Explosive ordnance surveys for wind farms and wind turbines

For a wind farm, we consider turbine sites, crane areas, access roads and cable routes together with the planned ground works. FONTANA-EOD plans suitable surveys according to the volume of ground affected, intervention depth and construction phase. Send site and infrastructure plans, ground investigation points and the construction sequence so that services and documentation can be defined before the drilling campaign, road construction and foundation works.

Divide the sites into assessment areas

Identify turbines, roads and cable alignments.

Assess deep interventions

Record foundations and borehole locations.

Hand over results

Document areas and sections.

Assess the energy project as a whole

Before ground investigation, foundations and cable construction

Clarify survey requirements before drilling and foundation construction

Before drilling and foundation construction, existing hazard indications and planned ground interventions are used to clarify which explosive ordnance surveys are required. This also includes ground improvement, crane areas, access roads, array cables and the grid connection. The actual work geometry at each turbine location is decisive, rather than the overall wind farm area alone.

Project references

Selected project examples

Divide turbine locations and infrastructure into assessment areas

Plan foundations, crane areas, roads and cables separately

A wind farm includes foundations, construction areas, roads and cable routes involving different ground intervention depths. These geometries have different requirements for preliminary assessment, surveying and documentation.

Each turbine location receives its own status, while access roads, array cables and the grid connection are recorded by chainage or section. This keeps design changes and construction progress traceable.

The construction sequence is essential to specialist planning: ground investigation, road and crane area construction, foundation excavation, array cabling and assembly have different lead times. Each section is prepared so that the next activity begins only within a documented volume of ground.

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Turbine foundations and excavations

Foundation excavation, ground improvement, piles, anchors and other foundation elements extend considerably below the subsequent ground surface.

Plan dimensions, excavation depth, foundation method and lateral working space determine the explosive ordnance assessment geometry.

A near-surface assessment of the site area does not automatically cover deep foundation volumes.

Assess the foundation and volume at depth
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Ground investigation boreholes and test areas

Geotechnical boreholes, cone penetration tests, dynamic core sampling and load tests often involve ground intervention before the final construction design.

Coordinates, target depth, borehole diameter, equipment position and safety space are described as a separate assessment task.

Individual preliminary investigation points must not be used to infer a blanket assessment of the subsequent foundation.

Prepare ground investigation and test points
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Crane standing and assembly areas

Crane standing areas, auxiliary crane areas, assembly, rigging and storage areas require soil removal, load-bearing layers, compaction and drainage where applicable.

The actual work boundaries may extend beyond the permanent crane area and must match logistics planning and construction conditions.

Temporary areas are not automatically covered by documentation for the turbine foundation.

Record crane and assembly areas
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Heavy-load access roads and bend areas

Access roads connect public roads to turbine locations and are upgraded for heavy transport, cranes and later maintenance.

Widening, bend radii, passing places, slopes, culverts and ground improvement create additional volumes of ground affected.

The section documentation follows the alignment actually built, not just an early road option.

Assess access roads and construction sections
Person in high-visibility clothing beside a utility trench, with solar panels and wind turbines in the background.

Array cabling and crossings

Internal medium-voltage cables, control lines, earthing and communication links run between turbines, the transfer station and the grid connection.

Trench width, excavation depth, joint bay areas, crossings and launch or reception pits are recorded as separate route sections.

For deep or trenchless crossings, we separately assess whether surveying the open cable trench is sufficient and which supplementary method may be needed.

Assess array cables and crossings
Person in high-visibility clothing beside a utility trench, with solar panels and wind turbines in the background.

Substation and grid connection

The transfer station, substation, switchgear building, storage installation or external cable route often forms a separate subproject with its own design and operator structure.

Foundations, cable basements, earthing systems, excavations and access roads are not conflated with turbine locations.

The handover between the wind farm and grid connection receives clear location, schedule and documentation references.

Coordinate the grid connection and substation
Development, approval and construction

Schedule surveys before the drilling campaign, civil engineering and installation

Wind farm planning changes through site optimisation, turbine selection, ground assessment and approval. The status of explosive ordnance work is therefore clearly updated for each design revision.

Seasonal restrictions, vegetation, forestry and nature conservation requirements and heavy-load logistics also apply. These constraints affect access and scheduling but must not lead to method limitations or outstanding areas being disregarded during construction.

