Person in high-visibility clothing beside a utility trench, with solar panels and wind turbines in the background.

Explosive ordnance assessment for district heating pipelines and heat networks

Before district heating work, pipe trenches, chambers and building service connections are checked against existing explosive ordnance documents. FONTANA-EOD plans suitable investigations according to existing utilities, working width, depth and construction phase. Send route and coordination plans, cross-sections, special structures and traffic phases so that services and documentation can be defined before the respective ground interventions.

Organise sections

Record the road corridor, chambers and connections.

Coordinate depth

Assess pipe trenches and special structures.

Hand over results

Document investigated and unresolved areas.

Assess the heat network within utility construction

Before pipe trenches, chambers and building service connections

Clarify investigation needs before pipe trenches and building service connections

Before district heating construction, existing indications of a suspected hazard and planned ground interventions are used to clarify which explosive ordnance investigation is needed. Main pipelines, chambers, crossings, building service connections and temporary pipelines are considered. The required scope depends on the actual construction cross-section, trench depth, retaining structures, lateral working spaces and particular civil engineering points.

Divide the heat network into construction sections

Plan pipe trenches, chambers and building service connections separately

District heating construction combines linear pipe trenches with chambers, crossings, building entries, temporary changeovers and temporary traffic areas. Each area has a different depth and technical environment.

The investigation scope is linked to the utility plan ready for construction and the construction phases. An early route line alone is insufficient for technical planning.

Where commissioning takes place in sections, the work status must be maintained so that open excavations, completed sections and later connection areas remain clearly distinguished.

Network expansion, infill connections and renewal create different requirements. A new main route focuses on the corridor and construction sections; building service connections and tie-ins require assessment of small, localised excavations within a densely occupied existing utility environment.

Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Pipe trench within the road corridor

The standard trench is described with its axis, pipe bundle, base depth, slope or retaining structure, working space and arrangements for soil alongside it.

Traffic management, footways, tree locations and existing utilities can greatly restrict the usable working width.

The investigation geometry follows the actual trench cross-section and intended construction phase.

Assess the pipe trench and construction section
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Chambers and valve structures

Drain, air-release, isolation and metering chambers have larger footprints and often greater depths than the linear trench.

Retaining structures, dewatering, foundations and internal utilities are recorded as a separate structural geometry.

If plans change or further installations are added, it is assessed whether the documented area and depth are sufficient or supplementary investigations are needed.

Assess chamber and structure depths
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Building service connections and entries

Building entries connect the public road corridor, property, basement area and existing utilities.

Short route sections can be more strongly affected by foundations, reinforcement, old utilities and restricted access than the main pipeline.

The work status is limited to the connection trench, core area and, where applicable, deep drilling points.

Have the building service connection assessed by specialists
Person beside a survey instrument on a construction site; a wheeled excavator with drilling equipment stands behind them.

Road, railway and watercourse crossings

Open-cut crossings, pipe jacking, HDD or protective pipe systems create launch and reception pits and deep drilling paths.

The near-surface crossing area and deep corridor are planned separately.

Traffic and operator coordination are linked to the explosive ordnance investigation sequence.

Assess crossing geometry and depth
Two people discussing plans at a table beside a vehicle on a construction site.

Existing network, changeovers and repairs

Network infill connections, pipeline replacement, changeovers and fault repairs often affect ground excavated several times and dense utility corridors.

Earlier construction work does not automatically provide a conclusion for deeper or laterally different interventions.

Existing documentation is checked against the new plan version, excavation and working depth.

Check existing documents against the new intervention
Survey trolley on an undeveloped construction site, with soil piles and a row of trees in the background.

Site facilities and intermediate conditions

Pipe storage, welding areas, diversions, temporary pipelines, site cabins and material areas can create additional ground interventions or loads.

These areas are identified in construction phase planning and included in the investigation area where needed.

After a change in construction condition, it is documented which areas remain unresolved or will be affected again later.

Consider temporary working areas
Network planning, procurement and construction phase

Prepare investigations for network planning, procurement and construction sections

District heating projects range from early network options to construction in sections while urban activities continue. Investigation needs are refined as the route, depths and traffic phases are defined.

The developer, heat supplier, designers and civil engineering teams need the same assignment of construction section, pipeline geometry, suspected hazard and documentation status.

