundation project workflow

Schedule investigation and handover of results before pile installation

The process is adapted to foundation design, ground investigation and installation dates. Investigation, evaluation and handover of results are scheduled before each foundation package.

Before execution begins, point status is checked against the latest approved foundation plan. This identifies last-minute changes and additional piles, and their supplementary investigation requirements are assessed.

For time-critical foundation works, point investigation may be organised by priority and installation package. The technical investigation standard remains unchanged for every point; only the sequence and data handover are adapted to the construction sequence. Test piles, crane positions and early component structures can be brought forward specifically. Main execution receives the current point list with investigation results and outstanding measures. Changes are recorded in the current execution plan with their dates and affected points.

01

Record the foundation task

The structure, pile or drilling system, number of points, depths, inclinations, dates and required statement are clearly described.

02

Assess records and suspected hazards

Historical assessment, pile plan, utilities, ground data and existing documentation are checked for spatial consistency.

03

Define the point location and depth volume

Coordinates, cross-sections, installation path and safety envelope are defined for each foundation element.

04

Plan the survey and drilling concept

The survey method and actual survey coverage are derived from geometry and interference conditions. Where borehole surveying is required, the borehole arrangement, casing, survey paths and possible alternative measures are planned.

05

Prepare fieldwork

Setting-out, access, equipment positions, utilities, occupational safety and construction time windows are agreed on site.

06

Carry out depth investigation

The selected investigations are carried out with clear point identifiers; deviations, depths not reached and interference are documented immediately.

07

Assess data and findings

Signals, drilling conditions, known installations and neighbouring points are checked for plausibility in relation to the foundation objective.

08

Hand over point status before installation

The report, point status, limitations and further measures are handed over to the planners and site management before actual installation.

Technical point and depth geometry

What information is required for reliable investigation of structural foundations

The ground to be investigated corresponds to the entire installation path of the foundation element. The point coordinate and final depth describe only part of this geometry.

Coordinate the survey arrangement with the actual pile volume

For vertical piles, the alignment, diameter, target depth and any predrilling are considered as a continuous depth volume. For borehole surveying, the survey arrangement must cover the pile cross-section and relevant safety envelope. A single survey line may be insufficient for large diameters or pile groups.

Inclined piles, micropiles and anchors move away from the visible starting point as depth increases. Their spatial path is derived from inclination, length and orientation. Property boundaries, neighbouring foundations or utilities may constrain both the foundation and investigation boreholes.

Casing and borehole condition affect the survey. Material, diameter, depth and possible magnetic or mechanical interference are documented. Survey paths must reach the planned investigation depth and be free of interruptions that have not been assessed.

For pile fields, point lists are divided into sections while retaining a common data structure. Each element has a clear status: planned, set out, drilled, surveyed, anomalous, supplemented or completed for the documented geometry.

For foundations at differing depths, it is also checked whether different pile types or load-transfer zones overlap spatially. Investigation geometry follows the actual ground volume, rather than only its plan-view representation.

01

Coordinate and height reference

The starting point, ground or working elevation and structure coordinate are clearly defined.

Elevation changes caused by excavation or filling are incorporated into the investigation depth.

For pile groups, overlaps and possible gaps between individual investigation volumes are checked geometrically.

02

Cross-section and safety envelope

Pile diameter, tool width and the required margin determine the lateral extent.

The survey geometry relates to the entire ground volume occupied.

The lateral extent also takes account of tool changes, enlargements and possible inclination of the drill string.

03

Target depth and borehole reach

Survey and drilling depth must cover the subsequent embedment length and relevant ground volume of the works.

Boreholes ending prematurely remain clearly identified as a limitation.

The height reference is checked after the working platform has been constructed so that investigation depth and pile-head elevation correspond correctly.

04

Inclination and spatial course

Inclined elements are treated as a three-dimensional corridor.

Orientation and length must match in the site plan and survey concept.

Inclined elements receive a clear orientation in the coordinate system and a traceable spatial endpoint.

05

Interference conditions and existing foundations

Reinforcement, utilities, old piles and steel components are recorded as possible survey and drilling obstructions.

Supplementary measures are planned before execution.

Deployment planning considers existing foundations as possible drilling obstructions as well as sources of interference.