Site areas and location selection

Before final locations are selected, historical indications, previous uses, known finds and existing authority documents are related to the wind farm site.

Options for turbine locations, access roads and cable alignments can be compared by additional assessment requirements and technical accessibility.

The early assessment supports planning and clarifies further survey requirements. It does not replace a necessary technical survey of the subsequent ground intervention.

Assess the wind farm site using historical evidence

Approval and detailed design

Turbine coordinates, the foundation concept, crane standing areas, access roads, array cables and the substation are translated into specific work geometries.

Design changes between approval and construction receive traceable revision identifiers.

The explosive ordnance status is maintained for each turbine location and route section.

Assess the wind farm layout

Preliminary geotechnical investigation

Ground investigation boreholes and probing often begin long before foundation construction itself.

The point list is assessed with coordinates, depth, equipment use and timing sequence.

Additional or relocated borehole locations are not assumed to be covered by the original commission without assessment.

Have geotechnical points assessed

Tendering and construction procurement

Quantities, locations, methods, enabling works, work areas, data formats and acceptance criteria are clearly described for civil engineering, cable construction and special services.

Provisional items receive a specific trigger such as an interference zone, design change or lack of access.

This facilitates technically sound comparison of tenders.

Define procurement and service boundaries

Construction phase and heavy-load logistics

Access road construction, crane areas, foundations, cable civil engineering and turbine installation follow different programme and logistics chains.

Before each activity begins, the following trade receives survey results and information on outstanding areas.

Weather, ground conditions and restricted vehicle access may change the deployment sequence.

Hand over results to subsequent trades

Repowering and dismantling

Repowering may involve new turbine locations, larger foundations, changed access roads and additional cable sections.

Existing turbines, foundations and utilities affect survey feasibility and construction conditions.

Earlier reports are checked against the new geometry and reused only within their documented scope.

Reassess the repowering geometry
Suspected hazards, ground intervention and documentation

Record surveys and outstanding areas for each turbine location

Historical indications, technical survey feasibility and construction geometry are considered separately for each turbine location and infrastructure section. Results show which areas have been surveyed and what still needs clarification before the next ground intervention.

The timing sequence may also differ between turbine locations. Access road construction may already be underway at one turbine while historical assessment or ground investigation is still taking place at another. Work status is therefore shown by phase as well as by area.

Suspected hazard area within the planned wind farm

Historical sources or authority information indicate possible explosive ordnance contamination within the wind farm site.

The indications are related to turbine locations, access roads, cable corridors and ancillary installations.

It is then defined which areas require technical surveys or design changes.

Relate suspected hazard areas to turbine locations

Open turbine and crane area

Open, accessible areas may permit systematic near-surface surveys.

Terrain, vegetation, soil moisture, target object and required depth determine the grid and method.

The survey area is overlaid with the foundation, crane and assembly areas.

Assess the survey method for the turbine site

Woodland, vegetation or difficult terrain

Dense vegetation, root zones, slopes, ditches or restricted vehicle access can prevent complete surveys.

Site preparation, equipment selection and setting out are coordinated with nature conservation, forestry and construction programme requirements. Necessary surveys and protective measures are planned before ground intervention during vegetation clearance, dismantling or creation of access; survey access available later receives its own assessment date.

Areas not reached remain spatially marked and are assigned a later assessment step.

Select surveys according to terrain and access

Deep foundation or borehole locations

For ground investigation boreholes, piles, anchors and other deep elements, we check whether existing surveys are sufficient and what supplementary work is needed.

The relevant volume follows the coordinates, target depth, diameter and subsequent construction method.

An area-wide preliminary surface survey does not automatically address this task.

Assess deep intervention points and foundations

Installation area affected by metal interference

Existing installations, scrap metal, utilities, foundations or former technical uses can obscure survey data.

Known sources of interference are documented; the method is matched to the remaining scope for assessment.

Zones where data cannot be evaluated are not treated as showing no explosive ordnance indications.

Determine suitable methods for technical interference zones

An anomaly or an actual find

Survey anomalies are assessed for plausibility against turbine location plans, known installations and historical evidence.

Survey anomalies receive a specialist follow-up investigation or exposure. Recovery of confirmed explosive ordnance is coordinated with the permitted scope of activities and local responsibilities. If an unexpected suspicious object is found, work stops immediately and the competent authorities are notified without delay.