Traffic management, temporary utility routes, opening of surfaces in sections and short-notice design changes can alter the accessible investigation area. Before the next ground intervention, changes are checked against the documented work status.

Network concept and options

Historical data and known finds are related to possible routes, chamber locations and handover points.

Early assessment supports selection of options, scheduling and procurement of further documents.

The early assessment clarifies further investigation needs. Any necessary technical investigation relates to the construction axis defined later.

Assess heat network routes historically

Construction design and utility coordination

Flow and return pipes, working space, chambers, connections, crossings and construction phases are translated into specific investigation areas.

Existing utilities and coordination plans must be assessed for currency and positional accuracy.

Relocated axes or changed chamber positions are checked against the existing work status.

Coordinate the construction route with specialists

Ground and utility investigation

Utility trial excavations, ground investigation boreholes and surveys involve ground interventions before pipeline construction itself.

Point position, depth and working space are checked in advance against the suspected hazard and existing sources of interference.

The results are later assigned to the district heating project file.

Coordinate methods before trial excavations and drilling

Specification and construction phases

Sections, depths, methods, traffic phases, stopping points and the documentation to be provided are clearly described.

Unspecified combined items make comparison of tenders and subsequent site management more difficult.

Supplementary services receive clear triggers and spatial limits.

Structure procurement and construction phases

Earthworks within dense existing infrastructure

Utility bundles, foundations, scrap metal content and lack of access can limit advance surveys.

For remaining areas, the technical suitability of explosive ordnance detection during construction is assessed. Each working layer is technically surveyed and assessed before controlled removal in layers with supplementary visual inspection follows. These steps are repeated until the agreed excavation base is reached.

The area addressed remains limited to the construction condition actually supervised.

Prepare investigation work during construction

Suspected location or find within the construction section

Unusual findings are documented with position, depth, construction phase and possible technical cause.

If an unexpected suspicious object is found, work stops immediately and the competent authorities are notified without delay.

Resumption of work follows the instructions of the competent authorities.

Document findings and subsequent decisions
Suspected hazard, existing infrastructure and construction geometry

Record investigated and unresolved areas for each construction section

The historical suspected hazard, alterations from technical installations and actual civil engineering cross-section are recorded separately. Suitable investigations are then selected for the respective section.

An easily accessible carriageway may allow an area survey, while a chamber location, building service connection or utility bundle requires a different approach.

For the project decision, the standard trench, chamber structure, crossing, tie-in and building service connection are not grouped together. Each area receives conclusions suited to its geometry, depth and subsequent construction.

Section with a reliable historical evidence basis or unresolved historical questions

Aerial photographs, maps and existing project documents are related to the street, properties and planned structures.

Gaps in data remain identifiable with their own status.

The result determines the priority of technical investigation.

Define the suspected hazard within the road corridor

Accessible standard trench

An area-wide geophysical investigation may be useful on sufficiently clear areas.

Survey method and grid depend on the target object, surface, ground conditions, depth and utility environment.

Subzones that cannot be surveyed are tracked separately.

Select area survey methods for the pipe trench

Densely occupied utility corridor

Gas, water, electricity, telecommunications, sewers, foundations and old utilities can obscure signals.

Known installations from coordination plans and site records are incorporated into the assessment.

For areas without reliable conclusions, a supplementary method or later construction condition is planned.

Assess a section altered by technical installations

Deep chamber or crossing geometry

Chamber excavations, pipe jacking, HDD and deep building service connections may extend beyond the depth range covered by near-surface investigation.

Point, axis and volume geometries are described with design depth and retaining structures.

The conclusion remains limited to the documented volume of ground affected.

Assess the particular deep location

Excavation under changing construction conditions

Demolition, temporary utilities, retaining structures and traffic phases may make areas accessible only gradually.

Suitable investigation is planned for newly accessible areas. Necessary investigations and protective measures are planned before ground interventions during demolition, opening of surfaces or preparation of access. Whether explosive ordnance detection during construction is an option is assessed by specialists for the planned excavation.

Each partial handover identifies the work status reached.

Coordinate excavation and construction conditions

Documented subsection

The plan, survey data, structure status, unusual findings, limitations and outstanding measures are brought together in a section file.

Handover follows the actual construction phase, not just the procurement lot boundary.

Later connections or deeper interventions are checked against this file.