06

Plan revision and point changes

Every relocation, increase in depth or change of method is checked against the existing documentation.

The new status is updated in the point list and project file.

A plan revision contains a traceable list of the points affected and the resulting specialist measures.

For foundation elements with varying depths or diameters, a point list organised by group is useful. This allows the survey concept, effort and execution status to be planned traceably for each element type.

Select an investigation

Select investigations by foundation element and depth volume

Two people discussing plans at a table beside a vehicle on a construction site.

Compare documents relating to suspected ordnance with the current pile field

The historical basis and earlier investigations are assigned to the planned foundation points. Additional piles, lateral working areas or a relocated structure alignment may affect volumes not previously considered.

Assign existing documentation to the current pile field
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Base method selection on spatial geometry

Diameter, inclination, embedment depth and installation method are considered together. The decisive question is whether the intended investigation can adequately cover this volume under the existing ground and interference conditions. Remaining limitations are clarified before installation.

Assess depth-related investigation
Services for structural foundations

Suitable methods for the pile field and foundation points

Technical investigation of deep foundations may combine several methods. The decisive factors are which physical property and which area or depth volume are investigated by each method.

01

Historical aerial photograph analysis

Establishes the basis for historical suspicion at the structure’s location and supports prioritisation of technical investigation.

It does not demonstrate objects in the individual pile or borehole volume.

It primarily supports spatial assessment, rather than point-specific release at depth.

02

Magnetometric area assessment

Detects ferromagnetic anomalies in accessible near-surface areas.

Existing reinforcement, utilities and structures may limit the survey.

Its coverage ends where the deep foundation volume is not reliably investigated.

03

TDEM

Can provide supplementary assessment of electromagnetic responses from conductive objects in suitable areas.

Depth, the target object and technical surroundings determine the extent of the statement.

The method is used only if it provides additional insight for the defined target object.

04

Ground-penetrating radar / GPR

Shows reflections at material and structural boundaries and may provide information about the ground or existing structures.

It does not identify explosive ordnance from a radar image alone.

The data may support planning but does not replace a clear assessment of the pile corridor.

05

Deep-ground and downhole surveys

Investigates defined point locations and depth volumes for piles, boreholes and inclined elements.

It may be required where suitable surface methods cannot sufficiently cover the ground volume of the subsequent foundation.

Borehole quality, survey path and point spacing directly determine the usability of the result.

06

Excavation supervision

In a technically suitable explosive ordnance survey alongside construction, each working layer is surveyed using technical equipment and assessed. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base. Simply watching excavation is insufficient.

It does not replace depth investigation of the subsequent pile or borehole corridor.

Excavation layers, hold points, authority to issue instructions, communication routes and documentation are defined in the work instructions before work begins. The service remains limited to the layers actually investigated.

Working methods for foundation projects

Compare the pile list and survey data before execution

Designers, surveyors and the field team use the same point identifiers. Before pile installation, the execution plan, survey results and outstanding tasks are reconciled.

Every foundation point receives a traceable investigation status

FONTANA-EOD first assesses the suspected hazard, foundation plan and required statement. This establishes which points can be prepared using an area survey and which require their own depth investigation.

Before fieldwork, coordinates, target depths, diameters, inclinations and installation methods are checked. Conflicting lists or missing plan revisions are clarified before drilling or surveying begins.

Survey and drilling data remain linked to the execution design through a clear point identifier. Interference, boreholes ended prematurely and depths not reached are documented. The suitability of supplementary investigation for the planned intervention is assessed by a specialist.

The conclusion describes the point location and depth volume actually investigated. It provides a clear basis for site management and specialist foundation works without including additional or changed foundation elements.

For large pile fields, investigation is divided into packages that make technical and scheduling sense. The common point and data standard remains unchanged, so that partial reports can be combined and later replacement or additional piles can be reliably assessed against the existing investigation status.

Clear point list

Coordinates, depth, diameter and installation method are agreed before work begins.

Surveyable geometry

The selected survey geometry must sufficiently cover the ground volume of the subsequent foundation. For borehole surveying, the arrangement and survey paths are defined accordingly.

Controlled borehole quality

Casing, depth, interference and survey conditions are documented.