Location, findings, handover and outstanding areas remain clearly assigned to the turbine or route section.

Clarify findings and follow-up measures
Site-specific project records

Documents clearly describing turbines, access roads and cable routes

The documentation must bring together the turbine location, infrastructure and construction phase. Documentation for the turbine foundation does not automatically apply to the crane area, access road or array cables.

For large wind farms, the documentation is also structured so that individual turbine records and the overall project overview are consistent. A turbine's detailed records contain points, areas and findings; the overall overview shows work status for all turbines and linear connections.

This keeps the transition from preliminary geotechnical investigation to foundation, road and cable construction technically clear and traceable.

Wind farm polygon and turbine identifiers

The wind farm area, land parcels, turbine numbers, turbine coordinates and design revisions are maintained within a consistent spatial reference.

Each location change receives its own revision and status check.

Extension or repowering areas not considered remain identifiable.

Historical site evidence

Aerial photographs, maps, previous uses, known finds and authority information are documented with their source and scope.

Data gaps remain visible for each turbine location and route section.

The historical assessment is not indiscriminately extended to the entire cadastral district.

Drilling, foundation and survey points

Geotechnical boreholes, foundation points, deep-ground surveys and survey areas receive unique identifiers.

Coordinates, target depth, diameter and work status remain linked.

Additional points are recorded as new geometry.

Road, crane and route sections

Access roads, bend areas, crane areas, assembly zones and array cables are documented by chainage or polygon.

Working widths and alignments actually built are distinguished from the early design revision.

Handovers between civil engineering, cable construction and installation remain traceable.

Limitations and status of measures

Vegetation, terrain, sources of interference, utilities, weather and lack of access are described by section.

Each limitation is assigned a technical follow-up measure and project status.

Outstanding areas can thereby be incorporated into the construction programme and variations.

Site report and construction handover

Maps, point lists, field records and conclusions are brought together for each turbine and infrastructure section.

The handover identifies areas addressed, method limitations and steps still required.

A later change in turbine or layout is assessed separately.

Data across turbine locations and construction phases

Keep turbine points, areas and linear infrastructure linked

The project records contain point lists for boreholes and foundations, together with plans for construction areas and cable and road sections. All documents use the same turbine location identifiers.

For subsequent operations and repowering, it remains clear which areas were originally assessed and which served only as temporary construction or logistics areas. Maintenance modifications, cable repairs or location changes can thus be checked specifically against the existing data.

Location and layout register

Approved coordinates, optimised turbine locations, repowering options and construction drawings are maintained under revision control.

This keeps the basis of each assessment unambiguous.

Borehole and foundation-point schedule

Ground investigation points, deep-ground surveys and foundation elements receive coordinates, target depths and status.

If points are relocated, we check whether the new location and depth remain within the documented survey area.

Area and route register

Crane areas, assembly areas, access roads, cable routes and ancillary installations are documented with section identifiers.

Handovers retain the same location references.

Anomaly and findings register

Anomalies, technical sources of interference, exposures and actual finds are categorised separately.

Each entry receives a follow-up decision.

Construction phase and field records

Working conditions, areas actually addressed, interruptions and construction stages are recorded continuously. After actual exposure or clearance work, the corresponding findings and clearance records are included.

The records support HSE and site management.

Final and handover package

Reports, maps, lists and outstanding measures are handed over for each turbine location and subproject.

Later additions remain distinguishable from the original status of work.

From site planning to construction handover

Coordinate surveys and handover of results with construction phases

The assessment follows not just the approved design but the actual sequence of ground investigation, road construction, foundations, array cables and grid connection.

Early drilling campaigns may take place before final turbine location optimisation. Subsequent civil engineering and foundation services are therefore not automatically inferred from these preliminary surveys; they are checked again against the applicable turbine and infrastructure plans.

01

Clarify the wind farm site and project phase

The site areas, number of turbines, design revision, construction concept and required decision are described.

02

Assess historical evidence

Aerial photographs, maps, historical records, previous uses and regional information are reviewed by turbine location.

03

Divide turbines and infrastructure into assessment areas

Foundations, borehole locations, crane areas, access roads, array cables and the grid connection are recorded as separate volumes of ground affected.