Document the subsection and handover
Project file from road corridor to connection

Which documents demonstrate the work status of the district heating route

Urban district heating projects need documentation that brings together the plan version, construction phase, existing utilities and explosive ordnance investigation status.

The report must also remain understandable to people not involved in survey work or excavation, such as procurement, traffic planning, network operations and later connection planning.

In urban projects, documentation must also work for handovers in sections. The site plan, depth reference, survey or supervision status and unresolved remaining areas are recorded so that site management and subsequent crews can identify the volume of ground for which reliable conclusions exist.

For building service connections, temporary diversions and later tie-ins, it is assessed whether documentation for the main pipeline section covers the actual area and depth. The additional excavation receives its own position, depth and decision on investigation work so that it can be clearly distinguished from already documented areas during execution.

Route and construction phase plan

The axis, flow and return pipes, pipe trench, chambers, connections, crossings and temporary areas are recorded using the same location reference.

Traffic and construction phases receive clear time and section references.

Plan revisions remain traceable.

Historical and official evidence

Aerial photographs, maps, earlier finds, existing correspondence and historical documents are recorded with their sources and scope.

Unresolved areas remain recorded as gaps in data.

The assessment relates to the current district heating section.

Survey and field records

Methods, survey lines, grids, ground conditions, surface, existing utilities, sources of interference and achievable data coverage at depth are recorded by section.

Drilling and deep investigation points receive coordinates, design depths and investigation depths.

Deviations from the planned scope are justified.

Anomaly and findings status

Unusual findings are recorded with position, depth reference, technical plausibility and further measure.

Exposure work, technical interfering objects and actual finds remain distinguishable.

The status is updated after each stage of work.

Unsurveyable and unresolved zones

Utility bundles, chambers, foundations, retaining structures and lack of access are identified spatially.

Suitable supplementary methods and later survey access are assessed for these zones. Explosive ordnance detection during construction is considered only where technically suitable.

They are not counted as part of the completed area.

Partial handover and final report

Reports, plans, status lists and outstanding measures are brought together for each construction phase and the overall project.

The handover describes the actual area and depth volume addressed.

New building service connections or network infill connections can later build on this in a targeted way.

Updatable data within the urban utility corridor

Keep utility plans and investigation results aligned

The project file contains historical evidence, utility plans, survey data, deep investigation points, findings and partial handovers.

Consistent identifiers help assign the road section, chamber, building service connection and traffic phase unambiguously within the documents.

Section and structure register

Streets, construction sites, chambers, crossings, connections and temporary areas receive unambiguous geometries.

This structure connects planning, fieldwork and site management.

Plan and utility register

The plan versions used, existing utility plans, coordination documents and their currency are documented.

Deviations between plans and local conditions remain identifiable.

Survey and point register

Survey lines, grids, drilling points, check areas and repeat surveys receive stable identifiers.

Raw data and evaluation can thus be assigned unambiguously.

Anomaly and measures list

Each point and unsurveyable zone receives a status, work record, result and next measure.

Project management and site management can thus identify outstanding prerequisites for each section.

Construction phase and handover notes

Subareas are handed over only with the associated plan version, depth addressed and limitations.

Traffic or network changeovers are kept separate from the technical conclusion.

Overall heat network project file

Section reports, maps, registers and conclusions are brought together in an updatable project file. Following actual exposure or clearance work, the corresponding findings and clearance records are included.

Later extensions can check and supplement the existing status in a targeted way.

From network planning to commissioning in sections

Include investigations and handover of results in the construction sequence

The specialist work is linked to network planning, utility coordination, traffic phases and civil engineering sections. Results needed are coordinated with the dates for procurement and ground interventions.

Early options, road sections ready for construction and later building service connections may involve different levels of investigation detail but remain linked in the same project file.

For construction in sections, investigation, pipeline construction, welding, testing, backfilling and reinstatement of surfaces are coordinated in time. For each section, it is recorded which area has already been addressed, which depths were reached and which remaining zones become accessible only in the next construction condition.

01

Define the project section and decision

The street, network function, construction phase, pipe cross-section, chambers, connections and assessment required are described.

Priority and later sections are planned separately.

02

Organise documents and existing utilities

Site plans, coordination documents, historical evidence, ground investigation data and traffic phases are brought together.

Contradictions or missing utility information are clarified before fieldwork.