Plausible evaluation

Survey signals are assessed against drilling data, existing structures and neighbouring points.

Further investigate outstanding points

Areas not reached or showing anomalies receive a clear next step.

Hand over results for each pile

The planners and site management can identify which foundations have been investigated for the documented revision.

Prepare the next construction section

Maintain the point list from design through execution

Clarify access and working elevations before surveying

The working platform, point setting-out and accessible borehole starting positions must suit the intended investigation sequence. If the working elevation changes through excavation or filling, depth information is checked again before the next intervention.

Hand over the results revision for each foundation element

The point identifier, coordinates, height reference and documented investigation scope are handed over together for execution. A point with an outstanding depth interval remains clearly identified as such. Results are not transferred to other piles solely because they are nearby.

Roles in the foundation project

Who maintains the pile list, surveys and reports changes

The developer, structural designers, geotechnical specialists, surveyors, specialist foundation contractor and explosive ordnance specialist company must work with the same point and depth data. Changes require a clear communication route.

Client

Developer or project promoter

Defines the structure, dates, contractual structure and required documentation.

Provides existing documents relating to suspected ordnance and existing conditions, and coordinates specialist appointments.

Design

Structural and foundation design

Defines the foundation system, point list, cross-sections, depths, inclinations and installation methods.

Plan changes are communicated to everyone involved before groundworks.

Geotechnics

Ground investigation and geotechnical consultancies

Describe the ground structure, groundwater, drillability and geotechnical constraints.

Ground investigation works and explosive ordnance investigation are coordinated spatially and in time.

Surveying

Setting-out and point management

Transfers design coordinates to the construction site and documents actual positions.

Duplicate identifiers, deviations from plans and elevation changes are clarified before execution.

Specialist contractor

FONTANA-EOD

Plans and carries out the commissioned explosive ordnance investigation and documents point status, results and limitations.

The service remains related to the agreed foundation geometry.

Public authorities

KBD, KMBD, KRD and local authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and, where applicable, building control authority are involved in their project-specific roles. Conditions and contacts are assigned to the actual foundation sections. If ordnance is found, the responsible authorities determine the next steps.

Structural foundation project documents

Which work and documentation items are used in depth investigation

The foundation plan, point register, drilling and survey data and final report form a continuous documentation chain. This allows it to be checked whether actual pile installation falls within the documented investigation volume.

Four people in orange high-visibility vests in front of two excavators on a construction site.
Person with a yellow survey cart on a footpath in front of a hedge.
Identify the project location

Clearly assign the structure’s location and foundation points

Illustrated map of Germany with location markers on a construction site.

Identify the site and applicable requirements

State the project location, structure designation, current plan revision and point identifiers. Include the plan view, foundation data and relevant sections with a common height reference. Existing requirements and reports are assigned to the points and construction sections concerned.

Use results correctly

Check investigation depth and installation geometry together

Use the same reference for depth information

A survey value measured from ground level can be compared with a foundation depth only if the reference elevations are clear. Changes to the working platform or pile-head elevation must therefore remain traceable in the documents.

Check evidence against the intervention

Reassess changed pile types

A different diameter, greater length or new inclination may change the ground volume occupied. Existing documentation is compared with the new geometry; necessary supplementary investigations are assigned to the respective point before installation.

Explore the technical principles

Technical information

Roadworks and civil engineering: brochure

How can carriageways, bridges and deep excavations be investigated for ordnance? The brochure explains preparation, suitable survey methods and supervision of earthworks.

1 / 8
Roadworks and civil engineering: brochure – page 1

German · 8 pages

Questions about structural foundations

Frequently asked questions about explosive ordnance investigation before deep foundation work

When must a structural foundation be investigated for explosive ordnance?

Before drilling, driving, vibrating, pressing or other foundation work, the available findings and planned groundworks are used to establish what explosive ordnance investigation is required. The foundation type, point location, depth, installation method, basis for suspicion and the ground volume actually occupied by the drilling rig, pile or auxiliary works are decisive.

Which foundation types require a deep point investigation?

Bored piles, driven piles, micropiles, grouted piles, well and caisson foundations and deep isolated foundations may require their own point and depth geometry. Sheet-pile connections, anchors and auxiliary boreholes are also considered where they enter soil layers that have not previously been investigated.