04

Define methods and sequence

Depth, ground conditions, vegetation, interference sources, access and construction schedules determine the technical approach.

05

Prepare access and fieldwork

Setting out, site preparation, vehicle access, HSE, weather windows and data handover are coordinated.

06

Carry out surveying and monitoring

Points, areas and linear sections are addressed according to the agreed geometry and construction phase.

07

Assess results and findings

Survey data, limitations and exposures are assessed for plausibility against turbine identifiers and the infrastructure plan.

08

Hand over turbine location status

Reports and outstanding measures are updated for designers, civil engineering, cable construction and installation.

Points, areas and lines

Define foundations, crane areas and access roads on the turbine site plan

A turbine location is not a single point. The foundation, geotechnical investigation points, crane area, assembly areas, access road and cable connection together form a multipart volume of ground affected.

The logistical use of an area also affects the assessment. Crane assembly, blade storage, tower section storage, auxiliary cranes and heavy transport sometimes use areas that will not remain visible in the permanent installation layout. These temporary zones are nevertheless clearly recorded during construction.

Derive the site assessment from ground investigation, logistics and cable design

The foundation is described by its centre point, footprint, excavation depth, possible ground improvement and specific foundation method. Geotechnical boreholes and probing are often outside the final foundation layout or carried out early; they therefore receive their own point identifiers and depths.

Crane standing, assembly, rigging and storage areas are defined according to soil removal, load-bearing layers, drainage and actual equipment positions. Access roads are recorded with their alignment, widened and bend areas, slopes, culverts and temporary extensions. Array cables, joint bays and crossings form a separate linear corridor.

The status of work remains linked to the turbine identifier and current plan. If a turbine location moves, the foundation concept changes or an access road is modified, the new volume of ground must be checked against the existing assessment. Earlier results and later additions remain identifiable with their respective design revisions.

Foundation and foundation volume

The footprint, depth, excavation, ground improvement and foundation elements determine the assessment area.

An area survey covers deep elements only where it actually covers their required location and depth.

Ground investigation and test points

Coordinates, target depth, drilling method and safety space are defined for each investigation point.

Changes to point lists are assessed before construction.

Crane and assembly areas

Permanent and temporary areas are defined by soil removal, load-bearing layers, drainage and equipment positions.

Lateral working spaces remain part of the geometry.

Access roads and heavy-load corridor

The alignment, widened sections, bends, passing places, slopes and culverts are recorded by chainage.

Design and as-built routes remain distinguishable.

Array cables and crossings

Trenches, joint bay areas, crossings, launch and reception pits and transfer points receive their own sections.

Deep bore paths require separate consideration.

Turbine status and updates

The turbine location, infrastructure, outstanding points and handover status are updated together.

Only documented areas are handed over to subsequent trades.

Select an investigation

Assess preliminary surveys and survey conditions for each location

Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Consider geotechnical points in good time

Preliminary geotechnical investigations can already involve deep ground intervention. Survey requirements for these points are therefore clarified before drilling begins. For later construction, the foundation, crane and assembly areas, access road, cable route and grid connection are recorded as connected areas that nevertheless require separate assessments.

Clarify depth-specific assessment before geotechnical drilling
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Assess ground conditions, vegetation and technical installations

Agricultural or forestry land may offer broad access, while former military, industrial, extraction or transport sites may have highly variable survey conditions. Vegetation, terrain, utilities, scrap metal, foundations and technical installations affect methodology and the achievable assessment.

Select suitable surveys for the survey conditions
Methods according to the site task

Which specialist service addresses which volume of ground within the wind farm

Historical assessment, area surveys, deep point-specific assessment and measures during construction fulfil different tasks. Their combination depends on the location, construction phase and desired assessment.

01

Historical aerial photograph analysis

Defines suspected hazard areas and data gaps for turbine locations and infrastructure.

It does not detect objects currently in the ground.

The result supports site and survey planning.

02

Magnetometry

Detects ferromagnetic anomalies in accessible areas and road sections.

Scrap metal, utilities, vehicles and installations can obscure surveys.

The grid and survey objective are defined for each location.

03

TDEM

TDEM detects time-dependent electromagnetic responses from conductive objects and can provide supplementary investigation of selected wind farm anomalies.