03

Relate the suspected hazard to the construction corridor

Historical suspected areas are overlaid with the pipe trench, chambers and special crossings.

This defines investigation areas and gaps in data for each construction phase.

04

Plan methods and access

Methods are selected according to the required investigation depth, survey conditions and access.

Existing utilities, the surface and traffic influence the sequence.

05

Carry out survey work and deep-ground investigation

Fieldwork is carried out with the plan version, section identifier and structure reference.

Interference zones, inaccessible areas and deviations are documented immediately.

06

Assess data and unusual findings

Survey data and field observations are checked against existing utilities, the suspected hazard and planned depth.

Unresolved points receive a specific further measure.

07

Hand over the subsection to site management

The report, plan, status list and limitations are provided for the upcoming civil engineering section.

The handover remains related to the documented construction condition.

08

Update records for network extensions and design changes

Additional connections, changed chamber positions or new crossings are compared with the existing project file.

Necessary supplementary work is documented as a new work step.

Pipe trenches, chambers and crossings

State pipe trenches, chambers and connections with their depths

The specialist assessment needs more than a utility axis. Trench base, working width, retaining structures, chamber excavations, crossing volumes and building entries determine the actual ground intervention.

Each area is assessed according to its area-wide, localised or deep geometry and related to existing technical sources of interference.

Derive investigation geometry from the pipe cross-section and construction phase

Flow and return pipes often share a trench, but spacing, bedding, welding and assembly requirements can create a wide working space. Slopes, retaining structures, dewatering and lateral utilities alter the accessible survey area.

Chambers, building service connections and crossings have their own layouts and depths. Their assessment is based on their actual structure or drilling geometry rather than inferred from a linear trench investigation.

Where construction phases change, it is defined which area can be surveyed before demolition and which can be investigated only after opening the road corridor or during a construction-stage sequence. Necessary investigations and protective measures are planned before preparatory ground interventions.

A district heating trench changes considerably at bends, branches, welding pits, fixed points and crossings. Investigation geometry therefore follows the actual construction cross-section, including retaining structures, working space and, where applicable, a deeper excavation base. Investigation of the pipeline axis alone does not automatically cover these lateral and vertical extensions.

Section and street reference

The road section, construction phase, axis and plan revision provide the common spatial reference.

Transitions between construction phases are documented without gaps.

Pipe trench and working space

Base depth, slopes or retaining structures, utility spacing and lateral assembly areas determine the area-wide investigation geometry.

Depth changes are recorded in the longitudinal section.

Chambers and valves

The layout, base depth, retaining structures, foundations and internal utilities are described as a separate structure.

Deep localised ground interventions receive separate coordinates and investigation depths.

Building service connection and proximity to buildings

The connection trench, building entry, basement wall, foundations and existing utilities limit access and survey feasibility.

The documentation remains related to the volume of ground actually reached.

Crossing and trenchless construction

The launch and reception pits, drilling path, protective pipe and possible positional deviation form a three-dimensional geometry.

Surface surveys are counted only where they cover the relevant volume.

Existing infrastructure and interference zones

Utility bundles, old sewers, reinforcement, tracks, vehicles and structures can obscure survey data.

These areas are mapped. Suitable supplementary methods and survey access are assessed for them.

Select an investigation

Select investigations for the main pipeline and special excavations

Two people with a tablet beside a marked construction area; plans lie in the foreground.

Consider technical survey limitations within the road corridor

Heat networks often run along streets with numerous utilities, previous excavations, fill, foundation remnants and changing surfaces. These installations and ground changes can limit geophysical methods. Surveyable areas, deep localised ground interventions and areas accessible only later are therefore planned separately.

Select suitable methods for technical survey limitations
Two people with a tablet beside a marked construction area; plans lie in the foreground.

Describe building service connections and chamber structures separately

Building service connections, transfer stations, chamber structures and crossings differ from the standard trench. They receive their own area and depth descriptions so that investigation of the linear pipe trench is not inappropriately transferred to larger or deeper excavations.

Determine the investigation for connections and structures
Methods by road and construction section

Which specialist service addresses each volume of ground affected by the heat network

The methods answer different spatial and physical questions. Their selection depends on the suspected hazard, existing utilities, surface, depth and construction phase.

01

Historical aerial photograph analysis

Assesses previous uses and possible suspected areas along the heat network corridor.

It does not provide a technical conclusion about present-day individual objects in the pipe trench.