What should you do if a suspicious object is found?

If an unexpected suspicious object is found, stop work. Do not touch, move or uncover it further. Leave the immediate area and warn others without putting yourself at risk. In Germany, notify the police on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine what happens next; a project enquiry does not replace reporting the find.

What documents are needed to plan the deep-ground survey?

A foundation plan, pile or borehole point list, coordinates, target depths, diameters, inclinations, installation methods, casing, construction phases, ground and utility data, and existing aerial photograph assessments or survey reports are required. The plan revision and execution stage must be clearly identified.

Information and requirements from authorities are supplied with their date, complete appendices and geographical scope. In Germany, the competent ordnance disposal service, local public-order authority and, where relevant, building-control authority are identified for the project location; outside Germany, local responsibilities apply.

How are raking piles, anchors or inclined boreholes taken into account?

The investigation area is not considered only at the starting point. Inclination, length, diameter and spatial course determine the ground actually occupied. Survey or borehole geometry is arranged to reflect the subsequent working corridor, including relevant safety zones.

What happens where metallic interference or existing foundations are present?

Reinforcement, utilities, sheet piles, existing piles and steel components may obscure magnetic or electromagnetic surveys. Known installations are recorded spatially before evaluation. Areas not sufficiently investigated are shown on the plan. Suitable supplementary methods and possible access after demolition or exposure are established for these areas.

What information belongs in foundation documentation?

The documentation includes the point and component identifiers, coordinates, target and investigation depths, survey or borehole geometry, method used, sources of interference, findings, limitations and follow-up decision. It must clearly show which foundation points and depths have been investigated for the planned execution.

What determines the effort, duration and costs?

Decisive factors are the number and depth of points, grid or alignment geometry, foundation method, drillability, casing, groundwater, access, utilities and existing structures, available work windows, setting out, data checking and documentation scope. Reliable quotations therefore require an up-to-date foundation design.

Enquire about the foundation project

We need these documents for your foundation investigation

A well-prepared enquiry links the structure’s location, foundation system and current execution geometry. This allows investigation boreholes, survey paths and documentation to be costed reliably.

Ground investigation drilling and explosive ordnance investigation drilling should be clearly distinguished in the schedule. Even where work sequences can be combined, the survey objective, responsibility and required documentation remain technically distinct.

The planned working platform also belongs in the enquiry. Its elevation and location affect the borehole starting point, investigation depth, equipment position and subsequent comparison of design and actual coordinates. Changes to the platform are taken into account by a specialist before foundation work begins.

Structure and foundation system

Provide the project address, site plan, structure alignments, foundation type, pile or borehole point list and current plan revision.

Where there are several options, identify which solution is to be investigated as the agreed basis.

Points, depths and installation methods

Coordinates, diameters, target depths, inclinations, installation methods, casing and any auxiliary boreholes are required.

Subsequent or temporary foundation elements are also considered.

Existing structures, ground conditions and dates

Include utility plans, existing foundations, ground data, groundwater information, historical assessment, earlier surveys and construction dates.

Access and available equipment standing areas affect practical execution.

For initial specialist assessment

A site plan, pile list, foundation method, maximum depth, number of points, construction period and existing indications of suspected ordnance are often sufficient for an initial review. FONTANA-EOD then identifies missing documents and suitable investigations for the foundation points.

For large pile fields, investigation can be organised by foundation section and installation date. Point identifiers and the data structure remain consistent across the entire structure.

Also state whether foundation boreholes are to serve as ground investigation boreholes at the same time or whether separate explosive ordnance survey boreholes are planned. This distinction affects bore diameter, casing, sequence and responsibility.

For time-critical pile fields, a priority list helps to investigate first the points needed for load testing, crane positions or the start of specialist foundation works.

For pile groups, test piles and dynamic or static load tests, the planned sequence should be stated. This allows the required point status to be linked to actual installation and avoids unnecessary duplicate investigation.

Structure reference

Site plan, alignments, components and plan revision.

Point geometry

Coordinates, diameter, inclination and target depth.

Installation method

Drilling, driving, vibrating, pressing or grouting.

Documentation objective

Documentation for detailed design, site management and specialist foundation engineering.

Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.