Ground conditions, depth and technical infrastructure influence the conclusions.

A point-specific foundation remains a separate geometry.

04

Ground-penetrating radar / GPR

Can show material and structural boundaries where ground conditions are suitable.

Reflections do not automatically identify explosive ordnance.

Moisture, heterogeneity and ground contact determine data quality.

05

Deep-ground and downhole surveys

Assesses ground investigation boreholes, foundation points and other deep interventions within the defined point location and volume at depth.

Coordinates and target depths must match subsequent construction.

No area-wide assessment is established outside the assessment geometry.

06

Excavation supervision

Where explosive ordnance detection during construction is technically suitable, each working layer is surveyed and evaluated using technical methods. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base.

Excavation layers, equipment operation, hold points, authority to issue instructions, communication channels and documentation are defined in the work instructions before work begins. Simply observing the excavator is insufficient.

The assessment remains limited to the area supervised.

Responsibility by turbine location

Check site plans against survey results before construction

Before drilling equipment, a civil engineering crew or crane is deployed, it must be clear which areas and depths have been surveyed and where tasks remain outstanding.

Hand over results for each turbine and construction section

FONTANA-EOD checks the turbine layout against the planned ground interventions. Foundations, borehole locations, crane areas, access roads, cable routes and the grid connection are planned separately and documented together.

Methods are selected according to suspected hazards, target object, depth, ground conditions, vegetation, terrain and technical interference. Where a reliable assessment cannot be achieved, limitations and follow-up measures are identified before the next trade begins.

Fieldwork is coordinated with setting out, geotechnical design, civil engineering, logistics and HSE. Changes in weather or construction schedules do not change quality requirements but may affect the sequence of work.

The conclusion remains limited to the documented turbine and infrastructure status. Repowering, relocation or changed foundations trigger a traceable check.

For projects with several turbine types or changed hub heights, foundations, crane logistics and infrastructure may change. The technical assessment relates to the turbine configuration actually commissioned so that earlier assumptions are not carried into construction without assessment.

Define survey scope for each turbine location

The turbine, infrastructure section, depth and desired decision are clearly defined.

Check point lists against the plan

Boreholes, foundations and survey areas remain linked to the applicable design revision.

Justified methods

The survey method and supplementary work follow ground conditions, interference, construction stage and target object.

Hand over results for each construction phase

Civil engineering, cable construction and installation receive a clear work status.

Identify unresolved areas

Vegetation, terrain, sources of interference and inaccessible zones remain visible.

Check changes against earlier results

Design changes and repowering are checked against the original assessment.

Prepare the next construction section

Link field campaigns and handover of results within the wind farm

Run separate campaigns using a shared data basis

Where turbines are very far apart or several construction clusters are involved, fieldwork can be divided into separate campaigns. The overall project records nevertheless ensure that all locations use the same identifiers, coordinate systems and quality requirements.

Hand over the survey scope for each turbine and section

The documentation relates to turbine identifiers, land parcels, turbine coordinates, foundation and borehole locations, crane areas, access road sections and cable chainage. FONTANA-EOD coordinates survey scope, occupational safety and handover of results with the construction programme.

Responsibilities from development to construction

Who coordinates turbine locations, infrastructure and communication about finds

Project developers, landowners, approval and specialist designers, civil engineering contractors, turbine suppliers and responsible authorities need coordinated information and decision procedures.

Project promoters

Project developers and operators

Define the site areas, project phase, programme, procurement and documentation requirements.

They provide existing land, approval and hazard documents.

Land and access

Owners, tenants and forestry parties

Support access, site preparation, vegetation and land-use coordination and knowledge of previous site uses.

Land availability and technical assessment status remain separate matters.

Specialist planning

Wind farm, geotechnical, civil engineering and electrical design

Translate the project into turbine points, foundations, crane areas, roads, cables and the grid connection.

Design changes are handed over so that their effects on work status can be assessed.

Execution

Civil engineering, cable construction and turbine logistics

Implement access, construction areas, earthworks, hold points and handovers according to the applicable plan.

Additional areas, relocated points or changed methods are reported before construction.

Specialist contractor

FONTANA-EOD

Assesses suspected hazards and work geometries, carries out the commissioned service and documents the result and limitations.