02

Magnetometry

Detects ferromagnetic anomalies in sufficiently clear, accessible areas.

Utility bundles, vehicles, rails and reinforcement can strongly influence data in urban areas.

03

TDEM

Measures electromagnetic responses from conductive objects and can provide supplementary information in a suitable environment.

Electromagnetic infrastructure, ground conditions and the target object determine usability.

04

Ground-penetrating radar / GPR

Can show layer boundaries, utility structures and discrete reflection areas beneath surfaced ground.

Data coverage at depth and interpretation depend on ground conditions, moisture, coupling and knowledge of existing infrastructure. Reflections do not automatically identify explosive ordnance.

05

Deep-ground and downhole surveys

Investigates defined chambers, drilling paths, piles, retaining structure points and deep building service connections.

The conclusion applies only to the documented point or corridor geometry.

06

Excavation supervision

Where explosive ordnance detection during construction is technically suitable, each working layer is surveyed and evaluated using technical methods. Controlled removal in layers and supplementary visual inspection then follow; these steps are repeated down to the agreed excavation base.

Excavation layers, stopping points, authority to give instructions, communication procedures and documentation are defined in the work instruction before work begins. Merely watching the excavator at work is insufficient.

Specialist responsibility within urban construction

Check the utility plan against investigation results before civil engineering work

Heat networks are built under tight spatial and time constraints. Designers, the specialist company and site management therefore coordinate survey access and investigation dates with traffic management and construction phases.

Each section receives a status that clearly links the plan version, construction phase, depth, method and unresolved areas.

Hand over results for trenches, chambers and connections

FONTANA-EOD relates the suspected hazard and investigation to the specific pipe trench, chamber, connection or crossing area. Neighbouring road areas are not automatically included in the assessment.

Methods are selected according to actual survey feasibility. Dense utility corridors, foundations and traffic influences are identified early and incorporated into the specification.

During construction, changes to the axis, depth, retaining structures or construction phase are recorded. Existing documentation is reused only where it covers the new volume of ground affected.

Unusual findings and interruptions are communicated with the section identifier and responsibility. Site management, network operations and the specialist company thus remain on the same information basis.

The final document describes the area addressed, method limitations and next decision required for heat network construction.

The technical assessment remains tied to the actual geometry even when construction phases change at short notice. If a tie-in is relocated, a chamber enlarged or the trench base deepened, FONTANA-EOD checks before ground intervention whether the documented volume remains sufficient or needs targeted supplementary investigation.

Clarify access and construction phase

Access, demolition condition and traffic management are clarified before survey planning.

Cross-check utility plans

Coordination plans and local conditions are assessed together.

Treat chambers separately

Structures and particular deep locations receive their own investigation and documentation geometries.

Document design changes

Plan revisions and partial handovers remain traceable through identifiers.

Prepare reporting procedures

Work stoppage, communication about finds and local interfaces are defined before work begins.

Use the result for construction

The report and plan show which areas were investigated and which tasks remain unresolved before the next civil engineering step.

Prepare the next construction section

Relate investigations to closure windows and construction conditions

Plan handover of results before the respective earthworks

Urban construction sections are often carried out under traffic, within short closure windows and with commissioning in sections. Before tendering, required investigations, handover of results and stopping points are coordinated with construction phases.

Clarify unresolved areas before the next construction condition

Using this information, FONTANA-EOD defines which areas are investigated when and which documents are still missing. The report shows areas addressed, methodological limitations and the technically required subsequent decision for the next construction condition.

Responsibilities and information procedures

Who manages route planning, traffic phases and communication about finds

District heating projects bring together heat suppliers, the municipality, traffic planning, utility coordination, civil engineering, the specialist company and locally competent authorities. Tasks and information procedures are defined for each construction section.

Project sponsors

Municipal utilities and heat suppliers

Define network expansion, construction sections, the programme, quality requirements and documentation needed.

They provide existing utility and project data and commission the specialist services required.

Design

Route, civil engineering and utility coordination

Translates the heat network into an axis, pipe trench, chambers, connections, crossings and construction phases.

Changes are communicated with the plan revision and their effect on areas already addressed.

Traffic and project management

Site, traffic and interface coordination

Connects explosive ordnance assessment with traffic management, access, changeovers, parallel trades and partial handovers.

Unresolved sections and stopping points remain identifiable in the construction phase plan.

Construction execution

Pipeline and civil engineering contractors

Constructs trenches, chambers, crossings and building service connections according to the agreed plan version.

Unplanned changes to position, depth or retaining structures are reported before ground intervention.

Specialist contractor

FONTANA-EOD

Assesses the suspected hazard and method suitability, carries out the commissioned specialist service and documents the result, limitations and follow-up measures.

The conclusion remains tied to the construction section, volume of ground affected and plan version.

Competent authorities

Local emergency response and explosive ordnance authorities

In Germany, the ordnance disposal services of the federal states and the locally competent authorities carry out hazard-response and find-management duties. Their involvement is established for the project location; outside Germany, local responsibilities apply.

The local public order authority and, where applicable, building control are involved according to their project-specific responsibilities. Conditions and contacts are assigned to the actual district heating sections and structures; reporting procedures are defined before work begins.

From road section to heat network file

Which documents are used in practice during district heating construction

The project documents connect the utility axis, road corridor, chambers, building service connections, construction phases and field services. Each representation remains related to the documented area, chainage and depth range.

Historical evidence, point-specific deep-ground investigations, supervised earthworks and findings are maintained in a common project file without mixing their different limits of conclusions.

Two people discussing plans at a table beside a vehicle on a construction site.

Section report for designers and network operations

The final documents bring together the plan version, investigated areas, uninvestigated zones and technically required next steps for heat network expansion.

Document section reports and handover
Four people in orange high-visibility vests in front of two excavators on a construction site.
Person with a yellow survey cart on a footpath in front of a hedge.
Identify the project location

Assign the main pipeline, branches and excavations unambiguously within the location

Illustrated map of Germany with location markers on a construction site.

Identify the site and applicable requirements

District heating projects often run through densely occupied road corridors. The main pipeline, branches, building service connections, chambers, fixed points and excavations have different widths and depths. Each actual volume of ground affected is therefore assessed with its construction condition, existing utilities and intended construction sequence, rather than the street as a whole.

State the project location, road section, chainage and construction section. Existing requirements and earlier investigations are assigned precisely to the affected volumes of ground.

Use results correctly

Preserve investigation limits when the heat network changes

Compare chamber and fixed-point geometries with the report

Chambers and fixed points may extend wider or deeper than the standard trench. Their positions and dimensions are compared with the documented investigation volume; supplementary tasks remain assigned to the respective structure.

Check evidence against the intervention

Consider temporary arrangements and new connection positions

Temporary pipelines or relocated building service connections may create additional ground interventions. Record them in the current plan and assess before execution which existing results actually cover the changed volume of ground.

Explore the technical principles

Technical information

Utility and energy projects: brochure

Utility routes, substations and energy installations place different demands on ordnance assessment. The brochure shows the design information needed and how investigation, construction sequence and documentation fit together.

1 / 8
Utility and energy projects: brochure – page 1

German · 8 pages

Common project questions

What should be clarified before pipe trenches, chambers and building service connections

Before each construction section, municipal utilities, designers and civil engineering teams need information on investigated areas and outstanding tasks. The road section, existing utilities, depth, construction phase and achievable survey quality remain decisive.

When should a district heating route undergo an explosive ordnance assessment?

The assessment should start once a sufficiently defined route corridor and the main construction methods are known. Before ground investigations, pipe trenches, chambers, crossings and building entries, the specific volumes of ground affected must be established by position, depth and construction phase.

Why is a general assessment of the road section insufficient?

Pipe trenches, chamber structures, building service connections, launch and reception pits and temporary working areas have different layouts and depths. For each area, it is assessed whether existing investigations cover its area and depth and which supplementary investigations may be needed. Results are brought together in the same project file.

How do dense existing utility networks affect survey work?

Metal utilities, cables, ducts, reinforcement and vehicles can obscure survey data or restrict access. Known installations are incorporated into planning. Zones that cannot be adequately evaluated are identified on the plan. Suitable supplementary methods and survey access are assessed for these zones. Explosive ordnance detection during construction is considered only where technically suitable.

What should you do if a suspicious object is found?

If an unexpected suspicious object is found, stop work. Do not touch, move or uncover it further. Leave the immediate area and warn others without putting yourself at risk. In Germany, notify the police on 110; outside Germany, use the local emergency reporting procedure. The competent authorities determine what happens next; a project enquiry does not replace reporting the find.