FONTANA-EOD carries out the commissioned technical investigation and documents its result. If ordnance is found, the responsible authorities decide on further action.

Public authorities

KBD, KMBD, KRD and local authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and, where applicable, building control are involved according to their project responsibilities. Conditions and contacts are assigned to the actual turbine locations and infrastructure sections; reporting procedures are defined before work begins.

From turbine points to wind farm records

Documents used in practice within a wind farm

Plans, point lists and records show which areas were investigated and which tasks remain unresolved.

The documents also support coordination between project development, geotechnical design, civil engineering and turbine logistics. Site-specific maps and point lists show the turbine to which each survey applies.

For site handovers, maps and lists are structured so that civil engineering, cable construction and installation use the same turbine and section references. This reduces queries between trades working at different times and supports reliable updates through to project completion.

Two monitors displaying aerial photographs and maps; further aerial photograph printouts lie on the desk.

Historical assessment of turbine locations

The mapping identifies substantiated suspected hazard areas, data gaps and requirements for further site assessments for wind turbines.

Check the historical basis for the site
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Drilling and foundation documentation for each turbine

Deep assessments relate to the documented turbine coordinates, point location and volume at depth and the planned foundation method.

Survey foundation and borehole locations
Person with a tablet at the edge of a cordoned-off excavation, with an excavator behind.

Supervised foundation and cable excavation

The suitability of construction-phase ordnance surveying is assessed for each excavation layer. The documented investigation area limits the statement’s scope.

Supervise foundation and cable excavation
Two people discussing plans at a table beside a vehicle on a construction site.

Findings records for turbine locations and routes

Survey anomalies, technical sources of interference, finds and outstanding follow-up measures remain assigned to the affected turbine or cable chainage location within the wind farm.

Document findings and follow-up measures spatially
Two people discussing plans at a table beside a vehicle on a construction site.

Individual turbine records and overall overview

The design basis, fieldwork, limitations and next construction decision are brought together for each turbine and the overall wind farm records.

Document turbine location records and handover
Four people in orange high-visibility vests in front of two excavators on a construction site.
Person with a yellow survey cart on a footpath in front of a hedge.
Identify the project location

Clearly locate turbines and infrastructure sections

Illustrated map of Germany with location markers on a construction site.

Identify the site and applicable requirements

Wind farm projects often extend across several cadastral districts and are implemented in campaigns at different times. One turbine location may already have undergone geotechnical investigation while its access road or array cable route remains at the option stage. Work status is therefore recorded for each turbine location and infrastructure section so that a partial decision is not inadvertently applied to the entire project.

The project location, turbine identifier, land parcel and coordinates together identify the turbine site. Existing requirements are assigned to the relevant location or infrastructure section.

Use results correctly

Use site documentation for the next construction phase

Check foundations and crane areas separately

A result for the foundation area does not automatically cover adjacent crane or assembly areas. Compare the location, working width and depth of these areas with the documented survey scope before the next construction phase begins.

Check evidence against the intervention

Update design changes to roads and cables

Relocated access roads or changed array cables may affect areas not previously considered. Assign the change to its section and design revision and clarify additional survey requirements before construction.

Explore the technical principles

Technical information

Utility and energy projects: brochure

Utility routes, substations and energy installations place different demands on ordnance assessment. The brochure shows the design information needed and how investigation, construction sequence and documentation fit together.

1 / 8
Utility and energy projects: brochure – page 1

German · 8 pages

Common project questions

What should be clarified before ground investigation drilling, foundation construction and array cabling

When should a wind farm be assessed for explosive ordnance?

The assessment should begin as soon as the proposed site areas, turbine coordinates and infrastructure corridors are sufficiently described. Geotechnical boreholes may involve relevant deep ground interventions even before approval or detailed design. Before foundation construction, access roads, crane areas and array cabling, the respective volumes of ground affected must be technically defined.

Is an area-based survey sufficient for a turbine foundation?

Not automatically. A near-surface survey can assess part of the site area but covers deep piles, anchors, boreholes or other foundation elements only where the achievable assessment geometry matches the subsequent intervention. Deep points are therefore planned and documented separately.

What should you do if a suspicious object is found?

If an unexpected suspicious object is found, stop work. Do not touch, move or uncover it further. Leave the immediate area and warn others without putting yourself at risk. In Germany, notify the police on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine what happens next; a project enquiry does not replace reporting the find.