When is a deep-ground survey needed?

Deep chambers, jacking and HDD corridors, piles, retaining structure points or other localised ground interventions may extend beyond the depth range covered by near-surface investigation. It is then assessed which supplementary investigation can cover the planned volume of ground to the required depth. Method selection considers the target object, ground conditions, interference and access.

When may ordnance specialist supervision of excavation be considered?

For areas that have not been fully investigated in advance, the technical suitability of explosive ordnance detection during construction is assessed. Each working layer is technically surveyed and assessed before controlled removal in layers with supplementary visual inspection follows. These steps are repeated until the agreed excavation base is reached. Excavation layers, instruction procedures, stopping points and documentation are established before work begins. Areas not covered remain unresolved.

What documents are needed for the initial assessment?

Required documents include the most current available route and coordination plans, construction sections, pipe trench cross-section, chambers, crossings, building service connections, depths of intervention, construction phases, existing utilities, historical assessments, ground investigation data and the documentation desired.

Information and requirements from authorities are supplied with their date, complete appendices and geographical scope. In Germany, the competent ordnance disposal service, local public-order authority and, where relevant, building-control authority are identified for the project location; outside Germany, local responsibilities apply.

What determines effort and cost?

Influencing factors include the length and number of construction sections, depth and size of chambers, utility density, surface, access, traffic phases, methods required, extent of evaluation and documentation requirements. Clear quantities and geometries enable reliable pricing.

Documents for specialist assessment

What information is needed for pipe trenches, chambers and construction phases

An initial enquiry may be based on preliminary or coordination design. Streets, priority construction sections, typical trench depth, special structures and the decision date should be identifiable.

For network expansion over several years, clear section and plan naming is particularly important so that later connections and construction phases can build on the existing status.

Information on utility coordination, explosive ordnance information requests, road construction, retaining structure type, planned dewatering and the times when individual sections are actually accessible for survey work or supervised investigation is also useful.

Route, road corridor and plan version

Send site and coordination plans with the axis, construction sections, road sides, land parcels and plan revision.

Mark traffic phases, exclusion areas and route options still unresolved.

Where several lots are involved, the intended section identifier should be identifiable.

Pipe trenches, chambers and crossings

Describe the standard cross-section, base depth, slopes or retaining structures, chambers, building service connections, pipe jacking and HDD areas.

State layouts, design depths, launch and reception pits and ground investigation points.

Dewatering and temporary pipelines are considered as separate construction conditions.

Existing infrastructure, construction times and purpose of the documentation

Attach utility plans, historical documents, ground investigation data, earlier reports and known interference zones.

State construction times, traffic management, changeovers, data formats and handover dates.

Identify whether documentation is needed for planning, procurement, site management or network operations.

For initial technical assessment

A site plan, route description, trench depth, chamber and crossing information, planned period and existing suspected hazard documents often suffice at the outset.

Using your documents, FONTANA-EOD assesses which investigations are needed for the individual construction sections.

For pricing, section quantities, access, construction conditions, point lists, data formats and handovers to be provided are then refined.

For reliable pricing, construction sections, the standard cross-section, chamber depths, tie-ins, building service connections, crossings and planned traffic phases should be separately identifiable. If construction plans are not yet available, the development corridor and priority sections can first undergo specialist assessment.

Route and construction phase

Road section, axis, plan revision, traffic phase and construction period.

Civil engineering geometry

Pipe trench, chambers, building service connections, crossings and maximum depth.

Existing surroundings

Utilities, sewers, foundations, surface, retaining structures and access.

Documentation objective

Document for planning, procurement, site management, network operations or the project file.

Project enquiry

Have your project assessed

Whether historical aerial photograph analysis, explosive ordnance surveying, surface surveying using GPR, magnetometry or TDEM, deep-ground surveys, downhole surveys, excavation supervision, area clearance or ordnance recovery is needed depends on the location, ground disturbance, depth, ground and existing documents. An early ordnance assessment provides clarity for tendering, programming, occupational safety and construction.

FONTANA-EOD combines its Section 7 SprengG licence, specialists holding Section 20 SprengG certificates of competence, suitable survey and clearance methods, and traceable documentation. Send the site plan, depth of ground disturbance, construction phase and existing documents for an initial technical assessment.