Which records are needed for planning?

Wind farm and site plans, turbine coordinates, foundation and excavation geometries, ground investigation point lists, crane and assembly areas, access roads, array cables, crossings, the substation, ground investigation and utility data, historical assessments, conditions, construction schedules and the desired handover date are required.

Information and requirements from authorities are supplied with their date, complete appendices and geographical scope. In Germany, the competent ordnance disposal service, local public-order authority and, where relevant, building-control authority are identified for the project location; outside Germany, local responsibilities apply.

How are woodland sites or sites with difficult access addressed?

Vegetation, root zones, slopes, ditches, soil moisture and restricted vehicle access are considered in the methodology. Areas not adequately surveyed are identified on the plan, and suitable supplementary measures and possible access after site preparation or dismantling are defined. Necessary surveys and protective measures are planned before ground intervention during vegetation clearance, dismantling or road construction. Where explosive ordnance surveying during construction is technically suitable, each working layer is technically surveyed and assessed before controlled removal with supplementary visual inspection; areas not covered remain outstanding.

What changes during repowering?

New turbine coordinates, larger foundations, changed crane areas, new access roads or additional cable routes may lie outside earlier assessment areas. Existing foundations and utilities also change survey conditions. Earlier documentation is therefore checked against the geometry, depth and construction conditions of the repowering project.

What roles do authorities and explosive ordnance clearance services have?

In Germany, state explosive ordnance disposal services and locally responsible authorities carry out hazard prevention and find-handling duties. Outside Germany, local responsibilities apply. FONTANA-EOD carries out the privately commissioned site assessment and documentation within the agreed scope. Reporting procedures and contacts are clarified for the affected locations and sections before work begins.

What determines the work involved and costs of wind farm assessment?

Factors include the number and location of turbines, depth and number of ground investigation and foundation points, crane area sizes, access road and array cable lengths, vegetation, terrain, sources of interference, accessibility, methods, construction phases and documentation scope. Reliable costing needs current site and infrastructure plans.

Documents for specialist assessment

Information required for turbine locations, construction areas and infrastructure

An initial enquiry can be based on early site proposals. Priority turbine points, planned ground investigation works, infrastructure corridors and the next decision deadline are essential.

The earlier drilling and foundation points are available, the more reliably the service scope can be defined. For infrastructure still subject to change, corridors and reserved areas are initially considered; construction-ready points and alignments subsequently receive precise assessment.

Planned alternative locations and reserve areas should also be marked so that their work status is not confused with that of the definitive turbine points.

Wind farm area and turbine locations

Send the site plan, land parcels, wind farm polygon, turbine coordinates, numbering and current design revision.

Mark options, relocated turbine positions and areas not yet accessible.

For repowering, old and new designs should be shown separately.

Boreholes, foundations and construction areas

Describe ground investigation points, target depths, foundation and excavation geometry, ground improvement, crane and assembly areas.

State access roads, bend areas, array cables, crossings and ancillary installations.

Deep intervention points and area-wide earthworks are identified separately.

Existing installations, conditions and programme

Include utility plans, ground investigation data, historical assessments, authority documents and known areas of interference.

Specify site preparation, the drilling campaign, road construction, foundation construction, cable construction and installation windows.

Provisional documents also show which baseline information is still missing.

For initial technical assessment

For an initial assessment, the wind farm polygon, turbine coordinates, planned ground investigation points, foundation concept, crane areas, access roads, array cables and existing hazard indications are often sufficient. FONTANA-EOD then identifies the required assessment scope and data.

For wind farm projects lasting several years, work can be phased according to the geotechnical campaign, approval status and construction priorities. This provides reliable assessments early for imminent turbine locations without prematurely fixing later layout options.

An overview of the planned contract and procurement structure is also helpful. This indicates whether site management and the operator need shared overall documentation, individual turbine location reports or a combination of both.

Site reference

Wind farm polygon, turbine identifier, coordinates, land parcel and current design revision.

Deep interventions

Ground investigation boreholes, foundation, piles, anchors, ground improvement and target depths.

Infrastructure

Crane and assembly areas, access roads, array cables, substation and grid connection.

Project organisation

Approval status, HSE, construction phases, logistics windows and required handover date.

Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.